REG NASA-LLIS-1084--2000 Lessons Learned - Mishap Investigation Board Report Findings for the GSFC Building 24 Pressurized Steam Line Close Call of August 19 1999.pdf
《REG NASA-LLIS-1084--2000 Lessons Learned - Mishap Investigation Board Report Findings for the GSFC Building 24 Pressurized Steam Line Close Call of August 19 1999.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1084--2000 Lessons Learned - Mishap Investigation Board Report Findings for the GSFC Building 24 Pressurized Steam Line Close Call of August 19 1999.pdf(7页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1084Lesson Info:a71 Lesson Number: 1084a71 Lesson Date: 2000-03-24a71 Submitting Organization: GSFCa71 Submitted by: Suzanne Johnson / Eric RaynorSubject: Mishap Investigation Board Report Findings for the GSFC Building 24 Pressurized Steam Line Close Call of August 19, 1999 A
2、bstract: The primary cause of this Central Power Plant (CPP) pressurized steam line incident was that no one took responsibility for coordinating all aspects of executing the outage.Recommendations included revising procedures, conducting an independent safety audit of the CPP, Developing as-built d
3、rawings for the CPP, and establishing “Locked And Tagged Out” processes and requirements.Description of Driving Event: On August 19, 1999, contractors were removing concrete from around steam lines with a jackhammer. These steam lines should have been de-energized prior to commencement of the work b
4、ut one line was found to still be pressurized with 100 psi steam. Background: The pressurized steam line incident occurred in and around Building 24, the Goddard Space Flight Center (GSFC) Central Power Plant (CPP), Steam Manhole (STW # 30 and an excavated hole outside of the north side of the CPP.A
5、 work request (#8002) was submitted in June 1998 to reroute the Condensate and High Pressure Drip (HPD) lines entering Building 24 at the north wall into the blow-down pit. The corrosive atmosphere in the pit was degrading the pipes so plans called for rerouting them above ground and bringing them t
6、hrough the wall above the pit. The plans developed to complete this task would include excavation of the site to expose the lines and the cutting and rerouting of the lines above ground. Detailed drawings and plans for this task were developed and in April 1999 the work commenced. After excavation o
7、f the site, it was discovered that the concrete kicker that held the pipes in place was much larger and closer to the wall than anticipated. This required a Field Change Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Request (#8002-1) to allow for j
8、ackhammer removal of the concrete kicker surrounding the condensate and HPD lines so that the necessary modifications could be made. The Project Manager (PM) for the re-routing project submitted a Utility Outage Request (UOR) to de-energize the condensate, the HPD and the adjoining High Pressure Ste
9、am (BPS) line prior to removal of the concrete. Note that the concrete kicker in question surrounded all three pipes. The contractors never intended to jackhammer the concrete around the HPS line but requested it to be de-energized as a precaution.The UOR submitted for de-energizing the condensate,
10、HPD and BPS line requested the outage for 7:00 a.m. on August 19, 1999 through 3:30 p.m. August 20, 1999. Securing these three lines required actions on the part of the Mechanical Maintenance Shop (MMS) and the CPP. The back of the UOR is the Utility Outage Safe Clearance Plan (UOSCP). One section o
11、f the UOSCP is reserved for the organization with the action to fill out what procedure is necessary to complete the outage. This section for the subject UOSCP was filled out by the MMS supervisor and included a brief statement about what action was necessary by CPP personnel. A CPP representative d
12、id not fill out the CPP procedure portion of the form, despite a note from the MMS supervisor requesting the CPP supervisor to review the section and sign off.The correct method for de-energizing the BPS line consists of closing the appropriate valves in STMH #30 and closing valves #1 through #3. Af
13、ter all valves are closed, the line must be “blown down“, that is, a pressure relief valve should be opened in the blow-down pit to allow the existing steam to escape.Contractor personnel involved in the excavation and pipe re-routing project were the Construction Manager (CM), the Project Manager (
14、PM), and the excavators, jack-hammerers, and pipe fitters. Personnel that were responsible for de-energizing the steam lines being worked on were civil servants from the MMS and the CPP.The following incident description describes the sequence of events that happened August 19, 1999 as best as the M
15、ishap Investigation Board (MIB) could reconstruct from witness testimony. Although many events were described by more than one witness as having occurred, the timeframes and order in which they occurred were often in conflict. The MIB felt that the descriptions of events were more accurate than the
16、times associated with them by individuals memories and therefore based this incident description on the most common version of events.On the morning of August 19, 1999, the contractor began preparations to commence jack-hammering the concrete kicker. Preparations included clearing debris from the ex
17、cavated hole, setting up an air compressor to power the jackhammer and talking with CPP personnel about the UOR. The contractors on-site supervisor and the CPP Maintenance Leader walked around inside the CPP identifying which valves needed to be shut off. Testimony is conflicting on whether or not t
18、hey discussed the need to secure the HPS line at this time.Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Around the same time, MMS workers entered STMH #30 and closed, locked and tagged out (LOTO) the appropriate valves. After the valves were secur
19、ed a MMS worker entered the CPP to inform them that the valves under MMS control were closed. While in STMH #30, MMS personnel discovered a leaking valve gasket on the line going from STMH #30 into building 4 that needed repair. This leaking valve gasket had no impact on the section of line being de
20、-energized. MMS personnel then proceeded to STMH # 15 to secure valves so that the gasket could be repaired later in the day. This is a common procedure in the MMS known as a piggy-back job, where the MMS takes advantage of an already existing UOR to complete some of their work.At some time on the m
21、orning of August 19, 1999, the CPP Maintenance Leader, an Operations Leader and a Boiler Operator began the task of closing valves. According to testimony, the Maintenance Leader was leading the task and instructing the Boiler Operator in which valves to close. The condensate and BPD lines were repo
22、rtedly secured without incident. Due to the complexity of the main north header lines, the lack of “as built“ CPP drawings, the lack of a procedure for securing the north side of the CPP and the lack of valve labels, closure of the BPS line required that the personnel involved trace the north header
23、 line down to identify the valves that needed to be closed. The first valve closed was Steam System Valve (SSV)-003. The second valve closed was SSV-0 17.While CPP personnel were in the process of closing the HPS valves, MMS personnel returned to STMH# 30 to replace the leaking valve gasket going in
24、to Bldg 4. They noticed the HPS line was still hot. It should have cooled off by this time if the line had been properly secured in the morning per the UOR. The MMS Shift Leader testified that they also noticed that the subcontractor was jack-hammering at this time. The MMS workers went to the CPP t
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS10842000LESSONSLEARNEDMISHAPINVESTIGATIONBOARDREPORTFINDINGSFORTHEGSFCBUILDING24PRESSURIZEDSTEAMLINECLOSECALLOFAUGUST191999PDF

链接地址:http://www.mydoc123.com/p-1018723.html