PPI TN-34-2009 Installation Guidelines For Electrofusion Couplings 14” and Larger《14及更大电熔接头的安装指南》.pdf
《PPI TN-34-2009 Installation Guidelines For Electrofusion Couplings 14” and Larger《14及更大电熔接头的安装指南》.pdf》由会员分享,可在线阅读,更多相关《PPI TN-34-2009 Installation Guidelines For Electrofusion Couplings 14” and Larger《14及更大电熔接头的安装指南》.pdf(26页珍藏版)》请在麦多课文档分享上搜索。
1、 Installation Guidelines For Electrofusion Couplings 14” and Larger TN-34/2009 105 Decker Court, Suite 825, Irving, TX 75062 P: 469-499-1044 F: 469-499-1062 www.plasticpipe.org Foreword This report was developed and published with the technical help and financial support of the members of the PPI (P
2、lastics Pipe institute). The members have shown their interest in quality products by assisting independent standards making and user organizations in the development of standards, and also by developing reports on an industry-wide basis to help engineers, code officials, specifying groups, and user
3、s. This report has been prepared by PPI as a service of the industry. The information in this report is offered in good faith and believed to be accurate at the time of its preparation, but is offered without any warranty, expressed or implied, including WARRANTIES OF MERCHANTABILITY AND FITNESS FOR
4、 A PARTICULAR PURPOSE. Any reference to or testing of a particular proprietary product should not be construed as an endorsement by PPI, which does not endorse the proprietary products or processes of any manufacturer. The information in this report is offered for consideration by industry members i
5、n fulfilling their own compliance responsibilities. PPI assumes no responsibility for compliance with applicable laws and regulations. PPI intends to revise this report from time to time, in response to comments and suggestions from users of the report. Please send suggestions of improvements to the
6、 address below. Information on other publications can be obtained by contacting PPI directly or visiting the web site. The Plastics Pipe Institute Phone: (469) 499-1044 http:/www.plasticpipe.org October 2009 Installation Guidelines for Electrofusion Couplings 14” and Larger A. Safety: Jobsite safety
7、 requirements should be fully understood and observed. Electrofusion fittings and equipment are not intended to be, and are not “Explosion Proof”. If used in a volatile environment, additional ignition concerns may be present and are not addressed in this document. When moisture at the fusion site i
8、s a safety concern, connect the leads to the fitting before the control unit is powered up. Take safety precautions to prevent exposure to electrical shock hazards. B. Operator Experience: Electrofusion couplings should only be installed by persons that have received training from an authorized elec
9、trofusion instructor, that have a strong working knowledge of polyethylene and heat fusion, and have qualified 14” and larger electrofusion joints through destructive testing. This document is a guide only, and should not be used in place of training by an authorized electrofusion instructor. Failur
10、e to follow all preparation steps can result in joint failure or leakage due to contamination or improper installation. Destructive tests are described in ASTM F1055-98 (2006) and can be in the form of burst tests, bend tests, peel tests and other methods useful in determining the quality of a fusio
11、n joint. (See Job Aid Appendix A for additional information). C. Pre-installation Requirements: 1. Pipe Diameter Some electrofusion manufacturers have specific dimensional requirements for pipe that is to be joined using electrofusion couplers. Verify that the pipe to be joined meets the electrofusi
12、on manufacturers requirements for optimum fusion. In the absence of specific dimensional requirements ensure that the pipe diameter is within the tolerances, at the specified temperature, of the applicable pipe standard (ASTM F714, AWWA C906, etc.). Standard tolerances are determined at 73F. Measure
13、 pipe diameter with a Pi tape (see Job Aid Appendix A) at 2” and 6” from the pipe end to determine diameter. Pipe toe-in or reduction in diameter, is a condition that occurs at the pipe end and should be checked to ensure that the pipe diameter is within tolerance at 2” from the end. Severe toe-in m
14、ay require the removal of up to one pipe diameter or 12” from the pipe end. In preparing a pipe for electrofusion the pipe OD is reduced by at least .014” by scraping the outside surface. This OD reduction should be taken into consideration when accepting pipe extruded close to the above minimum tol
15、erances. . 1. Pipe Ovality - Determine if an ovality condition exists: Measure the pipe diameter to determine the amount of out-of-roundness. if ovality exceeds 2%, re-rounding clamps must be used . 2. Pipe ends should be squarely cut to 90 5. A 4” or wider sling or strap can be used as a guide to m
16、ark the pipe for cutting (see Job Aid Appendix B). A level and protractor can be used to determine the angle of the cut. 3. Pipe alignment Pipe alignment should be inspected to ensure that no stresses are present in the assembly that might cause movement during fusion. 4. Power Source An adequate po
17、wer source is required. Ensure that power source is capable of delivering power for entire coupling fusion time without interruption (check generator for full fuel supply). Ensure that all connections are tight and clean. Loose connections can result in arcing or blown fuses. a. 110 Volt: A minimum
18、5000 watt continuous supply generator capable of delivering 115 volts to 135 volts at 45 Hz to 66 Hz to the control box. Minimum 30 amp breaker with “slow blow” or time delay fuse. 30 amp twist-lock Nema L5 receptacle. b. 220 Volt: A minimum 5000 watt continuous supply generator capable of deliverin
19、g 180 volts to 300 volts at 45 Hz to 65 Hz to the control box. Minimum 30 amp breaker with “slow blow” or time delay fuse. 15 amp twist-lock NEMA L6 receptacle. Note: Commercially available generators capable of meeting these requirements are usually in excess of 7500 watt capacity and need to be in
20、 good working order. 5. Extension Cords Typically, a single extension of up to 50 is permitted between the generator and the control box. The minimum wire gauge is 10/3 awg for extension lengths up to 50. Longer lengths may be allowed, consult the fitting and equipment manufacturer for specific reco
21、mmendations. 6. Control Box A 24 digit barcode compatible control box conforming to ISO 12716 must be used to deliver the required energy to the coupling. a. The control box must be capable of delivering 80 amperes at 40 volts output. b. The control box must be capable of reading the coupling barcod
22、e and applying the correct fusion parameters, including automatic temperature compensation, to the fitting without operator intervention. c. The control box must be capable of reading ambient temperatures at the fusion site. 7. Scraping Tools PIPE PREPARATION IS VERY CRITICAL TO THE ELECTROFUSION PR
23、OCESS. CAREFUL ATTENTION MUST BE GIVEN TO PROPER CLEANING AND SCRAPING PROCEDURES TO REMOVE CONTAMINATION AND SURFACE OXIDATION FROM THE PIPE SURFACE. a. Ensure that only mechanical type scraping tools designed specifically for electrofusion preparation are used to prepare the pipe surface. b. Do no
24、t use abrasives such as grinders, emery cloth, or sandpaper. 8. Markers Ensure that insertion depth and pipe scrape area markings are made with a non-greasy, non petroleum based, fast-drying, permanent marker or paint pen. 9. Cleaning agent / wiping cloth A clean, dry, non-dyed, lint free cloth is u
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- PPITN342009INSTALLATIONGUIDELINESFORELECTROFUSIONCOUPLINGS14 ANDLARGER14 更大 熔接 安装 指南 PDF

链接地址:http://www.mydoc123.com/p-1016784.html