1、TECHNICAL PAPER ON COMMUNITY RURAL ELECTRIFICATION IN NEPAL ON THE OCCASION OF “POWER SUMMIT 2008” By,RAMESHWAR YADAV Director NEPAL ELECTRICITY AUTHORITY COMMUNITY RURAL ELECTRIFICATION DEPARTMENT PULCHOCK, LALITPUR,NEPAL PHONE, 55 22 308, FAX, 55 23 451 E-MAIL: Ashoj 7- 8, 2065 (Sept. 23-24, 2008
2、) Kathmandu,Different Models of Rural Electrification Institution,Alternative Energy Promotion Centre, GoN, responsible for OFF-GRID Electrification. Nepal Electricity Authority, Govt. Undertaken Butwal Power Company (BPC) generates power, sell to NEA, as well as distribute electricity on their own
3、rural areas. Two companies, Salleri Chaialsa Electricity Company (SCEO) and Khumbu Bijuli Company (KBC), which generate in isolated mode and distribute electricity on their own in rural areas.,Rural Electrification Models of NEA,RE under Power Projects RE under Grant projects RE through Community RE
4、 by using Small Hydro Power Plants RE by annual Government Budget RE of small line extension by NEAs budget .,Concept Of Profit Center and Users group cooperative in NEA,NEA established Lamjung Electricity Users Association (LEUA) as a first pilot project in 1997 under GoN and NORDIC funding to mana
5、ge better services at least cost and restricted distribution losses. With the background to reduce the technical and non-technical loss of distribution system, arrears and black listed consumers NEA introduced the concept of profit center and accordingly Profit Center Bye Laws was brought enforce in
6、 2059 BS Concept of load centre based users group cooperative formation under Kailali- Kanchanpur Rural Electrification Project started in 1999. An international consultant National Rural Electric Cooperative Association (NRECA), USA was appointed in 1998 under loss component of KG-AHPP financed by
7、ADB,Concept Of Profit Center and Users group cooperative in NEA contd.,The action plan was focused on following recommendations also. - Formation of village user groups Lease out the distribution centers The study tour program in international utilities of Bangladesh, Thailand and Philippines was al
8、so included in the scope of this consultancy service. one of the common recommendations of study tour was “Formation of Cooperatives involving the local people. The consultancy works were completed in 1999, With the background of above facts and study, the NEA formed the Community Electricity Distri
9、bution Bye Laws 2060 . The policy of 80%-20% investment in rural electrification was shortly introduced by the government,Other Types of Cooperatives in RE,More than 500 Cooperatives of OFF-GRID System by using Micro Hydro Power Plant with the support of AEPC have been benefited. Khimti Rural Electr
10、ification Cooperative (KREC) covers four VDC of Dolakha district and six VDC of Ramechap district Financed by Himal Power Limited and UNDP Tamakosi Rural Electrification Cooperative (TREC) financed by HPL for four VDC of Dolakha district is also in the stage of formation.,Objectives of Community Ele
11、ctricity Bye Laws 2060,To promote public participation To encourage community management To promote technical and managerial capability of rural community To attract private investment in the field of rural electrification,The salient features of Cooperative Programs,Community Rural Electrification
12、is considered as priority one ( p1 ) project by the Government of Nepal . A separate “Community Rural Electrification Fund” is established for the community 20 percent of total investment is invested by the Community and 80 percent by GoN. . Mostly projects are completed by turn key contract basis.
13、There is a Task Force with the Chairmanship of NEA Board Member.,The salient features of Cooperative Programs,Project area is selected by the consumers, which reduces the dispute of consumers for power supply in that area . There is no any right of ways problem in construction of project . Highly tr
14、ansparency because the involvement of community is started from finalization of proposal to project hand over . All decisions regarding community are done by the Steering Committee of Community Rural Electrification .,The salient features of Cooperative Programs,Meter Reading at single point of dist
15、ribution system transfers the distribution losses to the account of Community It maintains the non-technical loss free zone of distribution system . Distribution Institution shall have to deposit monthly at least 10 percent of monthly sales income in “Repair and Maintenance Fund There is a provision
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
2000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- TECHNICALPAPERONCOMMUNITYRURALPPT