Advanced Corporate FinanceCapital Budgeting .ppt
《Advanced Corporate FinanceCapital Budgeting .ppt》由会员分享,可在线阅读,更多相关《Advanced Corporate FinanceCapital Budgeting .ppt(37页珍藏版)》请在麦多课文档分享上搜索。
1、Advanced Corporate Finance Capital Budgeting Complications Finance 7330 Lecture 2.1 Ronald F. Singer,Making Investment Decisions,We have stated that we want the firm to take all projects that generate positive NPV and reject all projects that have a negative NPV. Capital budgeting complications aris
2、e when you cannot, either physically or financially undertake all positive NPV projects. Then we have to devise methods of choosing between alternative positive NPV projects.,Mutually Exclusive Projects,IF, AMONG A NUMBER OF PROJECTS, THE FIRM CAN ONLY CHOOSE ONE, THEN THE PROJECTS ARE SAID TO BE MU
3、TUALLY EXCLUSIVE. For example: Suppose you have the choice of modifying an existing machine, or replacing it with a brand new one. You could not do both and produce the desired amount of output. Thus, these projects are mutually exclusive. Given the cash flows below, which of these projects do you c
4、hoose?,Mutually Exclusive Projects,Time Modify Replace Difference0 -100,000 -250,000 -150,0001 105,000 130,000 25,0002 49,000 253,500 204,500IRR?,Mutually Exclusive Projects,Time Modify Replace Difference0 -100,000 -250,000 -150,0001 105,000 130,000 25,0002 49,000 253,500 204,500IRR .40 .30 .25Assum
5、e the hurdle rate is 10%,Mutually Exclusive Projects,Time Modify Replace Difference0 -100,000 -250,000 -150,0001 105,000 130,000 25,0002 49,000 253,500 204,500IRR .40 .30 .25NPV( 10%) 36,000 77,700 41,700Notice the conflict that can exist between NPV and IRR.,EXAMPLES OF CAPITAL BUDGETING COMPLICATI
6、ONS,1. Optimal Timing 2. Long versus Short Life 3. Replacement Problem 4. Excess Capacity 5. Peak Load Problem (Fluctuating Load) 6. Capital Constraints,EXAMPLES OF CAPITAL BUDGETING COMPLICATIONS,These Capital Budgeting Complications will stop the Firm from taking all possible positive NPV PROJECTS
7、. Thus, the firm is faced with the choice of two possibilities.Remember: Goal is still Max NPV of all possibilities,EXAMPLES OF CAPITAL BUDGETING COMPLICATIONS,We can divide these problems into three separate classes, each with their own method of solutions. (1) Once and for all deal.Choose the one
8、alternative having the highest NPV.(2) Repetitive Deal. Choose the one alternative having the highest equivalent annual cash flow.(3) Capital Budgeting ConstraintChoose the combination of projects having the highest NET PRESENT VALUE.,Once and For all Deals,INVESTMENT TIMING:When is the optimal time
9、 to take on an investment project? Consider T possible times, where, t = 1, .T. Then each “starting time“ can be considered a different project in a set of T mutually exclusive projects. Then find that t which Max: NPV(t) (1+r)t,Once and For all Deals,Example You are in the highly competitive area o
10、f producing laundry soap and detergents. You have a new product which you feel does a superior job in washing clothes, but you anticipate that the product will have difficulty being accepted by the consumer. Thus you expect that if you introduce the product now, you will have to suffer a few years o
11、f losses until the product is accepted by the consumer. A competitor is about to come out with a similar product. You feel that if you allow your competitor to come out with the product first, you can benefit from the time he spends acclimating your potential customers. However, you will then be giv
12、ing up your competitive edge.,Once and For all Deals,The initial investment in the product has already been spent, is a sunk cost and can be ignored for this problem. The anticipated life of the productive process is ten years from the time the product is first produced. Thereafter, there will be so
13、 much competition that any new investment in this product will have a zero NPV. The discount rate is 15%.,Once and For all Deals,Expected cash flows are:CASH FLOW ($ MILLIONS )year (fromstart of project 1 2 3 4-10 _immediately -4 -3 -2 20If introduced after one year -1 1 3.5 19.5If introduced aftert
14、wo years 0 2 4 19WHAT SHOULD YOU DO?,Once and For all Deals,NPV(0) (Introduced Immediately) is: 47.649 millionNPV(1) (Introduced in one years time) is: 55.531 millionNPV(2) (Introduced in two years time) is: 56.118 millionWHICH ONE OF THESE THREE OPTIONS SHOULD BE TAKEN?47.649 55.531 56.118 | | |0 1
15、 2 3 4 5 Calculate NPV from time 0.,Once and For all Deals,ShortcutCalculate the annualized rate of change of NPV. If delaying causes the NPV to increase by more than the discount rate, the project should be delayed. If not, the project should not be delayed.,Once and For all Deals,CautionThis metho
16、d assumes that the project cannot be reproduced at a positive NPV after the initial life of the project. Otherwise, you have to also account for the fact that the project that is started earlier can also be reproduced earlier. In that case, the alternatives look like:START IMMEDIATELY 0 10 20 30 _ON
17、E YEAR DELAY 0 1 11 21 31_ THIS LEADS TO THE SECOND CLASS OF PROBLEMS:,Repetitive Deals,Mutually exclusive projects with different Starting Times Mutually exclusive projects with different Economic Lives Replacement Decision Management of Excess of Peak Capacity,examples: Alternatives with Different
18、 Lives3 Little PigsBrick vs. Wood vs. Straw.,Alternatives with Different Lives,Example: YOU HAVE THE OPTION OF UNDERTAKING ONE OF TWO DIFFERENT WAYS OF ACHIEVING SOME GOAL. WHICH ONE SHOULD YOU TAKE? (A) A Bridge costing 5M lasts 15 years(B) A Bridge costing 4M lasts 10 yearsBoth generate $1 Million
19、 in net revenues per year. Let the Discount rate = 12% for each alternative. NPV (A) = $1.81 MillionNPV (B) = $1.65 Million,Alternatives with Different Lives,Conceptually The NPV rule would say, take the project with the highest Net Present Value. This may be wrong.Consider what happens after ten ye
20、ars. In particular by year 30.,Alternatives with Different Lives,A 1.81 1.81 1.81._0 5 10 15 20 25 30 35 B 1.65 1.65 1.65 1.65_0 5 10 15 20 25 30 35PV(A) over infinite horizon:PV(A) = 1.81 + 1.81 + 1.81 + = 2,214,900 (1.12)15 (1.1)30 PV(B) over infinite horizon:PV(B) = 1.65 + 1.65_ + 1.65_ + = 2,435
21、,700 (1.12)10 (1.12)20,Alternatives with Different Lives,ALTERNATIVE EQUIVALENT ANNUAL CASH FLOW (EACF) or (NUS in Hewlett Packard)Note: BMA talk about Equivalent Annual Cost, this is a more general concept. Consider the annuity having the same NPV and life of the project.EACF (A) = That annuity hav
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
2000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ADVANCEDCORPORATEFINANCECAPITALBUDGETINGPPT
