ASHRAE LO-09-006-2009 A Design Tool for Hybrid Geothermal Heat Pump Systems in Cooling-Dominated Buildings《降温建筑中混合式地源热泵系统用设计工具》.pdf
《ASHRAE LO-09-006-2009 A Design Tool for Hybrid Geothermal Heat Pump Systems in Cooling-Dominated Buildings《降温建筑中混合式地源热泵系统用设计工具》.pdf》由会员分享,可在线阅读,更多相关《ASHRAE LO-09-006-2009 A Design Tool for Hybrid Geothermal Heat Pump Systems in Cooling-Dominated Buildings《降温建筑中混合式地源热泵系统用设计工具》.pdf(14页珍藏版)》请在麦多课文档分享上搜索。
1、74 2009 ASHRAEABSTRACT A practical method for designing hybrid geothermal heat pump (GHP) systems that use closed-loop, earth heat exchang-ers installed in vertical boreholes is presented. The design diffi-culty with hybrid GHP systems is inherently an optimization problem that is best solved with a
2、 computer-based system simulation method. Many parameters can be optimized and there is no unique expression of the objective function. In this work the optimization problem is defined as balancing the annual thermal loads on the ground by minimizing the bore-hole heat exchanger length and appropria
3、tely sizing supple-mental equipment. The supplemental equipment examined in this work has been limited to direct-contact evaporative cool-ing towers. The design method for GHP systems was developed from results of 91 detailed computer simulations. Three dimension-less groups containing key GHP desig
4、n parameters were iden-tified using the Buckingham Pi Theorem, and correlated with a fitted surface equation. With typical design parameters avail-able to a practitioner, the design method developed here can be used to estimate the total ground loop length for stand-alone GHP systems, along with the
5、 quantity of annual energy required to balance the annual ground loads. With additional input parameters also readily available to designers, the capacity of a cooling tower can be calculated, along with the corresponding reduced borehole heat exchanger length. Cool-ing tower capacity is calculated
6、using an annual equivalent full load hour concept.INTRODUCTIONEnergy utilization in the built environment is of increas-ing concern, and geothermal heat pump (GHP) systems (also known as ground-source heat pump or Geoexchange systems) are now relatively well established as a means of significantly r
7、educing energy consumption in space condi-tioning of buildings. This improvement in efficiency, however, generally comes at a higher first cost, which must be offset by lower operating and maintenance costs within an acceptable period of time to the building owner. As with most alternative energy sy
8、stems, high capital cost is a significant barrier to market penetration.One of the main goals in the design of a GHP system is the proper sizing of the total length of the ground-loop heat exchanger so that it provides fluid temperatures to the heat pump within design limits. Unlike with conventiona
9、l heating and cooling systems, design of GHP systems requires some type of life-cycle simulation due to the thermal storage effects of the earth. Annual heating loads in a building are rarely balanced with annual cooling loads, and thus thermal responses of the ground throughout the buildings life c
10、ycle must be considered. In heating dominated buildings, annual imbalances in the ground load will lead to progressively lower heat pump entering fluid temperatures, and in cooling domi-nated buildings, progressively higher heat pump entering fluid temperatures will occur. These excursions may resul
11、t in the heat pump equipment capacity being compromised if the ground-loop heat exchanger (GLHE) is not large enough. Borehole fields designed for buildings with relatively large annual ground load imbalances can often be excessively large and costly, making vertical closed-loop GHP systems noncompe
12、titive with conventional systems.The phenomenon of long-term temperature change in the subsurface due to GHP systems serving buildings with imbal-anced annual thermal loads has given rise to the concept of the A Design Tool for Hybrid Geothermal Heat Pump Systems in Cooling-Dominated BuildingsA.D. C
13、hiasson, PhD, PE, PEng C. Yavuzturk, PhDAssociate Member ASHRAE Member ASHRAEA.D. Chiasson is an assistant professor, Department of Mechanical and Aerospace Engineering, University of Dayton, Dayton, OH. C. Yavuzturk is an assistant professor, Department of Mechanical Engineering, University of Hart
14、ford, West Hartford, CT.LO-09-006 2009, American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc. (www.ashrae.org). Published in ASHRAE Transactions 2009, vol. 115, part 2. For personal use only. Additional reproduction, distribution, or transmission in either print or digital
15、form is not permitted without ASHRAEs prior written permission.ASHRAE Transactions 75hybrid GHP system, where a supplemental component is utilized to effectively balance the annual ground loads. These systems permit the use of smaller, lower-cost borehole fields, but their design adds to the complex
16、ity of the overall GHP design process because of the addition of another transient component to the system. For example, acceptable conditions for supplemental heat rejection to the atmosphere in a cooling-dominated building depends on weather conditions and ground loop temperature. Consequently, hy
17、brid GHP systems should be analyzed on an hourly basis in order to be able to fully assess their behavior. The fundamental task in designing hybrid GHP systems lies in properly sizing the supplemental component and the ground-loop heat exchanger, using an appropriate control algorithm for system ope
18、ration so that annual heat rejection and extraction loads in the ground can be balanced. Current engineering design manuals such as Caneta Research, (1995), Kavanaugh and Rafferty (1997), and ASHRAE (2003), developed from research conducted since the 1980s, mention the potential use of hybrid coolin
19、g tower GHP systems, but do not describe a detailed design process for these systems.Proper and reliable design of hybrid GHP systems is quite difficult and cumbersome without the use of a system simula-tion approach. Further, without an automated optimization scheme coupled to the system simulation
20、 program, the design activity itself can become tediously impractical and time consuming. The use of system simulation for analyzing complex building systems is ever increasing, but the necessary computing resources are not at the disposal of every design practitioner, nor is their use always econom
21、ically justified. As new technologies and design concepts emerge, design tools and methodologies must accompany them and be made usable for practitioners. Without reliable design tools, reluctance of practitioners to implement more complex systems can become a significant barrier. Therefore, the ove
22、rall goal of the work presented in this paper is to develop a tool for the design of hybrid GHP systems in cooling-dominated buildings that is useful to practitioners. The design tool is based on current “state-of-the-art” system simulation methods, cast in a format that allows straight-forward use.
23、 It should be noted however that the design practice of balancing ground loads in no way means that the system is economically optimal as the method is based on minimizing ground loop length under the assumption that the ground loop is the most costly portion of the system. One could choose to optim
24、ize a system based on life-cycle cost using a system simulation approach. However, attempting to find an optimum life-cycle cost is fraught with uncertainties in economic indi-cators and future energy prices. For this reason, a design approach of minimizing total ground loop length is preferred, and
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASHRAELO090062009ADESIGNTOOLFORHYBRIDGEOTHERMALHEATPUMPSYSTEMSINCOOLINGDOMINATEDBUILDINGS 降温 建筑 混合式 源热泵

链接地址:http://www.mydoc123.com/p-455293.html