1、Designation: D 6102 06Standard Guide forInstallation of Geosynthetic Clay Liners1This standard is issued under the fixed designation D 6102; the number immediately following the designation indicates the year oforiginal adoption or, in the case of revision, the year of last revision. A number in par
2、entheses indicates the year of last reapproval. Asuperscript epsilon (e) indicates an editorial change since the last revision or reapproval.1. Scope1.1 This guide covers directions for the installation ofgeosynthetic clay liners (GCLs) under field conditions typi-cally present in environmental lini
3、ng applications.1.2 This guide contains general installation guidelines. It isnot intended to replace project-specific installation require-ments as found in the contract drawings or specifications. Inthe event of a conflict, the requirement of the project specifi-cations will supersede the requirem
4、ents of this guide.1.3 This guide does not purport to establish specific proce-dure for all climatic, geographical, hydraulic, or topographicalconditions that may exist at a site. Appropriate installationprocedures under atypical field conditions should be modifiedas necessary to maintain the integr
5、ity of the GCL and adjacentlining system components.1.4 Different GCLs have different materials of constructionwith different physical properties. The procedures contained inthis guide, therefore, may not be universally applicable to allGCLs under all field conditions.1.5 This standard does not purp
6、ort to address all of thesafety concerns, if any, associated with its use. It is theresponsibility of the user of this standard to establish appro-priate safety and health practices and determine the applica-bility of regulatory limitations prior to use.2. Referenced Documents2.1 ASTM Standards:2D 6
7、53 Terminology Relating to Soil, Rock, and ContainedFluidsD 4439 Terminology for GeosyntheticsD 5888 Guide for Storage and Handling of GeosyntheticClay Liners3. Terminology3.1 Definitions: For definitions of other geosynthetic termsused in this guide, refer to Terminology D 4439. For definitionsof s
8、oils terms, refer to Terminology D 653.3.2 Definitions of Terms Specific to This Standard:3.3 geosynthetic clay liner (GCL), na manufactured hy-draulic barrier consisting of clay bonded to a layer or layers ofgeosynthetics.4. Significance and Use4.1 For optimum performance, GCLs must be installed in
9、 amanner that does not impact their physical, mechanical, orhydraulic properties.4.2 This guide identifies the proper installation proceduresand equipment for use by GCL designers, inspectors, andinstallers.5. Procedure5.1 The methods and equipment used for placement of theGCL can vary, but the prim
10、ary objective of the process is tominimize the potential for GCL damage. The placementmethods and equipment should be evaluated appropriatelywithin this context.5.2 Subgrade Preparation:5.2.1 For projects where the GCL is to be placed over anearthen subgrade, the subgrade surface must be prepared an
11、dapproved prior to installation in accordance either with projectspecifications or with this guide. The surface should be firmand unyielding, with no abrupt elevation changes, voids andcracks, ice, or standing water.5.2.2 The subgrade surface should be smooth and free ofvegetation, sharp-edged rocks
12、, stones, sticks, constructiondebris, and other foreign matter that could contact the GCL.The subgrade surface shall be compacted in accordance withthe project specifications. At a minimum, the subgrade shouldbe rolled with a smooth-drum compactor of sufficient weight toremove any excessive wheel ru
13、ts, footprints, or other abrupt1This guide is under the jurisdiction ofASTM Committee D35 on Geosyntheticsand is the direct responsibility of Subcommittee D 35.04 on Geosynthetic ClayLiners.Current edition approved Jan. 1, 2006. Published February 2006. Originallyapproved in 1997. Last previous edit
14、ion approved in 2004 as D 6102 - 04.2For referenced ASTM standards, visit the ASTM website, www.astm.org, orcontact ASTM Customer Service at serviceastm.org. For Annual Book of ASTMStandards volume information, refer to the standards Document Summary page onthe ASTM website.1Copyright ASTM Internati
15、onal, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959, United States.grade changes. Excessive rutting should be clearly defined andquantified. In some cases 25 mm is the maximum rut depthallowed. Furthermore, all protrusions extending more than 12mm from the subgrade surface sha
16、ll either be removed,crushed, or pushed into the surface with a smooth-drumcompactor.5.3 GCL Placement:5.3.1 All handling of the GCL at the job site should beconducted in accordance with Guide D 5888.5.3.2 GCL rolls are to be delivered to the working area ofthe site in their original packaging. Imme
17、diately prior todeployment, the packaging shall be carefully removed withoutdamaging the GCL.NOTE 1The orientation of the GCL (that is, which side faces up) maybe important and shall be in accordance with the engineers requirements.5.3.3 No equipment that could damage the GCL shall beallowed to trav
18、el directly on the GCL. Acceptable installation,for example, may be accomplished such that the GCL isunrolled in front of the backwards-moving deployment equip-ment, such as a front-end loader or bulldozer. If the equipmentcauses rutting of the subgrade, the subgrade must be restored toits originall
19、y accepted condition before placement continues.5.3.4 Care must be taken to minimize the extent to whichthe GCL is repositioned across the subgrade in order tominimize damage to the subgrade and to the bottom surface ofthe GCL. A temporary geosynthetic subgrade covering com-monly known as a slip she
20、et or rub sheet may be used to reducefriction damage during placement.5.3.5 The GCL should be placed so that seams are parallelto the direction of the slope. Other industry-accepted practicesfor installing geosynthetics on slopes shall be followed whereappropriate, to help ensure that the stability
21、and performance ofthe GCL is adequate.5.3.6 All GCL should lie flat on the underlying surface, withno wrinkles or folds, especially at the exposed edges of thepanels.5.3.7 Only as much GCL shall be deployed per working dayas can be covered in accordance with 5.8. The GCL shall becovered overnight.NO
22、TE 2If the GCL is hydrated when no confining stress is present, itmay be necessary to remove and replace the hydrated material. The projectengineer, Construction Quality Assurance (CQA) inspector, and GCLsupplier should be consulted for specific guidance if premature hydrationis suspected to have oc
23、curred.5.3.8 The GCL should not be installed when it is frozen.5.3.9 If GCLis placed over geosynthetic, care must be takenas to not damage underlying material with high groundpressure equipment directly on the geosynthetic.5.4 Anchorage:5.4.1 At the top of a slope, the end of the GCL roll may beplac
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
5000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASTMD61022006STANDARDGUIDEFORINSTALLATIONOFGEOSYNTHETICCLAYLINERS 土工 合成 粘土 衬垫 安装 标准 指南 PDF

链接地址:http://www.mydoc123.com/p-521538.html