REG NASA-LLIS-0836-2000 Lessons Learned Solid Rocket Booster (SRB) Refurbishment Practices.pdf
《REG NASA-LLIS-0836-2000 Lessons Learned Solid Rocket Booster (SRB) Refurbishment Practices.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-0836-2000 Lessons Learned Solid Rocket Booster (SRB) Refurbishment Practices.pdf(8页珍藏版)》请在麦多课文档分享上搜索。
1、Best Practices Entry: Best Practice Info:a71 Committee Approval Date: 2000-04-19a71 Center Point of Contact: MSFCa71 Submitted by: Wil HarkinsSubject: Solid Rocket Booster (SRB) Refurbishment Practices Practice: Engage in refurbishment activities to rebuild and prepare for reuse of the Solid Rocket
2、Boosters (SRBs) after each Space Shuttle Orbiter launch. These refurbishment activities include: (1) inspection, (2) reworking of anomalies to specification, (3) material review board (MRB) acceptance or scrapping, (4) cleaning, (5) corrosion protection and prevention, (6) scheduled part replacement
3、, (7) test and checkout, and (8) preparation for storage or return to flight buildup.Programs that Certify Usage: This practice has been used on Space Shuttle Solid Rocket Booster (SRB), Space Shuttle Solid Rocket Motor (SRM).Center to Contact for Information: MSFCImplementation Method: Benefit:This
4、 Lesson Learned is based on Maintainability Technique number OPS-01 from NASA Technical Memorandum 4628, Recommended Techniques for Effective Maintainability.Implementation Method:Refurbishment of SRB components is cost effective and conserves resources. This allows for reuse Provided by IHSNot for
5、ResaleNo reproduction or networking permitted without license from IHS-,-,-of SRBs, thus saving money for the program versus building new SRBs for each launch.Solid Rocket Booster (SRB) Refurbishment encompasses the activities required to return the reusable SRB component to a flightworthy condition
6、 after SRB ignition, liftoff, and flight; separation from the external tank; descent (free fall and parachute); ocean impact; and retrieval. When the decision was made to recover and reuse the SRB hardware, a design team was organized to formulate the maintainability criteria for a reusable booster.
7、 The SRB Flow Chart for Maintainability is shown in Figure 1. The maintainability design team produced the Solid Rocket Booster Maintainability Design Criteria Document (reference 1), a document that was used by designers as they conceived each design feature, performed the necessary tradeoffs of th
8、e design parameters, and made other design and product engineering decisions. The design team included maintainability as a design goal and incorporated the desired maintainability features into components of the end item throughout the design process. Maintainability factors that were considered du
9、ring the design of the SRB are shown in Table 1.refer to D descriptionD Figure 1. SRB Flow Chart for Maintainability 1. Accessibility2. Commonality of Fasteners3. Electrical Subsystem Installation and Removal4. Thrust Vector Control (TVC) Subsystem Installation and Removal5. Markings and Color Codin
10、g6. Unitization of Subsystems7. Irreversibility of Connectors8. Tool and Equipment Design9. Spares ProvisioningTable 1. SRB Maintainability Factors Design Process ConsiderationsProvided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Table 2 lists typical mai
11、ntenance actions that were considered during the design process. The SRB was designed to withstand launch, water impact, and towback environments, incorporating the capability of 10 flights for the parachutes; 20 flights for electrical/electronic components, Thrust Vector Control (TVC) components, a
12、nd SRM components; and 40 flights for the structures. SRB structures are typically welded and/or mechanically fastened aluminum except for the external tank attach ring, which is mechanically fastened steel. All aluminum structural assemblies are first painted and then coated with an ablative insula
13、tion. The SRM segments are forged D6AC steel. All structural components are cleaned and/or alodined as appropriate, before being primed and top coated with paint. The mechanically fastened aluminum and steel structural components are designed to be protected from salt water intrusion by applying sea
14、lant between adjoining surfaces, installing the fasteners with sealant, torquing the fasteners, and applying a fillet of sealant along the edge of brackets where they join the main structure. The electronic/electrical components exposed to salt water are sealed, and the external surfaces of these co
15、mponents are painted. The TVC hydraulic system is a closed-loop system that does not permit the intrusion of sea water. The SRM segments external surfaces are protected with an epoxy paint finish, and the internal surfaces are protected by the propellant insulator that is bonded to the inside surfac
16、es of the SRM segments. Areas not protected with paint or bonded-on insulation are protected with a water-repellent grease.1. Inspection2. Troubleshooting3. Calibration and Adjustment4. Repair5. VerificationTable 2. Maintenance Actions Specific ImprovementsTypical areas of the SRB that have been red
17、esigned or modified as a result of trouble areas found during recovery and refurbishment are discussed below:1. Galvanic corrosion occurred in the aft skirt of the first few SRBs recovered. To prevent this from recurring the design team added a zinc coating to selected metal components, and bolted a
18、nodes (Zinc bars) to some components of the TVC system.2. The aft skirts of the first few SRBs experienced water impact damage. The corrective action included the addition of gusset reinforcements to the structural rings. Foam was sprayed on the interior of the aft skirt to protect the reinforcement
19、 rings and the TVC components. Impact force with the water was reduced by increasing the diameter of the main parachutes from 115 feet to 136 feet. The larger parachutes decreased the SRBs water impact velocity from 88 ft/sec to 75.5 ft/sec (60 mph to 51.5 mph, respectively).3. During initial teardo
20、wn and inspection, water and corrosion were found between the mating Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-surfaces of structural members. To correct this problem, the sealant application specifications were modified to require the sealant
21、to be applied to both surfaces before joining.4. To eliminate potential water entry into the forward skirt, the following areas were modified or redesigned:1. The aft seal on the forward skirt was changed from a rectangular to a “D“ configuration to allow better contact between the forward skirt and
22、 the forward dome of the SRM.2. A fillet of sealant was added between the access door and the surrounding structure after final close-out of the forward skirt.3. Sealant was added to the mating surfaces and the installation bolts of the separation nut housing for the main parachute attach fittings.6
23、. The following practices improved maintainability, parachute deployment, and parachute inflation:1. To avoid abrasive damage that occurred during main parachute deployment, foam and ablative material were added to portions of the frustum and the main parachute support structure.2. To avoid damage t
24、o the parachutes during deployment, the parachutes are now packed in a circular pattern rather than the previous zig-zag pattern.3. The opening at the top of the main parachute canopy was decreased in diameter to allow quicker inflation of the parachute.8. After every flight electronic components we
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS08362000LESSONSLEARNEDSOLIDROCKETBOOSTERSRBREFURBISHMENTPRACTICESPDF

链接地址:http://www.mydoc123.com/p-1018482.html