ASTM E1185-2007 Standard Guide for Selecting Economic Methods for Evaluating Investments in Buildings and Building Systems《建筑物和建筑系统中投资评价的经济方法选择用标准指南》.pdf
《ASTM E1185-2007 Standard Guide for Selecting Economic Methods for Evaluating Investments in Buildings and Building Systems《建筑物和建筑系统中投资评价的经济方法选择用标准指南》.pdf》由会员分享,可在线阅读,更多相关《ASTM E1185-2007 Standard Guide for Selecting Economic Methods for Evaluating Investments in Buildings and Building Systems《建筑物和建筑系统中投资评价的经济方法选择用标准指南》.pdf(5页珍藏版)》请在麦多课文档分享上搜索。
1、Designation: E 1185 07Standard Guide forSelecting Economic Methods for Evaluating Investments inBuildings and Building Systems1This standard is issued under the fixed designation E 1185; the number immediately following the designation indicates the year oforiginal adoption or, in the case of revisi
2、on, the year of last revision. A number in parentheses indicates the year of last reapproval. Asuperscript epsilon (e) indicates an editorial change since the last revision or reapproval.1. Scope1.1 This guide identifies types of building design andbuilding system decisions that require economic ana
3、lysis andrecommends ASTM practices, adjuncts, and computer pro-grams that may be used to implement the appropriate economicmethods for each decision type.2. Referenced Documents2.1 ASTM Standards:2E 631 Terminology of Building ConstructionsE 833 Terminology of Building EconomicsE 917 Practice for Me
4、asuring Life-Cycle Costs of Buildingsand Building SystemsE 964 Practice for Measuring Benefit-to-Cost and Savings-to-Investment Ratios for Buildings and Building SystemsE 1057 Practice for Measuring Internal Rate of Return andAdjusted Internal Rate of Return for Investments in Build-ings and Buildin
5、g SystemsE 1074 Practice for Measuring Net Benefits and Net Sav-ings for Investments in Buildings and Building SystemsE 1121 Practice for Measuring Payback for Investments inBuildings and Building Systems2.2 ASTM Adjuncts:Discount Factor Tables, Adjunct to Practice E 91733. Terminology3.1 Definition
6、sFor definitions of terms used in this guide,refer to Terminologies E 631 and E 833.4. Significance and Use4.1 Standard practices for measuring the economic perfor-mance of investments in buildings and building systems havebeen published by ASTM. A computer program that produceseconomic measures con
7、sistent with these practices is avail-able.4Discount factor tables have been published by ASTM tofacilitate computing measures of performance for most of thepractices.34.2 This guide can be used to: (1) identify types of buildingdesign and system decisions that require economic analysis; (2)match th
8、e technically appropriate economic methods with thedecisions; and (3) locate the methods in the ASTM practicesand adjuncts listed in Section 2.4.3 More than one method can be technically appropriatefor many building decisions. Therefore the choice in practiceof which technically appropriate economic
9、 method to use forevaluating a particular building decision will often depend onthe perspective of the user. Some examples of factors thatinfluence the user are: (1) ease of applying the methods, (2)level of familiarity of the user with the methods, (3) preferenceof the user for different methods, a
10、nd (4) presence of budgetlimitations for the projects.4.4 This guide identifies some features and limitations of themethods that might influence users choices under varyingconditions.5. How to Use This Guide5.1 Table 1 indicates which standard practices (that is,economic methods) are technically app
11、ropriate for the follow-ing four types of building investment decisions: acceptance/rejection, design, size, and priority.5.1.1 In the context of this guide, an acceptance/rejectiondecision pertains to the cost effectiveness of an individualbuilding or building system. This type of decision is madei
12、ndependently of other project evaluations. It focuses on themerits of a single choice rather than on determining the mostcost-effective design or size.5.1.2 A design decision pertains to choices among compet-ing designs for an individual building or building system,where only one design can be chose
13、n.1This guide is under the jurisdiction of ASTM Committee E06 on Performanceof Buildings and is the direct responsibility of Subcommittee E06.81 on BuildingEconomics.Current edition approved April 1, 2007. Published April 2007. Originallyapproved in 1987. Last previous edition E 1185 02.2For referen
14、ced ASTM standards, visit the ASTM website, www.astm.org, orcontact ASTM Customer Service at serviceastm.org. For Annual Book of ASTMStandards volume information, refer to the standards Document Summary page onthe ASTM website.3Available from ASTM International Headquarters. Order Adjunct No.ADJE091
15、703.4BLCC5, the “NIST Building Life-Cycle Cost Program,” Office of AppliedEconomics, Building and Fire Research Laboratory, National Institute of Standardsand Technology. Available at http:/www.eren.doe.gov/femp. Click on “TechnicalAssistance” first, then on “Life-Cycle Cost Analysis.”1Copyright AST
16、M International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959, United States.5.1.3 A sizing decision pertains to choices among compet-ing sizes or investment levels for an individual building orbuilding system, where only one size or level can be chosen.5.1.4 A ranking decisi
17、on entails choosing one or moreprojects from a group of cost-effective projects when theavailable budget is not sufficient to fund them all.5.1.5 Examine Table 1 to find which methods should beconsidered for a given decision. The ASTM designations aregiven in parentheses under the method names.5.2 I
18、f there is any doubt as to which type of buildingdecision shown in Table 1 best applies, consult the examples inTable 2. Table 2 lists examples for each of the four types ofdecisions shown in Table 1. Find in Table 2 a building decisionsimilar to the one being analyzed, and select the correspondingd
19、ecision type from Table 1. Section 6 contains illustrative casesof this process.5.3 Once the type of decision has been identified and Table1 has been consulted for the technically appropriate method,there will be several methods from which to choose. Note thatwhile all of the methods that are marked
20、 as appropriate for agiven decision will generally give answers that support thesame decision (with the exception of payback), there are likelyto be special considerations that make one or more methodspreferred over the others. Examine the special considerationslisted in Table 3 before making a fina
21、l choice of methods.5.4 Examine the practice(s) that corresponds to the chosenmethod(s). In the selected practice(s), read the sections onsignificance and use, applications, and limitations. If thepractice(s) still seems appropriate, follow its procedures. If not,repeat the process using Tables 1 th
22、rough 3 until an acceptablepractice has been found or it has been determined that none ofthe practices is suitable for the decision at hand.5.5 For assistance in calculating the measure(s) of economicperformance provided by the selected method(s), use theadjunct and BLCC54. The adjunct on Discount F
23、actor Tablessupports manual calculations for all of the methods. TheBuilding Life-Cycle Cost Computer Program (BLCC5) sup-ports computer calculations for all the methods except netbenefits where revenues are involved, and payback.6. Illustrative Cases6.1 Section 6 illustrates how to use this guide t
24、o choose theappropriate practice for each of the four types of buildinginvestment decisions listed in Table 2.6.2 Acceptance or Rejection Decisions:6.2.1 If it is known (by recognition of the type of decisionor by having examined examples in Table 2) that the buildingdecision to be made is one of ac
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
5000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASTME11852007STANDARDGUIDEFORSELECTINGECONOMICMETHODSFOREVALUATINGINVESTMENTSINBUILDINGSANDBUILDINGSYSTEMS

链接地址:http://www.mydoc123.com/p-528118.html