REG UFGS-01 83 00 07 40-2012 RELIABILITY CENTERED ACCEPTANCE FOR FACILITY SHELLS.pdf
《REG UFGS-01 83 00 07 40-2012 RELIABILITY CENTERED ACCEPTANCE FOR FACILITY SHELLS.pdf》由会员分享,可在线阅读,更多相关《REG UFGS-01 83 00 07 40-2012 RELIABILITY CENTERED ACCEPTANCE FOR FACILITY SHELLS.pdf(10页珍藏版)》请在麦多课文档分享上搜索。
1、*USACE / NAVFAC / AFCESA / NASA UFGS-01 83 00.07 40 (February 2012)-Preparing Activity: NASA SupersedingUFGS-01 83 00.07 40 (February 2010)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated January 2012*SECTION TABLE OF CONTENTSDIVISION 01 - GENERAL REQUIREMENTSSECTIO
2、N 01 83 00.07 40RELIABILITY CENTERED ACCEPTANCE FOR FACILITY SHELLS02/12PART 1 GENERAL1.1 SYSTEM DESCRIPTION1.2 REFERENCES1.3 SUBMITTALS1.4 QUALITY ASSURANCE1.5 WARRANTYPART 2 PRODUCTS2.1 PRODUCT DATA2.1.1 Manufacturers Product Data2.1.2 Certification Data2.1.3 Specific Equipment Data2.1.4 Extra Mat
3、erialsPART 3 EXECUTION3.1 INSTALLATION3.2 EXAMINATION3.3 FIELD QUALITY CONTROL AND ACCEPTANCE TESTING3.3.1 Predictive Testing and Inspection Tests3.3.2 Baseline Data from Verification Testing3.4 OPERATIONS AND MAINTENANCE3.5 ACCEPTANCE DOCUMENTATION- End of Section Table of Contents -SECTION 01 83 0
4、0.07 40 Page 1Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-*USACE / NAVFAC / AFCESA / NASA UFGS-01 83 00.07 40 (February 2012)-Preparing Activity: NASA SupersedingUFGS-01 83 00.07 40 (February 2010)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences
5、 are in agreement with UMRL dated January 2012*SECTION 01 83 00.07 40RELIABILITY CENTERED ACCEPTANCE FOR FACILITY SHELLS02/12*NOTE: This specification covers the AIR FORCE ARMY NASA NAVY requirements for Reliability Centered Building and Equipment Acceptance for Facility Shell Systems (foundations,
6、structure, walls, openings, roofs, insulation, and vapor barrier systems, etc.). The contents universally apply to building envelope systems and may be utilized by other organizations, if deemed beneficial.Refer to Section 01 83 13.07 40 RELIABILITY CENTERED ACCEPTANCE FOR SUPERSTRUCTURE PERFORMANCE
7、 REQUIREMENTS for externally exposed structures such as communication towers, launch facilities; and partially open shelters such as those for fueling chemical storage, as well as underground special structures for explosives and ordinance.Refer to Section 01 86 12.07 40 RELIABILITY CENTERED ACCEPTA
8、NCE FOR MECHANICAL SYSTEMS for HVAC and Plumbing systems.Refer to Section 01 86 26.07 40 RELIABILITY CENTERED ACCEPTANCE FOR ELECTRICAL SYSTEMS for facility electrical power and distribution systems.Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing th
9、is guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information.Remove information and requirements not req
10、uired in respective project, whether or not brackets are present.Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR).SECTION 01 83 00.07 40 Page 2Provided by IHSNot for ResaleNo reproduction or networking p
11、ermitted without license from IHS-,-,-*PART 1 GENERAL1.1 SYSTEM DESCRIPTION*NOTE: This specification is not intended to limit the inspection and acceptance process to the use of Predictive Testing “DO“ for District Office (Engineering Division or other organization in the District Office); “AO“ for
12、Area Office; “RO“ for Resident Office; and “PO“ for Project Office. Codes following the “G“ typically are not used for Navy, Air Force, and NASA projects.Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects.*Government approval
13、is required for submittals with a “G“ designation; submittals not having a “G“ designation are for Contractor Quality Control approval.information only. When used, a designation following the “G“ designation identifies the office that will review the submittal for the Government. Submit the followin
14、g in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:SD-01 Preconstruction SubmittalsMaterial, Equipment, and Fixture Lists; G; G, _Quality Control Plan; G; G, _SD-02 Shop DrawingsFabrication Drawings; G; G, _Layout Drawings; G; G, _SD-03 Product DataManufacturers Catalog Data; G; G, _Specific
15、 Equipment Data; G; G, _Spare Parts List; G; G, _SECTION 01 83 00.07 40 Page 4Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Warranty; G; G, _SD-04 SamplesSamples; G; G, _SD-06 Test ReportsInfrared Thermography Test; G; G, _Ultrasonic (Airborne) Tes
16、t; G; G, _Visual Inspection; G; G, _SD-07 CertificatesCertificates; G; G, _SD-08 Manufacturers InstructionsManufacturers Instructions; G; G, _SD-10 Operation and Maintenance DataOperations and Maintenance Manuals; G; G, _SD-11 Closeout SubmittalsAcceptance Documentation; G; G, _Baseline Data Report;
17、 G; G, _1.4 QUALITY ASSURANCESubmit a Quality Control plan outlining the intended methods of receiving, testing, and installing equipment and structural components. The RCBEA GUIDE specifies minimum test equipment requirements. Use trained, certified personnel in the application of appropriate accep
18、tance testing PT issued directly to the Government. Perform corrective action that becomes necessary because of defective materials and workmanship while system is under warranty within 7_ days after notification, unless additional time is approved by the Contracting Officer. Failure to perform repa
19、irs within the specified period of time constitutes grounds for having the corrective action and repairs performed by others and the cost billed to the Contractor. Provide a 1_ year minimum contractor installation warranty.SECTION 01 83 00.07 40 Page 5Provided by IHSNot for ResaleNo reproduction or
20、networking permitted without license from IHS-,-,-PART 2 PRODUCTS2.1 PRODUCT DATASubmit material, equipment, and fixture lists for all equipment, structural components, materials, and fixtures planned for use to complete the job before commencing work. Include at a minimum, the items description, qu
21、antity, manufacturers style or catalog numbers, and specification and drawing reference numbers. Provide a complete list of construction equipment to be used.Provide product samples for roof, wall, and insulation system components, at a minimum include roof membrane materials, underlayment, flashing
22、, insulation, roof and wall penetrations, fasteners, and finish color swatches for Contracting Officer approval prior to commencing work or ordering materials. Size samples to clearly illustrate product features and characteristics.2.1.1 Manufacturers Product DataInclude manufacturers standard catal
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGUFGS01830007402012RELIABILITYCENTEREDACCEPTANCEFORFACILITYSHELLSPDF

链接地址:http://www.mydoc123.com/p-1019620.html