REG NASA-LLIS-1806--2007 Lessons Learned Capture of Apollo Lunar Module Reliability Lessons Learned Program Engineering Management.pdf
《REG NASA-LLIS-1806--2007 Lessons Learned Capture of Apollo Lunar Module Reliability Lessons Learned Program Engineering Management.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1806--2007 Lessons Learned Capture of Apollo Lunar Module Reliability Lessons Learned Program Engineering Management.pdf(6页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1806Lesson Info:a71 Lesson Number: 1806a71 Lesson Date: 2007-09-25a71 Submitting Organization: HQa71 Submitted by: David Oberhettingera71 POC Name: Dr. Bette Siegela71 POC Email: bette.siegelnasa.gova71 POC Phone: 202-358-2245Subject: Capture of Apollo Lunar Module Reliability
2、 Lessons Learned: Program/Engineering Management Abstract: A July 2007 workshop attended by Constellation Program personnel traced the success of the Apollo Lunar Module designers to the NASA and contractor culture, Grummans flat organization structure, an ability to hire the “best and brightest“ en
3、gineers, placement of the Reliability function within System Engineering, definition of a “reference mission“ common to all design elements, and strong configuration control. However, little formal training was provided, and limited best practice or lesson learned information was available.Descripti
4、on of Driving Event: As part of the Constellation Programs review of human spaceflight lessons learned, NASA hosted a July 20, 2007 panel discussion with a group of retired engineers who were members of Grumman Corporations Apollo Lunar Module Reliability and Maintainability Team. One of the lessons
5、 learned that was discussed focused on the Apollo program/engineering management approach to reliability (Reference (1): The Apollo engineering culture proved key to meeting objectives in a program environment in which technical performance was primary, schedule was secondary, and cost was a distant
6、 third. Throughout the program life cycle, the Grumman and NASA cultures encouraged (1) an environment of open communications that fostered attention to detail; (2) a focus on the mission rather than on the organization; (3) ability to challenge technical assumptions; (4) assignment of Provided by I
7、HSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-managers to work as technical contributors; (5) worker buy-in or ownership of the design, schedule, and flights; (6) a high level of dedication by NASA and contractor personnel; (7) astronauts who were visible to th
8、e design team; and (8) a contract type (e.g., Cost-Plus-Fixed-Fee) that matched the program priorities. Anyone could challenge a design at any time, and Grumman challenged NASA expertise as often as the customer confronted the contractor. Astronauts were “always there“ at Grumman, and that their liv
9、es were visibly at stake exerted pressure on engineers to “do things right the first time“ wherever possible. Business arrangements influenced the program results: had the Grumman Cost-Plus-Fixed-Fee contract instead been issued for a fixed price, then technical objectives could not have dominated o
10、ver cost. To complement this culture, Grummans Apollo program organization was very flat, with a minimal number of layers. The site organizations were structured to mirror the NASA headquarters organizational structure such that all Grumman personnel knew the identity of their NASA counterparts. Str
11、ong technical expertise was provided at all levels of the organization. Program management personnel had strong technical backgrounds, and the purchasing personnel who were initially responsible for subcontract management were soon replaced with technical personnel. The national priority and public
12、interest focused on the Apollo program meant that NASA and its contractors could attract the countrys best engineers and scientists. Unlike NASA, the reliability function was placed within the Grumman systems engineering organization instead of the mission assurance organization. This relationship e
13、nabled the Systems Reliability Group at Grumman to be deeply involved in system design and in the review of design tradeoffs. Grumman recognized that it was the reliability part of system engineering that would determine the early system configuration. Although subsystem engineering (e.g., propulsio
14、n, crew environmental control) reported vertically, the systems engineering organization (e.g., thermal, dynamics) was structured horizontally to assure technical penetration of design interfaces. When subsystem managers reported a failure mode, it was easy for Systems Engineering to task system int
15、egration engineers to modify interface hardware, and then advise the Crew Systems Group to modify the Caution & Warning System, Simulator Operations (crew training), and Mission Rules as necessary. Reliability was a concern at all levels of the engineering and program organizations. Organizational i
16、nterfaces with Grumman subcontractors and suppliers permitted reliability products, such as Failure Mode and Effects Analyses (FMEAs) used to find single point failures, to cover all hardware tiers. Nevertheless, problems occurred on certain assemblies (e.g., batteries) where FMEAs were not passed d
17、own to subcontractors. Also, there may have been more duplication of engineering analysis between NASA and Grumman (and other system contractors) than was necessary. Given that ground support equipment (GSE) was a large part of the program, the organizational separation between the engineering of GS
18、E and flight hardware may not have been optimal. This constrained the close examination of GSE failure modes (e.g., over-voltage conditions) that could harm flight equipment. Apollo Lunar Module design engineering focused on the early resolution of (1) reliability problems Provided by IHSNot for Res
19、aleNo reproduction or networking permitted without license from IHS-,-,-related to interfaces and (2) other critical design issues such as micrometeoroid protection and the Landing Gear Subsystem. This was facilitated by lunar mission planning performed by Grummans Apollo Mission Planning Task Force
20、 (AMPTF), which designed the baseline vehicle and established ground rules and constraints (e.g., daylight launch, daylight landing near the lunar equator, water landing on Earth) to serve as a baseline for the mission design. Establishment of the AMPTF assured that all design elements were traceabl
21、e to a common “reference mission,“ and that design organizations did not make inconsistent design assumptions (e.g., regarding the capacity of the propellant tanks). Functional diagrams were used for reliability analysis, as well as for educating new project staff on the detailed lander design. The
22、design engineering process featured strong configuration control, with Grumman project management represented on the Apollo Lunar Module change control board. This change control board was given significant authority: the NASA and contractor program managers met, decided on a course of action, and i
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS18062007LESSONSLEARNEDCAPTUREOFAPOLLOLUNARMODULERELIABILITYLESSONSLEARNEDPROGRAMENGINEERINGMANAGEMENTPDF

链接地址:http://www.mydoc123.com/p-1019300.html