REG NASA-LLIS-1807--2007 Lessons Learned Inheritance Review of the Mars Phoenix Flight System.pdf
《REG NASA-LLIS-1807--2007 Lessons Learned Inheritance Review of the Mars Phoenix Flight System.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1807--2007 Lessons Learned Inheritance Review of the Mars Phoenix Flight System.pdf(4页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1807Lesson Info:a71 Lesson Number: 1807a71 Lesson Date: 2007-12-11a71 Submitting Organization: JPLa71 Submitted by: David Oberhettingera71 POC Name: Glenn Tsuyuki, Robert F. Shotwella71 POC Email: Glenn.T.Tsuyukijpl.nasa.gova71 POC Phone: 818-354-2955 (Glenn Tsuyuki)Subject: I
2、nheritance Review of the Mars Phoenix Flight System Abstract: Despite the unusually large percentage of the Phoenix design and hardware that was inherited from previous Mars spaceflight projects, the format used for Phoenix project system and subsystem Inheritance Reviews (IRs) proved adequate to mi
3、tigate the risk within technical and programmatic constraints. A mission assurance checklist provided acceptance criteria to validate the flight worthiness of each subsystem. Consider using the Phoenix Inheritance Review format as a model for future missions that feature substantial inheritance. Pla
4、n carefully for the collection, analysis, and eventual archiving of records documenting the system and subsystem pedigree.Description of Driving Event: Reuse of NASA hardware, software, or designs that have been inherited from previous projects and proven in testing or spaceflight may help NASA to c
5、ontrol programmatic and technical risk. However, a formal Inheritance Review (Reference (1) is necessary to verify that the inherited product is acceptable, reliable, and compatible with current spacecraft requirements. Best scheduled at the earliest feasible time prior to the equivalent level Preli
6、minary Design Review (PDR), the Inheritance Review (IR) assesses the potential risk associated with product use and the need for modification or additional testing. JPL hopes that Mars Phoenix, the first in NASAs Scout series of highly innovative and relatively low-cost missions, will be the first l
7、ander to physically examine water on Mars. Launched in August 2007, the spacecraft features extensive inheritance (blue-shaded components in Figure 1) from the JPL Mars Surveyor 2001 Lander (MSP01) project that was cancelled in May 2000, which itself was based upon the Mars 98 Polar Lander (MPL). As
8、 70% of the MSP01 lander hardware had already been built, the hardware was moved by the system contractor to cleanroom storage. Available documentation was also stored, although the MSP01 design was largely drawn from the faster-better-cheaper era that limited the extent of engineering documentation
9、. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Figure 1 is a color diagram that depicts that extent of Phoenix flight system and payload heritage within the Phoenix subsystems Telecom, Power, GN Telecomm; Propulsion; Structures; Mechanisms; Guidan
10、ce, Navigation, and Control; Flight Software; Simulation Software; Command and Data Handling; Harness; Thermal; ATLO (Integration Support Equipment; and Mission Operations. In planning the subsystem IRs, JPL sought to exceed the minimum level of design penetration needed to prepare for the March 200
11、5 PDR by: 1. Soliciting the participation of the spacecraft system contractor in evaluating the system compatibility of the inherited or commercial off-the-shelf (COTS) product functionality with project Level 1 and Level 2 requirements. 2. Conducting a mission assurance review and system engineerin
12、g review in concert with the subsystem IRs.3. Utilizing a mission assurance checklist that provided acceptance criteria to validate the flight worthiness of each subsystem. The checklist was derived from the form (Hardware Review & Certification Record) that JPL uses to assess the risk to flight har
13、dware posed by mechanical or electrical integration with the system (Reference (3).4. Providing the project with a recommended course of action (e.g., modification or additional testing) in cases where a subsystem did not meet the checklists acceptance criteria. The Phoenix project found the IR form
14、at to be very useful in addressing mission assurance and system engineering needs. For example: 1. Cognizant engineers were very forthright and candid about their hardwares pedigree, and the detailed checklist forced them to actively seek out and review MSP01 and MPL documentation.2. Break-away spli
15、nter sessions at the spacecraft system contractor facilities to review archived MSP01 documents such as Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-drawings, build records, test data and material reviews (MRBs) were very useful in assessing the p
16、edigree of the Phoenix hardware.Although the Phoenix IR plan was well conceived, preparation for the reviews presented difficulties. Collecting all of the MSP01 and Mars 98 documentation (i.e., parts lists, waivers, anomaly reports, MRBs, GIDEP, reliability analyses) and analyzing material storage l
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS18072007LESSONSLEARNEDINHERITANCEREVIEWOFTHEMARSPHOENIXFLIGHTSYSTEMPDF

链接地址:http://www.mydoc123.com/p-1019301.html