ASTM D5786-1995(2006) Standard Practice for (Field Procedure) for Constant Drawdown Tests in Flowing Wells for Determining Hydraulic Properties of Aquifer Systems《用于测定含水层系统水硬性的流动井中.pdf
《ASTM D5786-1995(2006) Standard Practice for (Field Procedure) for Constant Drawdown Tests in Flowing Wells for Determining Hydraulic Properties of Aquifer Systems《用于测定含水层系统水硬性的流动井中.pdf》由会员分享,可在线阅读,更多相关《ASTM D5786-1995(2006) Standard Practice for (Field Procedure) for Constant Drawdown Tests in Flowing Wells for Determining Hydraulic Properties of Aquifer Systems《用于测定含水层系统水硬性的流动井中.pdf(3页珍藏版)》请在麦多课文档分享上搜索。
1、Designation: D 5786 95 (Reapproved 2006)Standard Practice for(Field Procedure) for Constant Drawdown Tests in FlowingWells for Determining Hydraulic Properties of AquiferSystems1This standard is issued under the fixed designation D 5786; the number immediately following the designation indicates the
2、 year oforiginal adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. Asuperscript epsilon (e) indicates an editorial change since the last revision or reapproval.1. Scope1.1 This practice covers the methods for controlling d
3、raw-down and measuring discharge rates and head to analyze thehydraulic properties of an aquifer or aquifers.1.2 This practice is used in conjunction with analyticalprocedures such as those of Jacob and Lohman (1)/(2),2andHantush (3)/(4).1.3 The appropriate field and analytical procedures fordetermi
4、ning hydraulic properties of aquifer systems are se-lected as described in Guide D 4043.1.4 This standard does not purport to address all of thesafety concerns, if any, associated with its use. It is theresponsibility of the user of this standard to establish appro-priate safety and health practices
5、 and determine the applica-bility of regulatory limitations prior to use.1.5 This practice offers a set of instructions for performingone or more specific operations. This document cannot replaceeducation or experience and should be used in conjunctionwith professional judgment. Not all aspects of t
6、his practice maybe applicable in all circumstances. This ASTM standard is notintended to represent or replace the standard of care by whichthe adequacy of a given professional service must be judged,nor should this document be applied without consideration ofa projects many unique aspects. The word
7、“Standard” in thetitle of this document means only that the document has beenapproved through the ASTM consensus process.2. Referenced Documents2.1 ASTM Standards:3D 653 Terminology Relating to Soil, Rock, and ContainedFluidsD 4043 Guide for Selection of Aquifer Test Method inDetermining Hydraulic P
8、roperties by Well TechniquesD 4750 Test Method for Determining Subsurface LiquidLevels in a Borehole or Monitoring Well (ObservationWell)3. Terminology3.1 DefinitionsFor definitions of terms used in this prac-tice, see Terminology D 653.4. Summary of Practice4.1 This practice describes the field pro
9、cedures for conduct-ing an aquifer test on a well that is flowing, that is, the head inthe well remains above the top of the well casing. This methodinvolves inducing a constant drawdown and measuring thevarying discharge rate from the control well.5. Significance and Use5.1 Constant drawdown test p
10、rocedures are used with ap-propriate analytical procedures to determine transmissivity,hydraulic conductivity, and storage coefficient of aquifers.6. Apparatus6.1 Various types of equipment can be used to measure theflow rate of the well. The equipment shall be sized so that itdoes not constrict the
11、 flow rate from the well.6.2 An apparatus shall be placed on the control welldischarge line such that the well can be shut in to prevent flowprior to conducting this field procedure and so that theapparatus will not constrict flow from the well when it isallowed to flow.6.3 Head measurements can be
12、made using one of thefollowing apparatuses:6.3.1 StandpipeA pipe or piece of well casing may beinstalled to extend above the elevation of the discharge. Thisstandpipe will also extend above the elevation of the head in1This practice is under the jurisdiction of ASTM Committee D18 on Soil andRock and
13、 is the direct responsibility of Subcommittee D18.21 on Ground Water andVadose Zone Investigations.Current edition approved July 1, 2006. Published July 2006. Originally approvedin 1995. Last previous edition approved in 2000 as D 5786 95 (2000).2The boldface numbers in parentheses refer to a list o
14、f references at the end ofthis standard.3For referenced ASTM standards, visit the ASTM website, www.astm.org, orcontact ASTM Customer Service at serviceastm.org. For Annual Book of ASTMStandards volume information, refer to the standards Document Summary page onthe ASTM website.1Copyright ASTM Inter
15、national, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959, United States.the control well. This standpipe will allow for direct measure-ment of the water level following methods described in TestMethod D 4750.6.3.2 Pressure MeasurementA pressure gauge (mechani-cal gage, manomete
16、r, or pressure transducer) may be installedbelow the shut-in mechanism in the control well. Determinethe head elevation by adding the pressure reading (expressed inthe height of the water) to the elevation of the sensor of thepressure gage.6.4 Control WellThis practice requires that water flowfrom a
17、 single well. This well, known as the control well, shallbe drilled and completed such that it transmits water from theaquifer (usually the entire thickness of the aquifer) as effi-ciently as possible to reduce head loss between the aquifer andthe well. Well development should be as complete as poss
18、ibleto eliminate additional production of sediments (aquifer par-ticles or drill cuttings) and consequent changes in well effi-ciency during the test.7. Procedure7.1 Pretest Procedures:7.1.1 Select Aquifer Test MethodDevelop a conceptualmodel of the site hydrogeology and select the appropriateaquife
19、r test method according to Guide D 4043. Observe therequirements of the selected test method with regard tospecifications for the control well and observation wells.7.1.2 Field ReconnaissanceMake a field reconnaissanceof the site before conducting the test to collect as much detailas possible on the
20、 depth, continuity, extent, and preliminaryestimates of the hydrologic properties of the aquifers andconfining beds. Note the location of existing wells and water-holding or conveying structures that might interfere with thetest. Turn off nearby wells well before the test, and disableautomatic pump
21、controls throughout the anticipated test period.Alternately, it may be necessary to pump some nearby wells orallow them to flow throughout the test. If so, the discharge shallbe at a constant rate, and shall not be started or stopped duringthe test and prior to the test for a duration at least equal
22、 to thatof the test. The control well should be equipped with a pipelineor conveyance structure adequate to transmit water away fromthe test site, such that the structure does not impede the flow ofwater from the control well.7.1.3 Construction of Control WellScreen the control wellthroughout the fu
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASTMD578619952006STANDARDPRACTICEFORFIELDPROCEDUREFORCONSTANTDRAWDOWNTESTSINFLOWINGWELLSFORDETERMININGHYDRAULICPROPERTIESOFAQUIFERSYSTEMS

链接地址:http://www.mydoc123.com/p-520693.html