ARMY UFGS-03 37 29-2009 CONCRETE FOR CONCRETE CUTOFF WALLS《混凝土隔水墙用混凝土》.pdf
《ARMY UFGS-03 37 29-2009 CONCRETE FOR CONCRETE CUTOFF WALLS《混凝土隔水墙用混凝土》.pdf》由会员分享,可在线阅读,更多相关《ARMY UFGS-03 37 29-2009 CONCRETE FOR CONCRETE CUTOFF WALLS《混凝土隔水墙用混凝土》.pdf(35页珍藏版)》请在麦多课文档分享上搜索。
1、*USACE / NAVFAC / AFCESA / NASA UFGS-03 37 29 (November 2009)-Preparing Activity: USACE (CW) SupersedingUFGS-03 37 29 (April 2006)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated October 2009*SECTION TABLE OF CONTENTSDIVISION 03 - CONCRETESECTION 03 37 29CONCRETE FO
2、R CONCRETE CUTOFF WALLS11/09PART 1 GENERAL1.1 UNIT PRICES1.1.1 Coring Concrete in Completed Panels1.1.1.1 Payment1.1.1.2 Measurement1.1.2 Unit of Measure1.2 REFERENCES1.3 SYSTEM DSCRIPTION1.3.1 Responsibility of Mixture Proportioning1.3.2 Concrete Proportioning1.4 SUBMITTALS1.5 QUALITY ASSURANCE1.5.
3、1 Government Testing and Sampling1.5.2 Preconstruction Sampling and Testing1.5.2.1 Aggregates1.5.2.2 Cementitious Materials and Admixtures1.5.3 Construction Testing by the Government1.5.3.1 Chemical Admixtures Requirements1.5.3.2 Cement and Pozzolan1.5.3.3 Concrete TestsPART 2 PRODUCTS2.1 MATERIALS2
4、.1.1 Cementitious Materials2.1.1.1 Portland Cement2.1.1.2 Pozzolan, Other than Silica Fume2.1.1.3 Ground Granulated Blast-Furnace (GGBF) Slag2.1.2 Aggregates2.1.2.1 Listed Sources2.1.2.2 Concrete Aggregate Sources2.1.2.3 Quality2.1.2.4 Fine Aggregate Grading and Moisture Content2.1.2.5 Coarse Aggreg
5、ate Grading and Moisture Content2.1.3 Chemical AdmixturesSECTION 03 37 29 Page 1Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-2.1.3.1 Air-Entraining Admixture2.1.3.2 Accelerating Admixture2.1.3.3 Flowing Concrete Admixtures2.1.4 Water2.2 PLANT AND
6、EQUIPMENT2.2.1 Capacity2.2.2 Batch Plant2.2.2.1 Batching Equipment2.2.2.2 Scales2.2.2.3 Batching Tolerances2.2.2.4 Moisture Control2.2.3 Concrete Mixers2.2.3.1 Stationary Mixers2.2.3.2 Truck Mixers2.2.4 Conveying Equipment2.2.4.1 Buckets2.2.4.2 Trucks2.2.4.3 Chutes2.2.4.4 Concrete PumpsPART 3 EXECUT
7、ION3.1 PLACING3.1.1 Time Interval Between Mixing and Placing3.1.2 Placing Temperature3.1.3 Concrete Deposited in Cutoff Trench3.1.4 Concrete Placement3.1.5 Required Height of Concrete3.2 CURING AND PROTECTION3.3 TESTS AND INSPECTIONS3.3.1 General3.3.2 Testing and Inspection Requirements3.3.2.1 Fine
8、Aggregate3.3.2.2 Coarse Aggregate3.3.2.3 Quality of Aggregates3.3.2.4 Deleterious Substances3.3.2.5 Scales3.3.2.6 Batch-Plant Control3.3.2.7 Concrete Mixture3.3.2.8 Placing3.3.2.9 Curing3.3.2.10 Mixer Uniformity3.3.3 Reports3.3.4 Concrete Coring3.3.4.1 Concrete Coring in Completed Panels3.3.4.2 Meth
9、od of Drilling3.3.4.3 Equipment and Supplies3.3.4.4 Core Boxes3.3.4.5 Disposition of Core Samples3.3.4.6 Backfilling Core Holes3.3.5 Evaluation and Acceptance- End of Section Table of Contents -SECTION 03 37 29 Page 2Provided by IHSNot for ResaleNo reproduction or networking permitted without licens
10、e from IHS-,-,-*USACE / NAVFAC / AFCESA / NASA UFGS-03 37 29 (November 2009)-Preparing Activity: USACE (CW) SupersedingUFGS-03 37 29 (April 2006)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated October 2009*SECTION 03 37 29CONCRETE FOR CONCRETE CUTOFF WALLS11/09*NOT
11、E: This guide specification covers the requirements for concrete cutoff wall structures.Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information.Remove information and requ
12、irements not required in respective project, whether or not brackets are present.Comments and suggestions on this guide specification are welcome and should be directed to the technical proponent of the specification. A listing of technical proponents, including their organization designation and te
13、lephone number, is on the Internet.Recommended changes to a UFGS should be submitted as a Criteria Change Request (CCR).*PART 1 GENERAL*NOTE: The content of this specification is such that guidance given in EM 1110-2-2000, “Standard Practice for Concrete“, is applicable.*1.1 UNIT PRICES*NOTE: If Sec
14、tion 01 22 00.00 10 MEASUREMENT AND PAYMENT is included in the project specifications, this paragraph title (UNIT PRICES) should be deleted from this section and the remaining appropriately edited subparagraphs below should be inserted into Section 01 22 00.00 10.SECTION 03 37 29 Page 3Provided by I
15、HSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-With the exception of coring concrete in completed panels, all costs in connection with this section, including all materials, will be included in the payment item(s) specified.Core recovery percentage for each bori
16、ng should be a high number such as 90 to 95, since it is expected that a competent concrete material is being cored. The deviation of the core hole should be in relation to the smallest dimension of the panels that will be produced for each jobsite.*1.1.1 Coring Concrete in Completed Panels1.1.1.1 P
17、aymentPayment will be made for costs associated with Coring Concrete in Completed Panels and backfilling the core holes. This price will constitute full compensation for mobilizing and demobilizing and furnishing all equipment and supplies necessary to perform all operations specified. No payment wi
18、ll be made for coring and backfilling at a location where the coring reveals the presence of “unacceptable concrete“, as specified in paragraph UNACCEPTABLE CONCRETE IN COMPLETED PANELS in PART 3. All costs incurred, including the initial core boring and as many additional core borings as may be req
19、uired to delineate the limits of the unacceptable concrete and the repair of the cutoff wall, shall be borne by the Contractor and shall not result in any additional cost to the Government.1.1.1.2 MeasurementCoring Concrete in Completed Panels will be measured for payment from the top of the panel t
20、o the bottom of the core hole. If overall core recovery for a boring is less than _ percent or the boring deviates from the cutoff wall prior to reaching a depth of _ meters feet, the boring shall be redrilled and backfilled at no additional cost to the Government.1.1.2 Unit of MeasureUnit of measur
21、e: per linear meter foot of cored hole.1.2 REFERENCES*NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title.
22、Use the Reference Wizards Check Reference feature when you add a RID outside of the Sections Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizards Check Reference feature to update the issue dates.References not used in the text will automati
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ARMYUFGS0337292009CONCRETEFORCONCRETECUTOFFWALLS 混凝土 隔水墙用 PDF

链接地址:http://www.mydoc123.com/p-449550.html