REG NASA-LLIS-1089--1992 Lessons Learned - TOPEX POSEIDON Spacecraft Handling Anomaly Special Review Board Final Report of May 29 1992.pdf
《REG NASA-LLIS-1089--1992 Lessons Learned - TOPEX POSEIDON Spacecraft Handling Anomaly Special Review Board Final Report of May 29 1992.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1089--1992 Lessons Learned - TOPEX POSEIDON Spacecraft Handling Anomaly Special Review Board Final Report of May 29 1992.pdf(9页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1089Lesson Info:a71 Lesson Number: 1089a71 Lesson Date: 1992-05-29a71 Submitting Organization: GSFCa71 Submitted by: Ronald J. Ploszaj / Eric RaynorSubject: TOPEX/POSEIDON Spacecraft Handling Anomaly Special Review Board Final Report of May 29, 1992 Abstract: Support equipment
2、 was damaged during a lift because the fixture assembly used for lifting the spacecraft into the thermal vacuum chamber was unstable in the TOPEX/POSEIDON configuration.The lesson provides 7 recommendations involving the need for stability analysis, formal mechanical GSE design reviews, peer review
3、of lifting fixture design, high fidelity dry runs, and involvement of host center personnel. Description of Driving Event: On Sunday March 8, 1992 the TOPEX/POSEIDON Spacecraft was being prepared for thermal vacuum (T/V) testing by a test team in Building 10 of the Goddard Space Flight Center (GSFC)
4、. As part of the procedure, the T/V Fixture Assembly consisting of the spacecraft, thermal test shrouding and instrumentation mounted on the Spacecraft Horizontal Support Structure (SHSS), suspended by four vertical cables from an H-frame spreader bar was lifted and positioned above the T/V chamber.
5、 At approximately 11:25 a.m., during final north / south crane positioning maneuvers, the suspended assembly began a slow overturning rotation. The assembly rotated approximately 135 degrees from horizontal before being halted by the entanglement of one of the four suspension cables with the SHSS. A
6、fter some bouncing and jostling, it came to rest at approximately 115 degrees.While resting in this anomalous position (+X end up), the Test Team visually determined that the H frame spreader bar assembly had sustained considerable damage during the rotation and might fail. A decision was made by th
7、e Spacecraft Manager to remove the vertical load from the overstressed and damaged H frame spreader assembly as quickly as possible by lowering the spacecraft and test fixture to the chamber floor. Within ten minutes of the overturning incident the Test Team, Provided by IHSNot for ResaleNo reproduc
8、tion or networking permitted without license from IHS-,-,-augmented by personnel from a GSFC contractor, lowered the rotated assembly to the chamber floor where it was temporarily secured. During the subsequent visual inspection of the secured assembly it was noted that sections of the thermal test
9、shroud and support fixturing had partially yielded. However, no apparent damage to the spacecraft or to the lower frame of the SHSS could be seen.An on site “failure review board“ of civil servant and contractor personnel was convened to review and discuss the situation. A decision was made by the b
10、oard that the Spacecraft/SHSS assembly should be removed and reoriented to a horizontal position outside of the chamber to minimize any further yielding of the supporting structures. A rigging crew was on the scene at this time, and was given the go ahead by the board to proceed with the removal of
11、the Spacecraft/SHSS assembly from the chamber.The damaged H-frame spreader bar and the four suspension cables were removed. A pair of nylon slings were attached from the +X end of the SHSS to the crane hook and the Spacecraft/Thermal Shroud/SHSS assembly was raised vertically out of the T/V chamber
12、and moved directly adjacent to it. The assembly remained there suspended a few inches above the floor while the team attached additional slings from the -X end of the SHSS to a forklift positioned on the -Z side of the load. By alternating operations of the crane and the forklift, the spacecraft and
13、 fixture were reoriented horizontally and lowered to the floor. At approximately 6:51 p.m. the operation was completed with the Spacecraft/SHSS assembly safely on the floor in the normal attitude. A video recording of both the anomaly and the recovery operation was made and is available from the TOP
14、EX Project office for viewing.Lesson(s) Learned: Root Cause of Problem:The T/V Fixture Assembly used for lifting the spacecraft into the thermal vacuum chamber was unstable in the TOPEX/POSEIDON configuration.Contributing Factors:1. A stability analysis of the total lifted assembly that was used in
15、the T/V lift was not performed.2. The lifting fixture guidelines contained in JPL900-501, Ground Handling Equipment Design Notebook were not adequately applied.3. A GSE Review which would have included a review of the T/V handling fixture assembly, was repeatedly postponed, and not held prior to its
16、 use for lifting the spacecraft into the T/V chamber.Additional Observations:1. The overall review process, at all levels (peer review to formal review) failed to identify the Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-lifting fixture deficiency
17、.2. No precursor run through (dry run) of the T/V lifting exercise, using either the actual or a high fidelity simulation of the lifted assembly, was run prior to the lift with the flight spacecraft. There was a low fidelity dry run with the TOPEX/POSEIDON handling fixture, but it was performed with
18、out a spacecraft mass simulation and at different locations and orientations than the flight spacecraft handling. (The stated purpose for the dry run was to check the SHSS and thermal shroud interfaces and clearances to the T/V chamber, not to dry run the actual spacecraft lift.)3. Just prior to the
19、 final crane move, the T/V Fixture Assembly was lifted by the crane and a “rocking test“ was performed on the assembly by the test team to assess its stability. The T/V Fixture Assembly appeared to be stable at that time because the lifting clevis friction was not exceeded during the rocking test.Le
20、ssons Learned:1. GSE Review - Ground support handling equipment should always be reviewed/approved by experienced designers and handling personnel prior to handling operations.2. Review material - Released drawings, analysis, and procedures for handling equipment should be available for review at le
21、ast 60 days before a test to permit adequate evaluation.3. Lifting Equipment Stability Analysis - No lifting equipment should ever be used without a complete stability analysis of the equipment with the load in its complete configuration.4. Precursor Handling Experience - On protoflight spacecraft,
22、the only precursor handling experience is with a dry run and mass mockups. The mass mockups handling dynamics, geometries, and sequences used for the dry run should simulate the protoflight spacecraft. Analysis and procedural checks are not always adequate to ensure surprises wont occur.5. Project o
23、verview of contract - Project support from the cognizant JPL (or other NASA Center) divisions should ensure, for the area of overview of their organization, that the contractor is adhering to all applicable requirements. All contractual documents (such as JPL 900-501) relating to potentially hazardo
24、us operations should be clearly identified and should receive special attention.6. Dedicated Briefing - A detailed and dedicated briefing structured to review the wording, text, diagrams, etc. is also a mandatory part of any functional demonstration. This briefing serves to inform the personnel who
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS10891992LESSONSLEARNEDTOPEXPOSEIDONSPACECRAFTHANDLINGANOMALYSPECIALREVIEWBOARDFINALREPORTOFMAY291992PDF

链接地址:http://www.mydoc123.com/p-1018728.html