ASTM C1214-2002(2009) Standard Test Method for Concrete Pipe Sewerlines by Negative Air Pressure (Vacuum) Test Method《负压(真空)试验法测定混凝土管下水道的标准试验方法》.pdf
《ASTM C1214-2002(2009) Standard Test Method for Concrete Pipe Sewerlines by Negative Air Pressure (Vacuum) Test Method《负压(真空)试验法测定混凝土管下水道的标准试验方法》.pdf》由会员分享,可在线阅读,更多相关《ASTM C1214-2002(2009) Standard Test Method for Concrete Pipe Sewerlines by Negative Air Pressure (Vacuum) Test Method《负压(真空)试验法测定混凝土管下水道的标准试验方法》.pdf(3页珍藏版)》请在麦多课文档分享上搜索。
1、Designation: C 1214 02 (Reapproved 2009)Standard Test Method forConcrete Pipe Sewerlines by Negative Air Pressure(Vacuum) Test Method1This standard is issued under the fixed designation C 1214; the number immediately following the designation indicates the year oforiginal adoption or, in the case of
2、 revision, the year of last revision. A number in parentheses indicates the year of last reapproval. Asuperscript epsilon () indicates an editorial change since the last revision or reapproval.1. Scope1.1 This test method covers procedures for testing concretepipe sewerlines, when using the negative
3、 air pressure (vacuum)test method to demonstrate the integrity of the installedmaterial and the construction procedures. This test methodcovers testing of 4 to 36-in. diameter circular concrete pipesewerlines utilizing gasketed joints.NOTE 1The user of this test method is advised that methods descri
4、bedherein may also be used as a preliminary test to enable the manufactureror installer to demonstrate the condition of sewer pipe prior to delivery orbackfill. Minimum test times presented in Table 1 are for pipelines.Holding times for testing an individual pipe may have to be increased toallow for
5、 the accumulation of leakage when the tested pipe are incorpo-rated into a continuous pipeline.NOTE 2The user of this test method is advised that the negative airpressure (vacuum) test criteria presented in this test method are similar tothose in general use. The test and criteria have been used wid
6、ely andsuccessfully in testing smaller diameter pipe. Larger pipe will be acceptedmore conveniently by visual inspection and individual joint testing.NOTE 3The user of this test method is advised that no correlation hasbeen found between loss of vacuum and water leakage.1.2 This test method is the i
7、nch-pound companion to TestMethod C 1214M; therefore, no SI equivalents are presented inthe test method.1.3 This standard does not purport to address all of thesafety concerns, if any, associated with its use. It is theresponsibility of the user of this standard to establish appro-priate safety and
8、health practices and determine the applica-bility of regulatory limitations prior to use. See Section 6 forspecific safety precautions.2. Referenced Documents2.1 ASTM Standards:2C 822 Terminology Relating to Concrete Pipe and RelatedProductsC 924 Practice for Testing Concrete Pipe Sewer Lines byLow-
9、Pressure Air Test MethodC 969 Practice for Infiltration and Exfiltration AcceptanceTesting of Installed Precast Concrete Pipe Sewer Lines3. Terminology3.1 DefinitionsFor definitions of terms relating to con-crete pipe, see Terminology C 822.4. Summary of Test Method4.1 The sewerline to be tested is
10、plugged. Air is removedfrom the plugged line by a vacuum pump or vacuum reservoir.The amount of vacuum loss is used to determine the accept-ability of the sewerline.5. Significance and Use5.1 This is not a routine test. The values recorded areapplicable only to the sewer being tested and at the time
11、 oftesting.6. Safety Precautions6.1 WarningThe user of this test method is advised thatthis test may be dangerous if a line is not prepared properly andproper procedures are not followed.6.2 Access manholes or structures must be ventilated and airquality continuously monitored.6.3 No one shall be al
12、lowed in or near the manholes duringtesting.7. Preparation of the Sewerline7.1 Where practical, clean the line prior to testing, wet thepipe surface, and eliminate debris.1This test method is under the jurisdiction of ASTM Committee C13 onConcrete Pipe and is the direct responsibility of Subcommitte
13、e C13.09 on Methodsof Test.Current edition approved June 1, 2009. Published July 2009. Originally approvedin 1992. Last previous edition approved in 2002 as C 1214 02.2For referenced ASTM standards, visit the ASTM website, www.astm.org, orcontact ASTM Customer Service at serviceastm.org. For Annual
14、Book of ASTMStandards volume information, refer to the standards Document Summary page onthe ASTM website.TABLE 1 Minimum Test TimeNominalPipeSize, in.T (Time),min/100 ftNominalPipeSize, in.T (Time),min/100 ft4 0.3 21 3.06 0.7 24 3.68 1.2 27 4.210 1.5 30 4.812 1.8 33 5.415 2.1 36 6.018 2.41Copyright
15、 ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959, United States.NOTE 4The user of this test method is advised that a wetted exteriorpipe surface is desirable and will produce more consistent test results. Airmay pass through the walls of dry pipe. This can be
16、 overcome by wettingthe pipe. Usually, moisture absorbed from the backfill is sufficient to copewith this situation. If the problem persists, segmental testing of the linewill establish if there is a significant leak.7.2 Plug all pipe outlets including laterals. Review safetyprecautions in Section 6
17、.8. Procedure8.1 Determine the test time for the sewerline to be tested byusing Table 1. Table 1 has been established using the criteriaspecified in Table 2 and the formulas contained in the Appen-dixes. The test time is the time required for the vacuum to dropfrom 7 to 5 in. of mercury.NOTE 5To pro
18、vide satisfactory test results, the vacuum pump shall becapable of evacuating the sewer test section in the required test time, orless, as determined by 8.1. The pump capacity required to accomplish theevacuation of the line is equal to the rate necessary to reduce the sewer tothe desired pressure p
19、lus the allowable vacuum loss rate:C 5 0.17D2L/T 1 Q (1)where:C = vacuum pump capacity, ft3/min,T = required test time, or less, min,D = pipe internal diameter, ft,L = length of test section, ft, andQ = allowable vacuum loss rate, ft3/min.8.2 Evacuate air until the internal air pressure of thesewerl
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASTMC121420022009STANDARDTESTMETHODFORCONCRETEPIPESEWERLINESBYNEGATIVEAIRPRESSUREVACUUMTESTMETHOD 真空

链接地址:http://www.mydoc123.com/p-463777.html