ASHRAE LO-09-046-2009 CCLEP Reduces Energy Consumption by More than 50% for a Luxury Shopping Mall《CCLEP为高档购物中心降低至少50%能耗》.pdf
《ASHRAE LO-09-046-2009 CCLEP Reduces Energy Consumption by More than 50% for a Luxury Shopping Mall《CCLEP为高档购物中心降低至少50%能耗》.pdf》由会员分享,可在线阅读,更多相关《ASHRAE LO-09-046-2009 CCLEP Reduces Energy Consumption by More than 50% for a Luxury Shopping Mall《CCLEP为高档购物中心降低至少50%能耗》.pdf(10页珍藏版)》请在麦多课文档分享上搜索。
1、492 2009 ASHRAEABSTRACTThe Continuous Commissioning Leading Project (CCLEP) process is an ongoing process to apply system opti-mization theory and advanced technologies in commercial retrofit projects. The CCLEP process was applied to a luxury shopping mall and office building. The case study buildi
2、ng has ten single fan dual-duct VAV AHUs, 123 dual-duct pneumatic controlled pressure independent terminal boxes, and a central heating and cooling plant. Major retrofit efforts include upgrading pneumatic to DDC controls for all AHUs, installing main hot deck dampers, replacing the boiler, installi
3、ng VFD on fans and pumps, and installing Fan Airflow Stations (FAS) and Pump Waterflow Stations (PWS). This paper presents the opti-mal control strategies, which include main hot deck damper control, supply fan control integrated with FAS, return fan control, optimal control for terminal boxes, chil
4、led water temperature and chilled water pump speed control, hot water temperature and hot water pump speed control. Boiler size was optimized at the time of replacement while the performance was measured and verified. The measured hourly utility data after CCLEP show that annual HVAC electricity con
5、sumption is reduced by 56% and gas use is reduced by 36%. INTRODUCTIONThe Continuous Commissioning Leading Project (CCLEP) process is an ongoing process to apply system opti-mization theory and advanced technologies to commercial retrofit projects. It was developed by Liu et al (2006) through a U.S.
6、 Department of Energy grant to the University of Nebraska and the Omaha Public Power District (OPPD) for continuous commissioning applications in commercial retro-fit projects. The CCLEP process, procedures and seven case study results have already been presented (Liu et al 2006).CCLEP was applied t
7、o a luxury shopping mall and office building. The case study building has ten single fan dual-duct VAV AHUs, 123 dual-duct pneumatic controller pressure independent terminal boxes, and a central heating and cooling plant. Major retrofit efforts include upgrading pneumatic to DDC controls for all AHU
8、s, installing main hot deck dampers, replacing the boiler, installing VFD on fans and pumps, and installing Fan Airflow Stations (FAS) and Pump Waterflow Stations (PWS). This paper presents the optimal control strat-egies, which include main hot deck damper control, supply fan control integrated wit
9、h FAS, return fan control, optimal control for terminal boxes, chilled water temperature and chilled water pump speed control, hot water temperature and hot water pump control. The measured hourly utility data after CCLEP show that annual HVAC electricity consumption is reduced by 56% and gas use is
10、 reduced by 36%. This paper demonstrates the energy savings and system performance improvement through retrofits and optimal system control. This paper will present the case study building information, CCLEP major retrofits, CCLEP optimal control strategies, CCLEP results and conclusions. BUILDING I
11、NFORMATIONThe case study building is located in Omaha, NE. The two-story shopping mall and office building was built in 1975 with a total floor area of 231,000 ft2(21,461 m2). There are multiple stores owned by different owners. The building is occupied from Monday to Sunday each week while the occu
12、-pancy schedule is different from store to store. CCLEP Reduces Energy Consumption by More than 50% for a Luxury Shopping MallL. Wu M. Liu, PhD, PE X. Pang G. Wang, PhD, PEStudent Member ASHRAE Member ASHRAE Student Member ASHRAE Member ASHRAEJ. Wang, PE T.G. LewisMember ASHRAE Member ASHRAEL. Wu an
13、d X. Pang are doctoral students and research assistants, G. Wang is a research associate professor, and M. Liu is a professor and chair of the graduate committee in the Department of Architectural Engineering, University of NebraskaLincoln, Linclon, NE. J. Wang is the manager and T.G. Lewis is a sen
14、ior technical analysis engineer of Commercial & Industrial Solutions at Omaha Public Power District, Omaha, NE.LO-09-046 2009, American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. (www.ashrae.org). Published in ASHRAE Transactions 2009, vol. 115, part 2. For personal use o
15、nly. Additional reproduction, distribution, or transmission in either print or digital form is not permitted without ASHRAEs prior written permission.ASHRAE Transactions 493A total of 123 dual-duct CAV and VAV pressure indepen-dent terminal boxes serve the conditioned area. The VAV box dampers are c
16、ontrolled by pneumatic controllers with inputs from the pneumatic thermostats.There are ten single fan dual-duct variable air volume (VAV) AHUs with inlet guide vanes. The design airflow is 45,000 CFM (76,451 m3/h) for both supply fan and return fan. For each AHU, the inlet guide vane was locked at
17、a fixed posi-tion due to lack of control. Thus, the air handling units were operated as constant air volume systems. These AHUs supply conditioned air to the entire building. Each AHU has a differ-ent operation schedule based on the occupied hours of the serving area. The AHU and central plants are
18、shut down when the building is unoccupied. The control valves for cooling coils and heating coils of AHUs are all three-way valves.The central plant consists of chilled water and hot water systems. The chilled water system includes two water cooled centrifugal chillers, 770 ton (2,462 kW) for each,
19、three constant speed primary chilled water pumps, four secondary chilled water pumps, one cooling tower with two constant speed fans, and three constant speed condensing water pumps. The chilled waterside has two parallel circuits with two secondary pumps for each circuit. Circuit 1 serves the cooli
20、ng coils of AHU1 to AHU4, and Circuit 2 serves the cooling coils of AHU5 to AHU10. Each circuit has two secondary pumps in parallel. The hot water system included three gas-fired steam boilers, 13.4 MMBtu/h (3.9 MW) for each, three constant speed circulation pumps and three constant speed secondary
21、pumps. The footprint of the hot water system was 5,000 ft2(464 m2). The central plant was not only serving this building but also an adjacent building for which the service was cut off years ago before the CCLEP. There was an Energy Management Computer System (EMCS) for the central plant only. The p
22、neumatic control of AHUs limited the capability of implementing advanced control.CCLEP MAJOR EVALUATION RESULTS The typical CCLEP process consists of four phases: a walk-through phase (Phase I), a detailed energy audit phase (Phase II), an implementation phase (Phase III) and a follow-up phase (Phas
23、e IV). In Phase I and II evaluation process, the building and facility performance are audited, the comfort and energy consumption issues are identified and advanced tech-nologies are developed as solutions based on comprehensive measurement and evaluation. The work scope is clearly defined. In Phas
24、e III and IV, the implementation and verifica-tion phase, mechanical design requirement and control upgrade specifications are developed. After defining the performance baselines, optimal control strategies are devel-oped and implemented. Comfort improvements and energy savings are identified, docum
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASHRAELO090462009CCLEPREDUCESENERGYCONSUMPTIONBYMORETHAN50FORALUXURYSHOPPINGMALLCCLEP 高档 购物中心 降低 至少 50

链接地址:http://www.mydoc123.com/p-455332.html