1、*USACE / NAVFAC / AFCESA / NASA UFGS-02 54 23 (February 2010)-Preparing Activity: USACE SupersedingUFGS-02 54 23 (April 2006)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated April 2010*SECTION TABLE OF CONTENTSDIVISION 02 - EXISTING CONDITIONSSECTION 02 54 23SOIL WA
2、SHING THROUGH SEPARATION/SOLUBILIZATION02/10PART 1 GENERAL1.1 MEASUREMENT AND PAYMENT1.1.1 Measurement1.1.2 Payment1.1.2.1 Treatability Studies1.1.2.2 Demonstration Test Run1.1.2.3 Feed Oversize Materials Treatment and/or Disposal1.1.2.4 Feed Materials Treatment1.1.2.5 Other Work Items1.1.3 Excess Q
3、uantity1.1.4 Reprocessing1.2 REFERENCES1.3 SYSTEM DESCRIPTION1.3.1 Soil Washing Treatment Process1.3.2 Soil Washing Treatment Plant1.3.2.1 Soil Preparation and Feed System1.3.2.2 Soil Washing and Separation System1.3.2.3 Spent Washwater Treatment System1.3.2.4 Plant Supporting System1.3.3 Performanc
4、e Requirements1.3.4 Cut Size Requirement1.3.5 Installation Requirements1.3.6 Results of Previously Conducted Treatability Studies1.3.7 Utilities1.3.8 Spent Washwater Treatment and Disposal Requirements1.3.9 Solid Waste Treatment and Disposal Requirements1.3.10 Emissions and Dust Control1.3.11 Noise
5、Control1.3.12 Sampling, Monitoring, and Control Requirements1.3.13 Contaminated Material Measurement Accuracy Requirements1.3.14 Mobilization1.3.15 Demobilization1.3.16 Submittal Requirements1.3.17 Other Submittal Requirements1.4 SUBMITTALSSECTION 02 54 23 Page 1Provided by IHSNot for ResaleNo repro
6、duction or networking permitted without license from IHS-,-,-1.5 QUALIFICATIONS1.6 DELIVERY, STORAGE, AND HANDLING1.7 SITE CONDITIONS1.7.1 Environmental Requirements1.7.2 Existing ConditionsPART 2 PRODUCTS2.1 MATERIALS AND EQUIPMENT2.1.1 Water Supply2.1.2 Reagent/Additive Certificates of Analyses2.2
7、 MIXES2.3 SAMPLES FOR TREATABILITY STUDIES2.4 EQUIPMENTPART 3 EXECUTION3.1 PREPARATION3.1.1 Stockpiles of Contaminated Materials3.1.1.1 Liner3.1.1.2 Cover3.1.1.3 Diversion Measures3.1.1.4 Stockpile Leachate3.1.2 Foundations3.2 ERECTION, INSTALLATION, AND DEMOBILIZATION3.3 OPERATION3.3.1 Different Ty
8、pes of Contamination and Materials3.3.2 Stockpile Management3.3.2.1 Feed Oversize3.3.2.2 Feed Material3.3.2.3 Treated Materials3.3.2.4 Process Sludge3.3.3 Auxiliary Requirements for System Operations3.3.4 Management of Reagents/Additives3.3.5 Change of Operating Conditions3.3.6 Management of Treatme
9、nt Plant Wastewater3.3.7 Daily Operations Report3.4 TESTS3.4.1 Post Treatment Testing3.4.2 Reprocessing3.4.3 Government Testing3.5 GOVERNMENT INSPECTION3.6 DEMONSTRATION3.6.1 Field Demonstration3.6.2 Full Scale Processing Equipment3.6.3 Sampling Locations3.6.4 Testing3.6.5 Commencement of Full Scale
10、 Operation3.7 PROCESS MATERIALS MANAGEMENT- End of Section Table of Contents -SECTION 02 54 23 Page 2Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-*USACE / NAVFAC / AFCESA / NASA UFGS-02 54 23 (February 2010)-Preparing Activity: USACE SupersedingUF
11、GS-02 54 23 (April 2006)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated April 2010*SECTION 02 54 23SOIL WASHING THROUGH SEPARATION/SOLUBILIZATION02/10*NOTE: This guide specification covers the requirements for removal of heavy metals/inorganics, organics, and radio
12、active wastes by water-based soil washing.Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information.Remove information and requirements not required in respective project, w
13、hether or not brackets are present.Comments and suggestions on this guide specification are welcome and should be directed to the technical proponent of the specification. A listing of technical proponents, including their organization designation and telephone number, is on the Internet.Recommended
14、 changes to a UFGS should be submitted as a Criteria Change Request (CCR).*PART 1 GENERAL*NOTE: This UFGS provides the framework for developing a project-specific soil washing specification. It should be modified as necessary for a given site, to incorporate the conditions, soil washing technology,
15、and regulatory requirements which are specific to the site.The appropriate regulatory agencies should be consulted to obtain their approval of work plans, specifications, drawings, and on the sampling methodology for a soil washing treatment project. The maximum allowable quantity of the treated mat
16、erials or the process sludge from which one SECTION 02 54 23 Page 3Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-composite sample must be taken for characterization and/or compliance should also be verified. This maximum allowable quantity per comp
17、osite sample collection may effect the size of a stockpile, and subsequently, determine the number of days required to reach this quantity based on the daily generation of the treated materials or the process sludge.The soil washing operation considered in this section starts with the raw contaminat
18、ed material piles; continues through preparation, feeding, washing, separation, stockpiling, waste (solid, liquid and/or gaseous) treatment and disposal; ends at the treated clean material piles. Refer to Section 02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL for requirements related to e
19、xcavation of the contaminated materials and redeposition (or backfilling) of the treated clean materials. Refer to Section 02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS for requirements relevant to offsite transportation and disposal.Additional references from Federal, state, and local
20、 regulatory requirements; utility company regulations; and applicable codes and standards published by scientific and engineering institutions should be included where appropriate in the body of the specification. Some of the potentially applicable Federal regulations are listed as follows:Toxicity
21、Characteristic Leaching Procedure (TCLP)Recording and Reporting Occupational Injuries and IllnessesOccupational Safety and Health StandardsSafety and Health Regulations for ConstructionPermittingNational Primary and Secondary Ambient Air Quality StandardsNational Emission Standards for Hazardous Air
22、 Quality PollutantsState and Local Air Quality Standards National Pollution Discharge Elimination System (NPDES) Discharge Limitations and Permit ProceduresHazardous Waste Identification and Standards Applicable to Generators, Transporters, and Owners and Operators of Treatment, Storage and Disposal
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ARMYUFGS0254232010SOILWASHINGTHROUGHSEPARATIONSOLUBILIZATION 土壤 彻底 清洗 PDF

链接地址:http://www.mydoc123.com/p-449525.html