SANS 10120-5 A-1986 Code of practice for use with standardized specifications for civil engineering construction and contract documents Part 5 Contract administration Section A Gen.pdf
《SANS 10120-5 A-1986 Code of practice for use with standardized specifications for civil engineering construction and contract documents Part 5 Contract administration Section A Gen.pdf》由会员分享,可在线阅读,更多相关《SANS 10120-5 A-1986 Code of practice for use with standardized specifications for civil engineering construction and contract documents Part 5 Contract administration Section A Gen.pdf(5页珍藏版)》请在麦多课文档分享上搜索。
1、 Collection of SANS standards in electronic format (PDF) 1. Copyright This standard is available to staff members of companies that have subscribed to the complete collection of SANS standards in accordance with a formal copyright agreement. This document may reside on a CENTRAL FILE SERVER or INTRA
2、NET SYSTEM only. Unless specific permission has been granted, this document MAY NOT be sent or given to staff members from other companies or organizations. Doing so would constitute a VIOLATION of SABS copyright rules. 2. Indemnity The South African Bureau of Standards accepts no liability for any
3、damage whatsoever than may result from the use of this material or the information contain therein, irrespective of the cause and quantum thereof. SAR:; 01 ZO : Part 5 Section A-1986 General PART 5 : CONTRACT AUMlNISTRATJON SliCTION A CONTICNTS Clause START OP CONSTNUCTlON . 3 General . l 1MMEDlATKL
4、Y APTER TllE HANDING OVER OF THE SITE . 1 General 1 Quality of Materials . J Water Supplies l Setting out of the Works 1 Plot Boundary Pegs . 1. Existing Services . 1 Prime Cost and Provisional Sum Items 1 Time-related Prel.iminary and General Items . 1 DURING CONSTRUCTION 1 Methods of Construction
5、l Contractors office and stores, and access . l Tolerances in practice . l Administratiorl . 2 Capacity of plant and equipment 2 Silencing of plant . 2 Contractors charges for iteros in Schedule of Quantities . 2 Dealing with water . Z Tolerances . 2 Time-related preliminary and general items . 2 QU
6、ALITY CONTROL AND OTllER CONSIUERATIONS . 2 General 2 Disputes . 2 Extension of time . 2 Second Revision March 1986 Thls section of the code supersedes SAUS 0120 : Part 5 : Section A-1982 Approved by the COUNCIL OF TllE SOUTH AFP1CN.J BUREAU OF STANUARDS SAPS 0120 : Part 5 Section A-1986 clenel a1 N
7、WE: The clause numler(s) given at the hcgjntring or aftcr the heading oE a clause is/are, unless otherwise stated, the nWer(s) of the relevant claube(s) of SARS lZOO A. STAPT OF CONSTRULTION GENERAL. Fol the purpocies of this part of the cuclc, contract ,ldminstration starts witlr instrurtlon to the
8、 contractor to commence work as S t out in Sub-lausc 4.1 of the Irtroducinn. IMML?.VIATELY AYTEH TllE llANDING OVER OP TlfE SlTE GEMCML. Early attention should bc given to the matters set out in 2.2-2.8 below. QUALITY OF MAlCRIALS (Subclause 3.1). The contractor slloulcl ensure thdt any samples he d
9、elvcrb dre a fair representation of the materials or goods that will be delivered in due Lourse fol mcorporatiotr rn the works. The engineer must, without delay, qive his deislon as to acceptability and he must preservc the samples carefully. WATER SUPPI,I$S (See Subclause 1.3.1 of Section A of Part
10、 3 of the code). Wlrenever rlouLt exists as to the quality of the water available for the works, the enqiueer must give his ruliry without delay, or order the tests to be carried out expedit.iously, and the contractor must co-operate in producing samples and in arranging for tests with a minimum of
11、delay. The provision of acceptable water is t.he responsibility of t.he contractor. Velays in the provision of wat.er are not acceptable as grounds for claiming extensions of tintc. SCTTING OUT OF TllE WOKKS (Suhclause 5.1.1). The engineer should place such line peq.: as are necessary to transfer th
12、e nformation given on the drawings on to the slte. The engineer should satlsfy hmself that the contractor has been given enough pegs to determine, by direct rearliry and without subsidiay arithmetical calculatjons, the positlon of all elements of the works from the data given on the drdwinys. Immedi
13、ately the pegs and bench marks have been placed, the engineer should point them out to the contractor and show him the relevant dimesions on the drawings. The contractor should pay particular attention to the protection and preservation of the pegs. The contractor should ensurc that referclice pegs
14、are placed at a safe distance from workin9 areas and arct carefully protected. PLOT BOUNUARY PEGS (Subclause 5.1.2). The contractor and tlle engineer should oyrec on the yositiot and existence of all ppys before any clearing or earthnioving is commenced. EXISTING SEHVJCES (Subclause 5.4). The engine
15、er should odc,r, and the contractor shuald carly out, further invcstgations to detect alid expose services in those areas where the dsiyn englrlecr has not been able to provide speciiic information. From the information provided by the desiqn engineer and the results of the investigaticns descrilwd
16、above, the contractor should be able to draw up a program for the protection or relocation of services that can be carried out well ahead of the main work of the contract. The engineer is in a more authoritative position than the contractor to deal with outside authorities who are required to make a
17、lt.eratiols to or protect services ahead of or simultaneously with contract works. The contract-or should assist him by openiuy up and diorillg such services without delay and by ensuring that the engineer has a copy of the relevant part of the program uf const.ruction. The enrirreer can assist by c
18、ompleting thc details, negotiating with outside bodies for the necessary protection vr alteration and following up these arrangements to ensure co-ordination of programs. PRIME COST AND PROVISIONAL SUM ITEMS. The contlactor should be kept fully informed of details of all prime cost and provisional s
19、um items that have been included in the schedule. Aqreement should be reached on the progrm for the delivery to the site of such items so that the necessary tenders can be called for dnd the contracts awarded or orders placed in good time. The purpose of the proqram 1s to ensure that the goods or be
20、rvlces are supplied to the contractor in ample time and that his work is not delayed. If, In the execution of a program submrtted and approved krr terms of the conditions of contract, delays occur that are due to factors beyond the contractors control, the contractor has valid grounds for claniing c
21、ompensation ior any increased costs that he may incur as a result of such delays. TIME-RELATED PREI.11.1INARY AND GENERAL ITEMS (Subclause 8.2.2) . Where a schedule i ncludas more than one time-related preliminary and general item and these have been priced together as a single sum, the engineer sho
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- SANS101205A1986CODEOFPRACTICEFORUSEWITHSTANDARDIZEDSPECIFICATIONSFORCIVILENGINEERINGCONSTRUCTIONANDCONTRACTDOCUMENTSPART5CONTRACTADMINISTRATIONSECTIONAGENPDF

链接地址:http://www.mydoc123.com/p-1028586.html