REG NASA-LLIS-1398--2004 Lessons Learned SWIFT Power Control Board Harness Wire Reversal.pdf
《REG NASA-LLIS-1398--2004 Lessons Learned SWIFT Power Control Board Harness Wire Reversal.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1398--2004 Lessons Learned SWIFT Power Control Board Harness Wire Reversal.pdf(4页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1398Lesson Info:a71 Lesson Number: 1398a71 Lesson Date: 2004-01-02a71 Submitting Organization: GSFCa71 Submitted by: Dennis S. Lee/Joe DezioSubject: SWIFT Power Control Board Harness Wire Reversal Abstract: Serious damage to an instruments heater control electronics resulted f
2、rom incorrect wiring within the interface harness. Efforts to expedite the I however, risks were expected to be mitigated by the Safe-to-Mate procedure, which was expected to verify compliance with the ICD. These “time saving” decisions and acceptance of excess risk resulted not only in damage to th
3、e instrument but also a 4-month schedule delay.Description of Driving Event: During instrument integration, a GSE power harness seriously damaged SWIFT heater control electronics. This mishap occurred on the Burst Alert Telescope (BAT) Power Control Board (PCB). The failure investigation identified
4、the root cause as a manufacturing error (miswire) in the GSE power interface harness. The PCB GSE harness was built and tested with a 28-volt reversed polarity in the power interface. The SWIFT Project desired to expedite the hardware I&T schedule. As a result, the PCB GSE power harness was accepted
5、 “as is” from the harness fabrication and test facility, without the proper documentation and QA review. At the time, it was rationalized that the Safe-To-Mate procedure would verify compliance to the Interface Control Document (ICD) and the safe flight hardware integration activities. As another ti
6、me saving approach, review and sign-off requirements for SWIFT integration work orders were reduced to accelerate schedule. This approach eliminated the need for system and discipline engineering signatures. Changing work order signature authority is inconsistent with GSFC policy for the control and
7、 authorization of flight hardware work orders. Following the PCB power-on fault, the GSFC policy was reinstated with signatures from quality assurance, systems Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-engineer and flight hardware leads. During
8、 the GSE electrical integration to the SWIFT PCB, the Safe-To-Mate procedure was performed, but not completed due to problems with a separate flight component, the Image Processor. To accelerate the integration schedule, the SWIFT Image Processor was being integrated in parallel with the PCB. Confus
9、ion ensued between the two integration procedures, and the PCB, GSE electrical Safe-To-Mate was not entirely finished. As a result of the application of reverse power, the SWIFT flight PCB sustained significant damage, which required a component rework cycle and a 4-month project schedule delay. The
10、re were several important situations and conditions, which resulted the SWIFT PCB power-on fault. These circumstances are the basis of the lessons learned. Each of these situations contributed to the PCB flight hardware damage, and individually, each could have prevented the failure condition. Overa
11、ll, a disciplined and careful system engineering and quality assurance approach can preclude damage to flight hardware electronic during power interface harness testing. Lesson(s) Learned: 1. During flight hardware integration, priority and precedence must be given to completion of the electrical po
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS13982004LESSONSLEARNEDSWIFTPOWERCONTROLBOARDHARNESSWIREREVERSALPDF

链接地址:http://www.mydoc123.com/p-1019037.html