1、Designation: D 2995 99 (Reapproved 2009)Standard Practice forEstimating Application Rate of Bituminous Distributors1This standard is issued under the fixed designation D 2995; the number immediately following the designation indicates the year oforiginal adoption or, in the case of revision, the yea
2、r of last revision. A number in parentheses indicates the year of last reapproval. Asuperscript epsilon () indicates an editorial change since the last revision or reapproval.This standard has been approved for use by agencies of the Department of Defense.1. Scope1.1 This practice covers the determi
3、nation of transverse andlongitudinal application rate of asphalt distributors in gallonsper square yard (or litres per square metre).1.2 This standard does not purport to address all of thesafety concerns, if any, associated with its use. It is theresponsibility of the user of this standard to estab
4、lish appro-priate safety and health practices and determine the applica-bility of regulatory limitations prior to use.1.3 The values given in inch-pound units are to be regardedas the standard. The SI values given in parentheses are forinformation purposes only.2. Summary of Practice2.1 Test Method
5、A:2.1.1 Pre-weighed calibration pads are placed on the surfaceof the roadway in front of the distributor to be calibrated. Theasphalt distributor to be calibrated is driven over the calibrationpads while spraying asphalt. The calibration pads are removedfrom the roadway and reweighed. The weight of
6、asphaltapplied to the pads is determined by subtraction and the rate ofapplication is calculated.2.2 Test Method B:2.2.1 Containers are placed under each nozzle of a bitumi-nous distributor and bituminous material is sprayed into thecontainers for a known period of time. The volume ofbituminous mate
7、rial sprayed after this period is calculated. Thetransverse uniformity of bituminous material sprayed on thepavement is obtained from this calculation and the distributionof bituminous material applied longitudinally on the pavementis calculated as a function of the distributor velocity.3. Significa
8、nce and Use3.1 The amount of bituminous material applied to a pave-ment surface using a bituminous distributor can be estimatedusing the described procedure.4. Apparatus4.1 Test Methods A and B:4.1.1 Balance, sensitive to 0.1 g.4.1.2 Weighing Box or Balance Shield, to protect balancefrom wind when t
9、he balance is in use at the project site (seeFig. 1).4.1.3 Balance Table and Work Table, for weighing.4.2 Test Method B:4.2.1 Elliptical Containers, measuring approximately 3.5 in.(88.9 mm) along the short axis and 9 in. (228.6 mm) along thelong axis of the ellipse and 8 in. (203.2 mm) in height, ca
10、pableof an internal volume of approximately 1 gal.4.2.2 Rubber Bands, capable of a snug fit when stretchedaround the elliptical containers.4.2.3 Stopwatch, capable of recording to the nearest 0.1 s.5. Materials5.1 Test Method A:1This practice is under the jurisdiction of ASTM Committee D04 on Road a
11、ndPaving Materials and is the direct responsibility of Subcommittee D04.24 onBituminous Surface Treatments.Current edition approved June 1, 2009. Published July 2009. Originally approvedin 1971. Last previous edition approved in 2004 as D 2995 04.FIG. 1 Weighing Box and Balance1Copyright ASTM Intern
12、ational, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959, United States.5.1.1 Geotextile Pads,2weighing a minimum of 8 oz/yd2and measuring 12 in. (304.8 mm) by 12 in. (304.8 mm).5.1.2 Aluminized Duct Tape, measuring 2 in. (50.8 mm)wide and 6 in. (152.4 mm) long.5.1.3 Butcher Pap
13、er #50,3measuring 30 in. (762 mm) by950 ft, for temporary protection of geotextile pads duringcalibration.5.2 Test Method B:5.2.1 Plastic Bags, capable of fitting inside the ellipticalcans but of sufficiently larger dimension to allow folding overthe edge of the elliptical containers once placed ins
14、ide.6. Procedure (Transverse Application Rate)6.1 Test Method A:6.1.1 Select enough of the geotextile fabric pads so thatwhen placed end-to-end on the roadway a continuous strip iscreated across the width of the roadway to be sprayed withasphalt.6.1.2 Create a loop with the duct tape with the adhesi
15、ve sidefacing out. Place two loops of duct tape on one edge of each ofthe geotextile fabric pads.6.1.3 Obtain the weight of the pad and tape assembly to thenearest 0.1 g.6.1.4 Place the pad assembly with the tape facing down onthe roadway so the taped edge is facing the distributor. Applypressure to
16、 the taped pad to secure it to the roadway. Continuethis operation for the remaining pads for the entire widthdesired for calibration.6.1.5 Place two sheets of the butcher paper over the padassemblies in the area where the distributor tires will fall on thepad assemblies as shown in Fig. 2. These sh
17、eets should bepositioned so they protect the pad assemblies from damage bythe distributor tires as the truck passes over the pad assemblies.The sheets of butcher paper should adhere to the front and reartires as the distributor passes over the pad assemblies leavingthe pad assemblies available to re
18、ceive the asphalt as it issprayed onto the roadway surface.6.1.6 As soon as the distributor has passed over the calibra-tion pad assemblies, remove each pad assembly from theroadway.6.1.7 Weigh each pad to the nearest 0.1 g. Record the weightof each pad and the pad position on the roadway on the rep
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASTMD299519992009STANDARDPRACTICEFORESTIMATINGAPPLICATIONRATEOFBITUMINOUSDISTRIBUTORS 测定 沥青 布料 使用 速率

链接地址:http://www.mydoc123.com/p-513914.html