1、*USACE / NAVFAC / AFCESA / NASA UFGS-02 62 16 (February 2010)-Preparing Activity: USACE SupersedingUFGS-02 62 16 (October 2007)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated April 2010*SECTION TABLE OF CONTENTSDIVISION 02 - EXISTING CONDITIONSSECTION 02 62 16COMMI
2、SSIONING AND DEMONSTRATION FOR SOIL VAPOR EXTRACTION (SVE) SYSTEMS02/10PART 1 GENERAL1.1 MEASUREMENT AND PAYMENT1.1.1 Baseline Monitoring1.1.2 Commissioning1.1.3 Demonstration1.2 REFERENCES1.3 GENERAL REQUIREMENTS1.3.1 Chemical Testing1.3.2 Submittal Requirements1.3.3 Sequencing and Scheduling1.4 SU
3、BMITTALS1.5 REGULATORY REQUIREMENTS1.5.1 Permits and Licenses1.5.2 Air Emissions1.5.3 Noise ControlPART 2 PRODUCTS (NOT APPLICABLE)PART 3 EXECUTION3.1 BASELINE MONITORING3.1.1 Temperature and Precipitation3.1.2 Barometric Pressure and Vadose Zone Pressure3.1.3 Soil Gas Monitoring3.1.4 Groundwater Le
4、vels3.1.5 Soil Boring Sampling3.1.6 Baseline Monitoring Report3.2 COMMISSIONING3.2.1 Commissioning Team and Checklists3.2.2 Tests3.3 DEMONSTRATION OF FULL-SCALE SYSTEM3.3.1 Period of Demonstration3.3.2 Hours of Operation and Downtime3.3.3 Operational Airflow RatesSECTION 02 62 16 Page 1Provided by I
5、HSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-3.3.4 Process Monitoring3.3.4.1 Meteorological Monitoring3.3.4.2 Vadose Zone Pressure Monitoring3.3.5 Groundwater Levels3.3.6 Process Air Stream and Equipment Monitoring3.3.6.1 Combustible Organic Vapor Monitoring3.
6、3.6.2 Airflow Rate Monitoring3.3.6.3 Air/Water Separator and Condensate3.3.6.4 Blower and Particulate Filter3.3.7 Vapor Stream Contaminant Level Monitoring3.3.7.1 Field Analysis of Vapor Stream Samples3.3.7.2 Laboratory Analysis of Vapor Stream Samples3.3.7.3 Full-Scale Demonstration Report- End of
7、Section Table of Contents -SECTION 02 62 16 Page 2Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-*USACE / NAVFAC / AFCESA / NASA UFGS-02 62 16 (February 2010)-Preparing Activity: USACE SupersedingUFGS-02 62 16 (October 2007)UNIFIED FACILITIES GUIDE
8、SPECIFICATIONSReferences are in agreement with UMRL dated April 2010*SECTION 02 62 16COMMISSIONING AND DEMONSTRATION FOR SOIL VAPOR EXTRACTION (SVE) SYSTEMS02/10*NOTE: This guide specification covers the requirements for commissioning and demonstration for soil vapor extraction (SVE) systems.Edit th
9、is guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information.Remove information and requirements not required in respective project, whether or not brackets are present.Comments and s
10、uggestions on this guide specification are welcome and should be directed to the technical proponent of the specification. A listing of technical proponents, including their organization designation and telephone number, is on the Internet.Recommended changes to a UFGS should be submitted as a Crite
11、ria Change Request (CCR).*PART 1 GENERAL*NOTE: Commissioning is performed after construction has been completed, and is an ordered process for testing and start-up of SVE system equipment. During commissioning, pre-commissioning checklists are completed, and functional performance tests are performe
12、d to test individual components of the system and subsystems. Demonstration serves as a prove-out period. The purpose of the demonstration is to show that the SVE system, as a whole, is ready to be put into service.This guide specification should be used in conjunction with Section 02 01 50 OPERATIO
13、N, MAINTENANCE, AND PROCESS MONITORING FOR SOIL VAPOR SECTION 02 62 16 Page 3Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-EXTRACTION SYSTEMS. For small-scale SVE projects, editing and combining this section with Section 02 01 50 should be consider
14、ed. Additional guidance on start-up of SVE systems can be found in EM 1110-1-4001 SOIL VAPOR EXTRACTION AND BIOVENTING, dated Nov 1995.This guide specification should be coordinated with other sections that may also include commissioning requirements for SVE system components, to avoid unnecessary d
15、uplication of requirements.*1.1 MEASUREMENT AND PAYMENT*NOTE: If there is a separate Measurement and Payment Section, edited versions of these paragraphs should be inserted in that section. Coordinate these paragraphs with the bidding schedule.Separate, lump sum prices are generally recommended for
16、Baseline Monitoring, Commissioning, and Demonstration. However it is also recommended that bidders be required to provide unit cost amounts for laboratory testing for chemical data. Unit costs will provide a basis for negotiating for additional tests, if determined that more testing than was origina
17、lly anticipated is required. Under the pricing structure shown below, costs for laboratory analysis are covered under Section 01 35 45.00 10 CHEMICAL DATA QUALITY CONTROL.It is recommended that the bid sheet be structured so that a portion of the payment (i.e., at least 30 percent) for construction
18、of the SVE system be withheld at least until the full-scale demonstration has been completed. If acceptance of the SVE system is granted before the bugs are worked out, there may not be sufficient incentive for the Contractor to finish fixing problems with the SVE system.*Measurement shall be based
19、on completion of contract requirements. Payment will be at the respective contract prices in the bidding schedule.1.1.1 Baseline MonitoringCompensation shall be a lump sum price for Baseline Monitoring. Physical and chemical testing performed in the field, and sampling shall be included in this pric
20、e. Cost for laboratory analysis of samples is covered in Section 01 35 45.00 10 CHEMICAL DATA QUALITY CONTROL and is not included in this price.1.1.2 Commissioning*NOTE: Laboratory analysis of samples is usually not required during Commissioning. Vapor stream SECTION 02 62 16 Page 4Provided by IHSNo
21、t for ResaleNo reproduction or networking permitted without license from IHS-,-,-monitoring during commissioning typically involves using a field instrument, such as a flame ionization detector (FID).*Compensation shall be a lump sum price for completion of Commissioning. Physical and chemical testi
22、ng performed in the field, and sampling shall be included in this price. Laboratory analysis of samples will be not be _ required during Commissioning.1.1.3 Demonstration*NOTE: Vapor stream monitoring during the full-scale demonstration typically involves using a field instrument, such as an FID, in
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ARMYUFGS0262162010COMMISSIONINGANDDEMONSTRATIONFORSOILVAPOREXTRACTIONSVESYSTEMS 土壤 蒸汽 提取 SVE 系统 示范 PDF

链接地址:http://www.mydoc123.com/p-449531.html