《REG NASA-LLIS-1095-2001 Lessons Learned Construction Site Safety Coordination of Requirements Power Compatibility Design Review Submittal Review.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1095-2001 Lessons Learned Construction Site Safety Coordination of Requirements Power Compatibility Design Review Submittal Review.pdf(3页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1095Lesson Info:a71 Lesson Number: 1095a71 Lesson Date: 2001-08-27a71 Submitting Organization: DFRCa71 Submitted by: Roy TryonSubject: Construction Site Safety: Coordination of Requirements, Power Compatibility, Design Review, Submittal Review Description of Driving Event: The
2、 Center has an existing campus complex of modular buildings fed by a main distribution panel (MDP) with 120-208 volt/3 phase power output. A recent project added 3 more buildings to the complex, each having its own 120-208 volt/3 phase power panel. The mechanical engineer specified HVAC units by spe
3、cific brand name and numeric catalog number, “or approved equal“. Embedded in that catalog number was a letter code that denoted the specific voltage for the HVAC equipment motors. In this case it denoted 480 volt power. The electrical drawings and specifications (provided by NASA) showed 120-208 vo
4、lt power supply. Therefore, the mechanical subcontractor furnished and installed exactly what NASA specified and approved during product submittals. It was only when the HVAC equipment was actually installed in the field, and the electrical subcontractor tried to connect up the 208 volt circuit feed
5、er that anyone realized that there was insufficient voltage to power the specified 480 volt HVAC motors.NASA had several options: (1) Remove the 480 volt equipment and replace them with new 208 volt equipment. (2) Run new 480 volt circuits back to the campus main switchgear. (3) Install new addition
6、al step-up transformers for each of the 3 HVAC units. Due to constructability, cost and schedule impacts, option #3 was selected.Lesson(s) Learned: 1. The design Project Manager must coordinate mechanical equipment with electrical power service.2. The mechanical designer should not rely on very prec
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS10952001LESSONSLEARNEDCONSTRUCTIONSITESAFETYCOORDINATIONOFREQUIREMENTSPOWERCOMPATIBILITYDESIGNREVIEWSUBMITTALREVIEWPDF

链接地址:http://www.mydoc123.com/p-1018734.html