REG NASA-LLIS-1414-2004 Lessons Learned Acquisition Philosophy and Mechanism.pdf
《REG NASA-LLIS-1414-2004 Lessons Learned Acquisition Philosophy and Mechanism.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1414-2004 Lessons Learned Acquisition Philosophy and Mechanism.pdf(5页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1414Lesson Info:a71 Lesson Number: 1414a71 Lesson Date: 2004-01-01a71 Submitting Organization: ARCa71 Submitted by: Donald R. MendozaSubject: Acquisition Philosophy and Mechanism Abstract: A “Fly-off” type of procurement using a relatively small Source Evaluation Board (SEB) c
2、an minimize the time to assess, award, and implement a contract. However, in order to minimize the Governments risk under this process, the SEB must leverage enough expertise (in “ex-official” status, if necessary, to fill any knowledge gaps the small SEB might have) to ensure all the Contractors bu
3、siness practices are adequate and reflect a system that provides sufficient insight/oversight to build the required “hands-off” Government/Contractor relationship after contract award.Description of Driving Event: Due to several constraints, schedule being the most significant, the Project implement
4、ed a procurement mechanism that was aimed at minimizing the time to assess and select the Contractor. This procurement mechanism consisted of three phases. The first phase was geared around having, the three “best” small business companies proficient in composite blade design and construction; enter
5、 into a “paper fly-off”. The second phase was aimed at down selecting one of the three designs and manufacturing proposals while the last phase was a contract award to manufacture and deliver the winning design. This approach was chosen to minimize the Governments risk such that the Contractor award
6、ed the work, under this relatively short time frame, would have a high probability of successfully meeting the Governments requirements. Thus, the Government placed a high priority on upfront screening and studies to enable its own participation to transition into an oversight mode once the contract
7、 was awarded. The idea was to build a SEB that was small yet complete with regard to the expertise required to assess both the technical and programmatic areas of each proposal. Then, key SEB individuals were transitioned into the Project after the award was made such that the entire three-phase pro
8、curement cycle was seamless and the one contractor chosen to complete the work would be able to move from design to manufacture with little interruption. While this approach allowed the SEB to meet its schedule constraints, it also exposed several Provided by IHSNot for ResaleNo reproduction or netw
9、orking permitted without license from IHS-,-,-opportunities for continuous improvement (as successfully demonstrated during the Projects implementation) such that the mechanisms next application could build on the success of this experience. These areas for improvement are summarized in the followin
10、g Lessons Learned and Recommendations. References: none Additional Key Words: Fly-off procurement, SEB, expert ex-official, timely & efficient. Lesson(s) Learned: In order to use a “fly-off” type of procurement to minimize the time to assess, award, and implement a contract while ensuring the Govern
11、ments risk is minimized, the following issues should be considered. 1. While it can improve efficiency, a small selection team (SEB) may not be adequately effective in assessing all technical and programmatic areas.2. Any technical or programmatic areas not sufficiently addressed during procurement
12、may increase the Governments risk during contract implementation. This is especially true in instances where an originally selected system design is found to be inadequate and in need of a re-design (in the case of the Project in question, new analytical tools and techniques available after Contract
13、 award helped to identify new risks and needed design improvements). While the Government is responsible to identify inadequacies at any and all times during the project life cycle, it must make every effort to completely remove itself from the Contractors design process. Any participation by the Go
14、vernment in the design undermines the philosophy of placing the risk (via ownership of design) on the Contractor and exposes the Government to a higher level of risk. The Government must be cognizant of this immigration of risk when it elects to participate in a design process, and must balance the
15、risk of effectively acquiring ownership of the design against other risks inherent in the situation or migrating to it.3. Since the procurements goal is to minimize the time from start to finish, part of it its philosophy is to instill efficiency into the Contractor-Government roles and relationship
16、s. Thus, it becomes paramount during the selection process to ensure that the Contractors processes, procedures, and tools are adequate (as based on some established criteria such as ISO 9001 and/or CMMI) to allow the Government to take a “hands-off” approach during implementation. Also, any criteri
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS14142004LESSONSLEARNEDACQUISITIONPHILOSOPHYANDMECHANISMPDF

链接地址:http://www.mydoc123.com/p-1019053.html