ARMY UFGS-01 32 01 00 10-2008 PROJECT SCHEDULE《项目进度》.pdf
《ARMY UFGS-01 32 01 00 10-2008 PROJECT SCHEDULE《项目进度》.pdf》由会员分享,可在线阅读,更多相关《ARMY UFGS-01 32 01 00 10-2008 PROJECT SCHEDULE《项目进度》.pdf(19页珍藏版)》请在麦多课文档分享上搜索。
1、*USACE / NAVFAC / AFCESA / NASA UFGS-01 32 01.00 10 (August 2008)-Preparing Activity: USACE SupersedingUFGS-01 32 01.00 10 (July 2007)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated July 2008*SECTION TABLE OF CONTENTSDIVISION 01 - GENERAL REQUIREMENTSSECTION 01 32
2、01.00 10PROJECT SCHEDULE08/08PART 1 GENERAL1.1 REFERENCES1.2 SUBMITTALS1.3 QUALITY ASSURANCEPART 2 PRODUCTS (Not Applicable)PART 3 EXECUTION3.1 GENERAL REQUIREMENTS3.1.1 Approved Poject Schedule3.1.2 Schedule Status Reports3.1.3 Default Terms3.2 BASIS FOR PAYMENT AND COST LOADING3.3 PROJECT SCHEDULE
3、 DETAILED REQUIREMENTS3.3.1 Critical Path Method3.3.2 Level of Detail Required3.3.2.1 Activity Durations3.3.2.2 Design and Permit Activities3.3.2.3 Procurement Activities3.3.2.4 Mandatory Tasks3.3.2.5 Government Activities3.3.2.6 Activity Responsibility Coding (RESP)3.3.2.7 Activity Work Area Coding
4、3.3.2.8 Contract Changes/Requests for Equitable Adjustment (REA) Coding (MODF)3.3.2.9 Contract Line Item (CLIN) Coding (BIDI)3.3.2.10 Phase of Work Coding (PHAS)3.3.2.11 Category of Work Coding (CATW)3.3.2.12 Definable Features of Work Coding (FOW1, FOW2, FOW3)3.3.3 Scheduled Project Completion and
5、Activity Calendars3.3.3.1 Project Start Date3.3.3.2 Schedule Constraints and Open Ended Logic3.3.3.3 Early Project CompletionSECTION 01 32 01.00 10 Page 1Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-3.3.4 Interim Completion Dates3.3.4.1 Start Phas
6、e3.3.4.2 End Phase3.3.4.3 Phase “X“ Hammock3.3.5 Default Progress Data Disallowed3.3.6 Out-of-Sequence Progress3.3.7 Negative Lags and Start to Finish Relationships3.3.8 Calculation Mode3.3.9 Milestones3.4 PROJECT SCHEDULE SUBMISSIONS3.4.1 Preliminary Project Schedule Submission3.4.2 Initial Project
7、 Schedule Submission3.4.3 Design Package Schedule Submission3.4.4 Periodic Schedule Updates3.4.5 Standard Activity Coding Dictionary3.5 SUBMISSION REQUIREMENTS3.5.1 Data CDs3.5.2 Narrative Report3.5.3 Approved Changes Verification3.5.4 Schedule Reports3.5.4.1 Activity Report3.5.4.2 Logic Report3.5.4
8、.3 Total Float Report3.5.4.4 Earnings Report by CLIN3.5.5 Network Diagram3.5.5.1 Continuous Flow3.5.5.2 Project Milestone Dates3.5.5.3 Critical Path3.5.5.4 Banding3.5.5.5 S-Curves3.6 PERIODIC SCHEDULE UPDATE MEETINGS3.6.1 Update Submission Following Progress Meeting3.6.2 Status of Activities3.6.2.1
9、Start and Finish Dates3.6.2.2 Remaining Duration3.6.2.3 Percent Complete3.6.2.4 Logic Changes3.6.2.5 Other Changes3.7 REQUESTS FOR TIME EXTENSIONS3.7.1 Justification of Delay3.7.2 Submission Requirements3.7.3 Additional Submission Requirements3.8 DIRECTED CHANGES3.9 WEEKLY PROGRESS MEETINGS3.10 OWNE
10、RSHIP OF FLOAT3.11 TRANSFER OF SCHEDULE DATA INTO RMS/QCS- End of Section Table of Contents -SECTION 01 32 01.00 10 Page 2Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-*USACE / NAVFAC / AFCESA / NASA UFGS-01 32 01.00 10 (August 2008)-Preparing Acti
11、vity: USACE SupersedingUFGS-01 32 01.00 10 (July 2007)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated July 2008*SECTION 01 32 01.00 10PROJECT SCHEDULE08/08*NOTE: This guide specification covers the requirements for the preparation and maintenance of the project sch
12、edule for construction projects or design-build construction projects.Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable items(s) or insert appropriate information.Remove information and requirements not requi
13、red in respective project, whether or not brackets are present.Comments and suggestions on this guide specification are welcome and should be directed to the technical proponent of the specification. A listing of technical proponents, including their organization designation and telephone number, is
14、 on the Internet.Recommended changes to a UFGS should be submitted as a Criteria Change Request (CCR).This guide specification includes tailoring options for construction and design-build construction projects. Selection or deselection of a tailoring option will include or exclude that option in the
15、 section, but editing the resulting section to fit the project is still required.*PART 1 GENERAL*NOTE: Selection of the optional requirements in this guide specification should be coordinated with Construction Division to ensure that the schedule requirements are appropriate for the complexity of th
16、e constructability portion of the BCOE review. See ER 415-1-11. Paragraphs may not be removed from SECTION 01 32 01.00 10 Page 3Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-this specification except as noted.If it is desired to monitor a Contracto
17、rs schedule by use of an in-house program, this will require use of the Standard Data Exchange Format (SDEF). Use of proprietary systems will not be specified. See ER 1-1-11, Appendix A.*1.1 REFERENCES*NOTE: This paragraph is used to list the publications cited in the text of the guide specification
18、. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title.Use the Reference Wizards Check Reference feature when you add a RID outside of the Sections Reference Article to automatically place the reference in t
19、he Reference Article. Also use the Reference Wizards Check Reference feature to update the issue dates.References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process.*The publications l
20、isted below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.U.S. ARMY CORPS OF ENGINEERS (USACE)ECB 2005-10 (2005) Scheduling Requirements for Testing of Mechanical Systems in ConstructionER 1-1-11 (1995) Prog
21、ress, Schedules, and Network Analysis Systems1.2 SUBMITTALS*NOTE: Review submittal description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project. Submittals should be kept to the minimum required for adequate
22、 quality control.A “G” following a submittal item indicates that the submittal requires Government approval. Some submittals are already marked with a “G”. Only delete an existing “G” if the submittal item is not complex and can be reviewed through the Contractors Quality Control system. Only add a
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ARMYUFGS01320100102008PROJECTSCHEDULE 项目 进度 PDF

链接地址:http://www.mydoc123.com/p-449502.html