1、05-11 23 51 00 - 1 SECTION 23 51 00 BREECHINGS, CHIMNEYS, AND STACKS SPEC WRITER NOTES: 1. Delete between /-/ if not applicable to project. Also delete any other item or paragraph not applicable in the section and renumber the paragraphs. 2. This section does not include free-standing chimneys. PART
2、 1 GENERAL: 1.1 DESCRIPTION: This section specifies flue gas exhaust system and all accessories from the boiler outlet to the stack outlet to the atmosphere. Flue gas recirculation (FGR) ductwork (if required by burners furnished) is also specified. 1.2 RELATED WORK: A. Section 07 60 00, FLASHING an
3、d SHEET METAL: Roof Penetrations. B. Section 13 05 41, SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL COMPONENTS, C. Section 23 05 11, COMMON WORK RESULTS FOR HVAC and STEAM GENERATION. D. Section 23 05 51, NOISE and VIBRATION CONTROL FOR BOILER PLANT. E. Section 23 07 11, HVAC, PLUMBING, and BOI
4、LER PLANT INSULATION. F. Section 23 08 00, COMMISSIONING OF HVAC SYSTEMS. Requirements for commissioning, systems readiness checklists, and training /G. Section 23 52 39, FIRE-TUBE BOILERS: Economizers/ /H. Section 23 52 33, WATER-TUBE BOILERS: Economizers/ /I. Section 23 09 11, INSTRUMENTATION and
5、CONTROL FOR BOILER PLANT: Boiler Draft Control System./ 1.3 QUALITY ASSURANCE: A. Provide scale drawings showing nominal dimensions and weight of the systems. B. Boiler and burner manufacturer shall review complete system from boiler flue gas outlet to stack outlet to atmosphere and advise the Gover
6、nment of any changes required to meet boiler and burner performance requirements. Note the altitude of plant site. C. If a double wall, factory-fabricated, positive pressure breeching and stack system is provided, the manufacturer shall completely engineer the entire system and provide all component
7、s. Manufacturers representative shall provide installation instructions prior to start of construction, train the installers and certify in writing to the Resident Engineer Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-05-11 23 51 00 - 2 (RE) that
8、the entire installation complies with the official standards of the manufacturer and with the project specifications. D. Flue gas recirculation ductwork shall be designed and provided by the burner manufacturer. E. Conform to NFPA 54 and NFPA 31 for installation of fuel burning equipment and applian
9、ces. 1.4 SUBMITTALS: A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, and SAMPLES. B. Design, materials, weights, construction, pressure and temperature limitations of breeching and stack systems, flue gas recirculation system. /Seismic design data. / C. Drawings showing a
10、ll components, system arrangement and dimensions. D. Design, construction, allowable movements, movement forces, pressure and temperature limitations of expansion joints. E. Damper design, construction, pressure and temperature limitations, pressure loss at design flow, and leakage of closed damper.
11、 F. Support designs, locations and loads for entire assembly. /Seismic design data. / G. Written statement from boiler/burner manufacturer that the design of the system is satisfactory to achieve the required boiler/burner performance. 1.5 APPLICABLE PUBLICATIONS: A. The publications listed below fo
12、rm a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only. B. American Institute of Steel Construction (AISC): Steel Construction Manual, Thirteenth Edition C. ASTM International (ASTM): A36/A36M-08 Standard Specification for
13、Carbon Structural Steel A242/A242M-04(2009) Standard Specification for High-Strength Low-Alloy Structural Steel A307-07b . Standard Specification for Carbon Steel Bolts and Studs, 60,000 psi Tensile Strength A563-07a . Standard Specification for Carbon and Alloy Steel Nuts A568/A568M-09a . Standard
14、Specification for Steel, Sheet, Carbon, and High-Strength, Low-Alloy, Hot-Rolled and Cold-Rolled, General Requirements For D. American Welding Society (AWS): Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-05-11 23 51 00 - 3 Dl.l/D1.1M-2010 Structura
15、l Welding Code-Steel E. Manufacturers Standardization Society of the Valves and Fittings Industry (MSS): SP-58-2009 . Pipe Hangers and Supports Materials, Design, Manufacture, Selection, Application, and Installation F. National Fire Protection Association: NFPA 54-2006 . National Fuel Gas Code NFPA
16、 31-2006 . Standard for the Installation of Oil-Burning Equipment PART 2 PRODUCTS: 2.1 BREECHING, STACKS, FGR DUCTWORK: SPEC WRITER NOTES: 1. Coordinate the breeching and stack design (diameter and height) with the draft requirements of the boiler/burner. The contract drawings must show breeching an
17、d stacks in plan and sections and show diameters and heights. 2. The stack height must be sufficient to avoid flue gas being entrained into the boiler room make-up air or impinging on nearby buildings. 3. Where multiple boilers are connected to a common breeching and stack, the design should be base
18、d on boilers operating at the required steam output to serve peak load conditions plus a standby boiler in the pre-purge cycle. In this situation, the media in the breeching and stack is a mixture of hot flue gas and relatively cool purge air. A. Refer to drawings for arrangement and dimensions, exc
19、ept FGR ductwork shall be designed by the burner manufacturer. Connections to boilers and economizers must comply with the written recommendations of the boiler and economizer manufacturers. Ninety-degree tee sections are not permitted. Intersections must be made with lateral tees. SPEC WRITER NOTE:
20、 Add wind-loading information. Edit out seismic requirements in non-seismic zones. B. Service: Design for continuous 315 C (600 F), 12 kPa (50 inches WC) positive and negative internal pressure, wind-loading for outside stacks _. /Design system and supports for seismic loads in accordance with Secti
21、on 13 05 41, SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL COMPONENTS./ Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-05-11 23 51 00 - 4 SPEC WRITER NOTES: 1. Only UL-listed pre-engineered double- wall systems should be utilized in the building
22、 beyond the perimeter of the boiler plant. 2. Select pre-engineered, pre-fabricated double-wall system (Par. C) or custom designed single wall system (Par. D) for the boiler plant. Design details for the custom-designed single wall system must be shown on the drawings. C. Pre-engineered, Pre-Fabrica
23、ted, Double-Wall System: 1. Complete factory-built system, all components and installation engineered and provided by manufacturer of system. SPEC WRITER NOTE: Allow air space with no insulation on outside stack only if the stack gas cooling and consequent reduction in draft will allow specified bur
24、ner performance. 2. Provide double wall metal stacks, tested to UL 103 UL 127 UL 641 and UL listed, for use with building heating equipment, in compliance with NFPA 211. 3. Corrosion-resistant steel, double-wall, circular cross section, positive pressure, blanket insulation between walls. /For stack
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- VA2351002011BREECHINGSCHIMNEYSANDSTACKSPDF

链接地址:http://www.mydoc123.com/p-1074924.html