ANSI ASME PTC 46-2015 Overall Plant Performance.pdf
《ANSI ASME PTC 46-2015 Overall Plant Performance.pdf》由会员分享,可在线阅读,更多相关《ANSI ASME PTC 46-2015 Overall Plant Performance.pdf(306页珍藏版)》请在麦多课文档分享上搜索。
1、Overall Plant PerformancePerformance Test CodesAN AMERICAN NATIONAL STANDARDASME PTC 46-2015(Revision of ASME PTC 46-1996)ASME PTC 46-2015(Revision of ASME PTC 46-1996)Overall PlantPerformancePerformance Test CodesAN AMERICAN NATIONAL STANDARDTwo Park Avenue New York, NY 10016 USADate of Issuance: O
2、ctober 25, 2016This Code will be revised when the Society approves the issuance of a new edition.ASME issues written replies to inquiries concerning interpretations of technical aspects of thisdocument. Interpretations are published on the Committee Web page and undergo.asme.org/InterpsDatabase. Per
3、iodically certain actions of the ASME PTC Committee may bepublished as Cases. Cases are published on the ASME Web site under the PTC Committee Page atgo.asme.org/PTCcommittee as they are issued.Errata to codes and standards may be posted on the ASME Web site under the Committee Pages toprovide corre
4、ctions to incorrectly published items, or to correct typographical or grammatical errorsin codes and standards. Such errata shall be used on the date posted.The PTC Committee Page can be found at go.asme.org/PTCcommittee. There is an option availableto automatically receive an e-mail notification wh
5、en errata are posted to a particular code or standard.This option can be found on the appropriate Committee Page after selecting “Errata” in the “PublicationInformation” section.ASME is the registered trademark of The American Society of Mechanical Engineers.This code or standard was developed under
6、 procedures accredited as meeting the criteria for American NationalStandards. The Standards Committee that approved the code or standard was balanced to assure that individuals fromcompetent and concerned interests have had an opportunity to participate. The proposed code or standard was madeavaila
7、ble for public review and comment that provides an opportunity for additional public input from industry, academia,regulatory agencies, and the public-at-large.ASME does not “approve,” “rate,” or “endorse” any item, construction, proprietary device, or activity.ASME does not take any position with r
8、espect to the validity of any patent rights asserted in connection with anyitems mentioned in this document, and does not undertake to insure anyone utilizing a standard against liability forinfringement of any applicable letters patent, nor assumes any such liability. Users of a code or standard ar
9、e expresslyadvised that determination of the validity of any such patent rights, and the risk of infringement of such rights, isentirely their own responsibility.Participation by federal agency representative(s) or person(s) affiliated with industry is not to be interpreted asgovernment or industry
10、endorsement of this code or standard.ASME accepts responsibility for only those interpretations of this document issued in accordance with the establishedASME procedures and policies, which precludes the issuance of interpretations by individuals.No part of this document may be reproduced in any for
11、m,in an electronic retrieval system or otherwise,without the prior written permission of the publisher.The American Society of Mechanical EngineersTwo Park Avenue, New York, NY 10016-5990Copyright 2016 byTHE AMERICAN SOCIETY OF MECHANICAL ENGINEERSAll rights reservedPrinted in U.S.A.CONTENTSNotice .
12、 viForeword viiCommittee Roster . ixCorrespondence With the PTC Committee xIntroduction . xiSection 1 Object and Scope . 11-1 Object . 11-2 Scope 11-3 Test Uncertainty . 11-4 References . 2Section 2 Definitions and Descriptions of Terms 42-1 Definitions of Correction Factors . 42-2 Terms . 4Section
13、3 Guiding Principles. 83-1 Introduction . 83-2 Test Plan 143-3 Test Preparations 163-4 Conduct of the Test 173-5 Calculation and Reporting of Results . 21Section 4 Instruments and Methods of Measurement 234-1 General Requirements 234-2 Pressure Measurement . 274-3 Temperature Measurement . 314-4 Hum
14、idity Measurement 394-5 Flow Measurement . 414-6 Primary Heat Input Measurement 484-7 Electrical Generation Measurement . 494-8 Grid Frequency 564-9 Data Collection and Handling 56Section 5 Calculations and Results. 585-1 Fundamental Equations 585-2 Measured Plant Power and Heat Input Terms in the F
15、undamentalEquations . 585-3 Particularizing Fundamental Performance Equations to Specific Cycles andTest Objectives 615-4 Discussion of Application of Correction Factors . 635-5 Special Considerations of Performance Equations as Applied to CombinedCycles . 705-6 Special Case When Piping Is Outside t
16、he Test Boundary 755-7 Special Considerations as Applied to Steam Turbine Plants 75Section 6 Report of Results 786-1 General Requirements 786-2 Executive Summary 786-3 Introduction . 786-4 Calculations and Results . 786-5 Instrumentation 79iii6-6 Conclusions . 796-7 Appendices 79Section 7 Test Uncer
17、tainty. 807-1 Introduction . 807-2 Pretest Uncertainty Analysis . 807-3 Post-test Uncertainty Analysis 807-4 Inputs for an Uncertainty Analysis . 80Figures3-1.5-1 Generic Test Boundary . 113-1.5-2 Typical Steam Plant Test Boundary . 113-1.5-3 Typical Combined Cycle Plant Test Boundary . 123-4.4.3-1
18、Three Post-test Cases . 214-2.6.2-1 Five-Way Manifold . 304-2.6.2-2 Water Leg Correction for Flow Measurement . 324-3.3.2.1-1 Four-Wire RTDs . 344-3.3.2.2-1 Three-Wire RTDs . 354-3.6.2-1 Flow-Through Well 364-7.3.1-1 Three-Wire Metering System . 514-7.3.2-1 Four-Wire Metering System 525-4.1.5-1 Typi
19、cal Test Boundary for a Power Plant Requiring Application of HeatSink Correction Factor, H90045Aor H92755A665-4.1.5-2 Typical Test Boundary for a Power Plant Requiring Application of HeatSink Correction Factor, H90045Bor H92755B675-4.1.5-3 Typical Test Boundary for a Power Plant Requiring Applicatio
20、n of HeatSink Correction Factor, H90045Cor H92755C685-7.3-1 Output Versus Throttle Steam Flow 765-7.4-1 Typical Test Boundary for a Reheat Rankine Steam Cycle Power Plant . 77Tables1-3-1 Largest Allowable Test Uncertainties . 22-1.1-1 Symbols . 52-1.1-2 Subscripts . 53-1.4.1-1 Guidance for Establish
21、ing Permissible Deviations From Design(All Values) . 103-1.10-1 Design, Construction, and Start-up Considerations 153-4-1 Typical Pretest Stabilization Periods 173-4-2 Recommended Minimum Test Run Durations . 174-2.6.2-1 Units and Conversion Factor for Water Leg Correction for FlowMeasurement 334-5.
22、1-1 Recommendations for Differential Pressure Meters for DifferentApplications . 424-5.3.1-1 Units and Conversion Factor for Mass Flow Through a Differential PressureClass Meter . 444-5.3.1-2 Summary Uncertainty of Discharge Coefficient and Expansion Factor 454-7.3-1 Metering Method Restrictions Sum
23、mary 505-1-1 Summary of Additive Correction Factors in Fundamental PerformanceEquations . 595-1-2 Summary of Multiplicative Correction Factors in Fundamental PerformanceEquations . 605-3.4-1 Examples of Typical Cycles and Test Objectives Corresponding SpecificPerformance Equations 635-5.3-1 Required
24、 Test Series for Phased Construction Combined Cycle Plants 72Nonmandatory AppendicesA Sample Calculations, Combined Cycle Cogeneration Plant Without DuctFiring Internal Heat Sink 81ivB Sample Calculations, Combined Cycle Cogeneration Plant With DuctFiring External Heat Sink . 87C Sample Calculations
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ANSIASMEPTC462015OVERALLPLANTPERFORMANCEPDF
