REG NASA-LLIS-1733--2004 Lessons Learned Genesis Sample Return Mishap (2004).pdf
《REG NASA-LLIS-1733--2004 Lessons Learned Genesis Sample Return Mishap (2004).pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1733--2004 Lessons Learned Genesis Sample Return Mishap (2004).pdf(6页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1733Lesson Info:a71 Lesson Number: 1733a71 Lesson Date: 2004-02-10a71 Submitting Organization: JPLa71 Submitted by: David Oberhettingera71 POC Name: Donald Sweetnama71 POC Email: Donald.N.Sweetnamjpl.nasa.gova71 POC Phone: 818-354-7771Subject: Genesis Sample Return Mishap (200
2、4) Abstract: The Genesis sample return mishap was attributed to a design error in which the gravity switches that activate the parachute deployment sequence were phased (oriented) incorrectly so that their mechanisms could not detect the atmospheric entry. Mission critical functions should have func
3、tional backups as well as redundant hardware. Ensure that heritage designs that have been modified are fully tested, that design engineers fully understand the system function of their hardware, and that peer reviews of critical functions achieve full fidelity.Description of Driving Event: The missi
4、on of the Genesis spacecraft was to collect solar wind samples and return those samples to Earth for analysis. In September 2004, the spacecraft approached Earth and fired pyros that jettisoned the Sample Return Capsule (SRC). After entering Earths atmosphere, the SRC was expected to open a drogue p
5、arachute, followed by release of the main parachute and the mid-air capture of the SRC by a helicopter. Instead, the pyro event to release the drogue chute did not occur, and the SRC struck the Earth at high speed. This resulted in a loss of some of the science return, but the integrity of the sampl
6、e collectors was maintained sufficiently to achieve mission success. Failure analysis determined that four gravity switches (g-switches)- two switches mounted on each of the two relay modules (Figure 1), each within an SRC Avionics Unit (AU)- were phased incorrectly. That is, they were assembled acc
7、ording to the drawings, but the design placed the switches on both relay boards in the wrong orientation relative to the deceleration force during Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-atmospheric entry (Reference (1). This orientation prev
8、ented the switch mechanism (Figure 2) from closing during the deceleration of the SRC. G-switch closure was required to trigger the critical events needed for the SRCs safe return. The switch design error resulted from modifications to the heritage Stardust Avionics Unit that changed both the orient
9、ation of the circuit boards and the orientation of the switches as they were mounted on each circuit board. These apparently minor design changes constituted a departure from design heritage that necessitated testing. Indeed, the centrifuge test that was performed for Stardust would have detected th
10、e Genesis design error, but the test was not performed because of (1) an erroneous view of the Genesis AU design as Stardust heritage and (2) a 4-month schedule slip in the delivery of the AU for test and verification. The multiple Genesis g-switches within the duplicate Avionics Units provided hard
11、ware redundancy, but not functional redundancy. Hardware redundancy was provided in that both switches needed to close in only one of the AUs. However, an independent pressure switch to sense altitude, or a countdown timer that started when the SRC was released from the spacecraft, would have added
12、a backup function for triggering drogue chute deployment during the entry, descent, and landing (EDL) phase. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Figure 1 is a black and white photo of a portion of an approximated one foot square circuit b
13、oard. The board is populated with a number of modular and discrete components. Arrows have been added to the image to point to the location and orientation of two identical, cylindrical, G-switches attached to the board. The two piece parts are coplanar to the board, and are 2-inches apart and in-li
14、ne with each other along their long axisFigure 1. G-switch function requires an appropriate orientation (polarity) on the SRC Relay Module. The g-switches are mounted (per print) with the flared end containing the fixed contact (see Figure 2) positioned toward the top of the photo. Provided by IHSNo
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS17332004LESSONSLEARNEDGENESISSAMPLERETURNMISHAP2004PDF

链接地址:http://www.mydoc123.com/p-1019267.html