《ASTM A979 A979M-2003(2009) Standard Specification for Concrete Pavements and Linings Installed in Corrugated Steel Structures in the Field《现场用波纹钢结构件中填装的混凝土铺料和衬料的标准规范》.pdf》由会员分享,可在线阅读,更多相关《ASTM A979 A979M-2003(2009) Standard Specification for Concrete Pavements and Linings Installed in Corrugated Steel Structures in the Field《现场用波纹钢结构件中填装的混凝土铺料和衬料的标准规范》.pdf(4页珍藏版)》请在麦多课文档分享上搜索。
1、Designation: A979/A979M 03 (Reapproved 2009)Standard Specification forConcrete Pavements and Linings Installed in CorrugatedSteel Structures in the Field1This standard is issued under the fixed designation A979/A979M; the number immediately following the designation indicates the yearof original ado
2、ption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval.A superscript epsilon () indicates an editorial change since the last revision or reapproval.1. Scope1.1 This specification covers the minimum material require-ments and descri
3、bes the procedures for installing concretepavements and linings in corrugated steel pipes and structuralplate structures in the field. Specific designs with additional orgreater requirements shall be detailed in the contract docu-ments. This specification is applicable to paving or lining newpipes a
4、nd for rehabilitating existing structures. The pipe to bepaved or lined is described in Specifications A760/A760M,A761/A761M, and A762/A762M.1.2 This specification covers pipes 48 in. 1 200 mm andlarger for pavements and 24 in. 600 mm and larger for fulllinings.1.3 New pipes are to be designed in ac
5、cordance withPractice A796/A796M and installed in accordance with Prac-tice A798/A798M for factory-made pipes and Practice A807/A807M for structural plate structures. Structures to be reha-bilitated shall be structurally stable.1.4 Pipes with plant installed concrete pavements and lin-ings are cover
6、ed under Specification A849.1.5 This specification is applicable to product in eitherinch/pound units as A979 or in SI units as A979M. Inch/poundunits and SI units are not necessarily equivalent. SI units areshown in brackets in the text for clarity, but they are theapplicable values when materials
7、are ordered to A979M.1.6 This standard may involve hazardous materials, opera-tions and equipment. The standard does not purport to addressall of the safety concerns, if any, associated with its use. It isthe responsibility of the user of this standard to establishappropriate safety and health pract
8、ices and determine theapplicability of regulatory limitations prior to use.2. Referenced Documents2.1 ASTM Standards:2A185/A185M Specification for Steel Welded Wire Rein-forcement, Plain, for ConcreteA615/A615M Specification for Deformed and PlainCarbon-Steel Bars for Concrete ReinforcementA760/A760
9、M Specification for Corrugated Steel Pipe,Metallic-Coated for Sewers and DrainsA761/A761M Specification for Corrugated Steel StructuralPlate, Zinc-Coated, for Field-Bolted Pipe, Pipe-Arches,and ArchesA762/A762M Specification for Corrugated Steel Pipe,Polymer Precoated for Sewers and DrainsA796/A796M
10、 Practice for Structural Design of CorrugatedSteel Pipe, Pipe-Arches, and Arches for Storm and Sani-tary Sewers and Other Buried ApplicationsA798/A798M Practice for Installing Factory-Made Corru-gated Steel Pipe for Sewers and Other ApplicationsA807/A807M Practice for Installing Corrugated SteelStru
11、ctural Plate Pipe for Sewers and Other ApplicationsA849 Specification for Post-Applied Coatings, Pavings, andLinings for Corrugated Steel Sewer and Drainage PipeA902 Terminology Relating to Metallic Coated Steel Prod-uctsC31/C31M Practice for Making and Curing Concrete TestSpecimens in the FieldC33
12、Specification for Concrete AggregatesC39/C39M Test Method for Compressive Strength of Cy-lindrical Concrete SpecimensC150 Specification for Portland CementC309 Specification for Liquid Membrane-Forming Com-pounds for Curing ConcreteC595 Specification for Blended Hydraulic CementsC618 Specification f
13、or Coal Fly Ash and Raw or CalcinedNatural Pozzolan for Use in Concrete1This specification is under the jurisdiction of ASTM Committee A05 onMetallic-Coated Iron and Steel Products and is the direct responsibility ofSubcommittee A05.17 on Corrugated Steel Pipe Specifications.Current edition approved
14、 Nov. 1, 2009. Published January 2010. Originallyapproved in 1997. Last previous edition approved in 2003 as A979/A979M - 03.DOI: 10.1520/A0979_A0979M-03R09.2For referenced ASTM standards, visit the ASTM website, www.astm.org, orcontact ASTM Customer Service at serviceastm.org. For Annual Book of AS
15、TMStandards volume information, refer to the standards Document Summary page onthe ASTM website.1Copyright ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959, United States.D3405 Specification for Joint Sealants, Hot-Applied, forConcrete and Asphalt Pavements32.
16、2 American Water Works Association Standards:AWWAC602 Standards for Cement-Mortar Lining of WaterPipelines-4 in. (100 mm) and larger-in place43. Terminology3.1 DefinitionsFor definitions of general terms used inthis specification, see Terminology A902.3.2 Definitions of Terms Specific to This Standa
17、rd:3.2.1 contractor, nthe installer or applicator of the con-crete pavement of lining.3.2.2 engineer, nthe designer of the work and its details.3.2.3 fabricator, nthe producer of the pipe.3.2.4 lining, nfor corrugated metal pipe, a layer of non-metallic material applied uniformly to the interior of
18、a fabri-cated pipe, of sufficient thickness to fill and cover the corru-gations.3.2.5 pavement, nfor corrugated metal pipe, a liningapplied only to a portion of the interior circumference, usuallylocated in the lower portion (as the pipe is installed).3.2.6 purchaser, nthe person or agency purchasin
19、g thefinished product.4. Requirements4.1 Concrete PavementsConcrete pavements shall beplaced after the pipe has been installed. For new pipes,pavements shall be placed after the pipe is backfilled to finalgrade. If the depth of fill exceeds four feet, the pavement maybe placed after four feet of bac
20、kfill over the pipe has beenplaced. If the paving is placed prior to completion of the entirefill, any gaps between the pipe and pavement shall be filledwith heated joint sealer conforming to Specification D3405.Special pavement designs, which exceed the minimum require-ments of this specification,
21、shall be detailed in the job plansand specifications. In lieu of special designs, pavements shallextend over the area to be protected or rehabilitated. Invertpavements shall cover a minimum of the bottom 25 % of around pipes circumference and 40 % of the circumference ofa pipe-arch (the invert of th
22、e pipe-arch), unless a special designis detailed in the plans and specifications.4.1.1 The concrete for pavements shall have a minimum28-day compressive strength of 3250 psi 22.4 MPa whentested in accordance with Specification C31/C31M and TestMethod C39/C39M. The pavement shall have a minimum 3 in.
23、75-mm thickness above the crests of the corrugations orstructural plate bolts or nuts as applicable.4.1.2 A minimum pavement thickness of 1-12 in. 38 mmabove the crests of the corrugations or structural plate bolts ornuts as applicable is required if concrete with a 28-dayminimum compressive strengt
24、h of 5 000 psi 34.5 MPa whentested in accordance with Specification C31/C31M and TestMethod C39/C39M, is used.NOTE 1For rehabilitation applications, greater concrete pavementthicknesses may be required to replace necessary pipe ring compressionstrength lost due to service conditions.4.2 Concrete Lin
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASTMA979A979M20032009STANDARDSPECIFICATIONFORCONCRETEPAVEMENTSANDLININGSINSTALLEDINCORRUGATEDSTEELSTRUCTURESINTHEFIELD

链接地址:http://www.mydoc123.com/p-460215.html