1、BRITISH STANDARD BS 7813:1995 ISO 4124:1994 Guide for Statistical control of dynamic liquid hydrocarbon volumetric metering systemsBS7813:1995 This British Standard, having been prepared under the directionof the Sector Board for Materials and Chemicals, was published under the authority ofthe Stand
2、ards Board and comesinto effect on 15June1995 BSI 09-1999 The following BSI references relate to the work on this standard: Committee reference PTI/12 Draft for comment88/52423 DC ISBN 0 580 24139 4 Committees responsible for this British Standard The preparation of this British Standard was entrust
3、ed to Technical Committee PTI/12, Petroleum measurement and sampling, upon which the following bodies were represented: Department of Trade and Industry (National Engineering Laboratory) Department of Trade and Industry (Oil and Gas Office) Institute of Petroleum Salvage Association The following bo
4、dy was also represented in the drafting of the standard, through subcommittees and panels: GAMBICA (BEAMA Ltd.) Amendments issued since publication Amd. No. Date CommentsBS 7813:1995 BSI 09-1999 i Contents Page Committees responsible Inside front cover National foreword iii Section 1. General 1.1 Sc
5、ope 1 1.2 Definitions 1 1.3 Symbols and units 1 1.4 Central proving 2 1.5 On-line proving 2 Section 2. Statistical measurements 2.1 Principles of statistical measurement 3 2.2 Measurement procedure 6 Section 3. Central proving 3.1 Collection of data 9 3.2 Reliability of data collected and resulting
6、values 10 3.3 Performance charts 11 3.4 Control charts and tests 18 3.5 Worked examples 21 Section 4. On-line proving 4.1 Collection of data 45 4.2 Reliability of data collected 47 4.3 Performance charts 47 4.4 Control charts 48 4.5 Worked examples 52 Section 5. Secondary control 5.1 Comparison betw
7、een meter and tank 63 Annex A (informative) Statistical tables 67 Annex B (informative) t-distribution values for95% and99% probability (two-sided) 70 Annex C (informative) Normal (Gaussian) distribution 71 Annex D (informative) Outlier tests 73 Annex E (informative) Random uncertainty of polynomial
8、 approximation 75 Annex F (informative) Bibliography 75 Figure 1 Performance chart: K-factor versus flowrate showing scatter (range) of5 to10 consecutive runs 8 Figure 2 Control chart (general) 8 Figure 3 Performance chart No.1 13 Figure 4 Performance chart No.2 14 Figure 5 Performance chart No.3, E
9、 = f (Q) 14 Figure 6 Performance chart No.4 UCC polynomial 15 Figure 7 Control chart No.1 19 Figure 8 Control chart No.2 19 Figure 9 Control chart No.3 20 Figure 10 Control chart No.4 20 Figure 11 Double chronometer method of pulse interpolation 24 Figure 12 Performance chart, turbine No.310,1978 28
10、 Figure 13 Log (Q/v) vs. meter factor, turbine No.310,1978 29 Figure 14 Performance chart, turbine No.310,1979 33 Figure 15 Log (Q/v) vs. meter factor, turbine No.310,1979 34BS7813:1995 ii BSI 09-1999 Page Figure 16 Performance chart, turbine No.310,1980 38 Figure 17 Log (Q/v) vs. meter factor, turb
11、ine No.310,1980 39 Figure 18 Comparison of1978 data with1979 data, log (Q/v) vs. meter factor, turbine No.310 43 Figure 19 Comparison of1979 data with1980 data, log (Q/v) vs. meter factor, turbine No.310 44 Figure 20 Permissable change in flowrate during proving 46 Figure 21 Performance chart from s
12、eries of on-line provings 48 Figure 22 K-factor (mean of5 or10 consecutive runs) versus time 49 Figure 23 Combined performance/control chart 51 Figure 24 Moving-average meter factor versus time 52 Figure 25 Control chart for meter operating within linear range 56 Figure 26 Chart A Meter performance
13、curves Meter turbine provedwithpipe prover 59 Figure 27 Control chart Meter operating outside linear range 61 Figure C.1 Frequency histogram 72 Figure C.2 Bell-shaped distribution curve 72 Table 1 Performance chart No.5 Direct matrix 16 Table 2 Performance chart No.6 17 Table 3 Example5: test result
14、s for turbine meter 25 Table 4 Performance chart, meter No.310 test report,1978 30 Table 5 Meter factor for turbine meter No.310,1978 31 Table 6 Random uncertainty of polynomial for turbine No.310,1978 32 Table 7 Performance chart, meter No.310 test report,1979 35 Table 8 Meter factor for turbine me
15、ter No.310,1979 36 Table 9 Random uncertainty of polynomial for turbine No.310,1979 37 Table 10 Performance chart, meter No.310 test report,1980 40 Table 11 Meter factor for turbine meter No.310,1980 41 Table 12 Random uncertainty of polynomial for turbine No.310,1980 42 Table 13 Example4 Normalizin
16、g meter factor 58 Table 14 Computed uncertainty for vertical cylindrical tanks at15 C 65 Table 15 Computed meter uncertainty at15 C 65 Table 16 Combined values of transfer uncertainty for tank and meter 66 Table A.1 Distribution of the range 67 Table A.2 Limiting values E 2(n, ), P =0,95 68 Table A.
17、3 Limiting values E 2(n, ), P =0,99 69 Table B.1 t-distribution values 70 Table D.1 For use with Dixons Test for outliers 73 Table D.2 For use with Grubbs Test for outliers 74 List of references Inside back coverBS7813:1995 BSI 09-1999 iii National foreword This British Standard has been prepared by
18、 Technical Committee PTI/12. It is identical with ISO4124:1994, Liquid hydrocarbons Dynamic measurement Statistical control of volumetric metering systems, published by the International Organization for Standardization (ISO). ISO4214 was prepared by Subcommittee2, Dynamic petroleum measurement, of
19、Technical Committee, Petroleum products and lubricants, in which the United Kingdom participated. A British Standard does not purport to include all the necessary provisions of a contract. Users of British Standards are responsible for their correct application. Compliance with a British Standard do
20、es not of itself confer immunity from legal obligations. Cross-references International Standard Corresponding British Standard BS6866 Proving systems for meters used in dynamic measurement of liquid hydrocarbons ISO7278-3:1986 Part3:1987 Methods for pulse interpolation (Identical) Summary of pages
21、This document comprises a front cover, an inside front cover, pagesi to iv, pages1to76, an inside back cover and a back cover. This standard has been updated (see copyright date) and may have had amendments incorporated. This will be indicated in the amendment table on the inside front cover.iv blan
22、kBS7813:1995 BSI 09-1999 1 Section 1. General 1.1 Scope In dynamic measuring systems the performance of meters for liquid hydrocarbons will vary with changes in flow conditions, viz. flowrate, viscosity, temperature, pressure, density of product, and with mechanical wear. This International Standard
23、 has been prepared as a guide for establishing and monitoring the performance of such meters, using appropriate statistical control procedures for both central and on-line proving. These procedures may be applied to measurements made by any type of volumetric or mass metering system. The procedures
24、to be followed for collecting data, on which the control limits are based, are described. An alternative method for establishing the reliability of these data is described in ISO7278-3. Methods are described for calculating the warning and action control limits for the charts covering the selected p
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- BS78131995GUIDEFORSTATISTICALCONTROLOFDYNAMICLIQUIDHYDROCARBONVOLUMETRICMETERINGSYSTEMS 液态 容量 系统 统计 控制

链接地址:http://www.mydoc123.com/p-547059.html