《REG NASA-LLIS-1144--2000 Lessons Learned - International Space Station (ISS) Program Extravehicular Activity (EVA) Supportability.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1144--2000 Lessons Learned - International Space Station (ISS) Program Extravehicular Activity (EVA) Supportability.pdf(3页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1144Lesson Info:a71 Lesson Number: 1144a71 Lesson Date: 2000-02-01a71 Submitting Organization: HQa71 Submitted by: David M. LengyelSubject: International Space Station (ISS) Program/Extravehicular Activity (EVA)/Supportability Description of Driving Event: Potential Internatio
2、nal Space Station (ISS) Supportability Problems With Existing Extravehicular Activity (EVA) AssetsLesson(s) Learned: The EVA Project Office has several planned initiatives to ensure the availability of adequate EVA resources to support the ISS and Space Shuttle. These initiatives cover acquisition o
3、f material, development of procedures, and improved training.Recommendation(s): Expedite completion of the planned initiatives related to the safety of EVA so that maximum benefit can be realized during the upcoming intensive ISS assembly schedule.Evidence of Recurrence Control Effectiveness: NASA c
4、oncurs with the ASAP recommendation. In June 1999, the EVA Project Office initiated the development of a small planar hard upper torso (HUT) in addition to the medium, large, and extra-large HUTs already developed. With four HUT sizes, the broadest range of crewmembers (5th percentile Asian female t
5、o 95th percentile Caucasian male) will be accommodated. The small planar HUT has successfully completed the concept development phase, and the preliminary design review is scheduled for May 2000. The first flight item is on schedule for delivery in October 2002.Redesign of the (EMU) to allow for on-
6、orbit replacement of a primary life support subsystem, HUT, displays and control module, and secondary oxygen pack is ahead of schedule to support the ISS 6A Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-flight. The EVA Project Office is assessing
7、the feasibility of flying the EMU on-orbit replacement unit configuration on ISS flight 5A prior to the need to leave an EMU onboard the ISS during 6A.Single mission certification for the phase VI glove was accomplished prior to ISS flights 2A and 2A.1. Full certification (up to 19 EVAs) was complet
8、ed in March 2000, approximately 1 year prior to leaving phase VI gloves onboard the ISS for 90-day increments.Like the phase VI glove, the U.S. Simplified Aid for EVA Rescue (SAFER) has flown with single-mission certification on five previous missions. Anomalies identified during three of these prev
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS11442000LESSONSLEARNEDINTERNATIONALSPACESTATIONISSPROGRAMEXTRAVEHICULARACTIVITYEVASUPPORTABILITYPDF

链接地址:http://www.mydoc123.com/p-1018783.html