1、*USACE / NAVFAC / AFCESA / NASA UFGS-01 45 00.00 40 (May 2012)-Preparing Activity: NASA SupersedingUFGS-01 45 00.00 40 (February 2010)UNIFIED FACILITIES GUIDE SPECIFICATIONS*SECTION TABLE OF CONTENTSDIVISION 01 - GENERAL REQUIREMENTSSECTION 01 45 00.00 40QUALITY CONTROL05/12PART 1 GENERAL1.1 SUMMARY
2、1.2 SUBMITTALS1.2.1 Quality Assurance (QA) Plan1.2.2 Records1.2.2.1 Narrative Description1.2.2.2 Monthly Performance Report1.2.2.3 Letters of Authority or Delegation1.2.2.4 Off-Site Inspection and Control1.3 QUALITY ASSURANCE1.3.1 Qualifications of Quality Representative1.3.2 Quality Control Require
3、ments1.3.2.1 Management and Organization1.3.2.2 Identification and Data Retrieval1.3.2.3 Procurement1.3.2.4 Receiving Inspection System1.3.2.5 Nonconforming Articles and Material Control1.3.2.6 Fabrication, Process, and Work Control1.3.2.7 Quality Control Records1.3.2.8 Drawings and Change Control1.
4、3.3 Quality Inspections1.3.3.1 Government Inspections1.3.3.2 Contractors Quality Inspections1.3.4 Field Services1.3.4.1 Responsibility for Inspection and Testing1.3.4.2 Inspection and Test Records1.4 HANDLING AND STORAGE1.5 SEQUENCING AND SCHEDULINGPART 2 PRODUCTSPART 3 EXECUTION- End of Section Tab
5、le of Contents -SECTION 01 45 00.00 40 Page 1Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-*USACE / NAVFAC / AFCESA / NASA UFGS-01 45 00.00 40 (May 2012)-Preparing Activity: NASA SupersedingUFGS-01 45 00.00 40 (February 2010)UNIFIED FACILITIES GUID
6、E SPECIFICATIONS*SECTION 01 45 00.00 40QUALITY CONTROL05/12*NOTE: This guide specification covers the requirements for inspections, test reports, and contractor obligations for establishing effective quality assurance procedures for NASA.Adhere to UFC 1-300-02 Unified Facilities Guide Specifications
7、 (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information.Remo
8、ve information and requirements not required in respective project, whether or not brackets are present.Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR).*PART 1 GENERAL1.1 SUMMARYThe requirements of this
9、 Section apply to, and are a component part of, each section of the specifications.1.2 SUBMITTALS*NOTE: Review Submittal Description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project.The Guide Specification t
10、echnical editors have designated those items that require Government approval, due to their complexity or criticality, with a “G.“ Generally, other submittal items can be reviewed by the Contractors Quality Control SECTION 01 45 00.00 40 Page 2Provided by IHSNot for ResaleNo reproduction or networki
11、ng permitted without license from IHS-,-,-System. Only add a “G” to an item, if the submittal is sufficiently important or complex in context of the project.For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following
12、 the “G“ designation to indicate the approving authority. Codes for Army projects using the Resident Management System (RMS) are: “AE“ for Architect-Engineer; “DO“ for District Office (Engineering Division or other organization in the District Office); “AO“ for Area Office; “RO“ for Resident Office;
13、 and “PO“ for Project Office. Codes following the “G“ typically are not used for Navy, Air Force, and NASA projects.Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects.*Government approval is required for submittals with a “G“
14、designation; submittals not having a “G“ designation are for Contractor Quality Control approval.for information only. When used, a designation following the “G“ designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33
15、 00 SUBMITTAL PROCEDURES:SD-06 Test ReportsQuality Control Data; G; G, _Quality Control Coordinating Actions; G; G, _Quality Control Training; G; G, _Inspection Records; G; G, _Letters of Authority or Delegation; G; G, _Field Tests; G; G, _Factory Tests; G; G, _SD-07 CertificatesContractors Quality
16、Representative Qualifications; G; G, _Special Certifications; G; G, _1.2.1 Quality Assurance (QA) PlanAddress the following within the QA Plan:a. Description of the authority, responsibilities and coordinating procedures, of on-site/off-site quality assurance personnel, including those QA personnel
17、not under direct control of the Contractor.SECTION 01 45 00.00 40 Page 3Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-b. List personnel designated by the Contractor to accomplish the work required by the contract.c. Provide an appendix with a copy
18、of each form, report format, or similar record to be used in the QA program.d. Contractors organization that handles construction contract activities.e. Contractors operational plan for accomplishing and reviewing work controls, fabrication controls, certifications, and documentation of quality cont
19、rol operations, inspections, and test records, including those for subcontractors.f. Include within these provisions the methods to be used during the procurement cycle (order to delivery) for those materials or equipment that require source inspections, shop fabrications, or similar operations loca
20、ted separately from the work site.g. Description of on-site personnel training.h. Certification(s) of personnel, procedures, processes, and equipment.i. Non-Destructive Testing (NDT) requirements.j. Identification of independent certifying and testing laboratories.1.2.2 RecordsInclude all quality co
21、ntrol data; factory tests or manufacturers certifications, quality control coordinating actions; records of quality control training/certifications as well as routine hydrostatic, electrical continuity, grounding, welding, line cleaning, field tests and similar tests. Ensure Quality records are avai
22、lable for examination by the Contracting Officer.Furnish legible copies of the test and inspection records to the Contracting Officer. Ensure records cover work placement traceable to the contract schedule, specifications and drawings, and are verifiable.1.2.2.1 Narrative DescriptionSubmit for appro
23、val, the narrative description of an inspection system which provides for compliance with the quality requirements and technical criteria of the contract within 7 _ calendar days after notice to proceed.1.2.2.2 Monthly Performance ReportSubmit a monthly performance report that summarizes the quality
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGUFGS01450000402012QUALITYCONTROLPDF