REG NASA-LLIS-1042--1998 Lessons Learned Space Shuttle Program Operations-Processing Workforce.pdf
《REG NASA-LLIS-1042--1998 Lessons Learned Space Shuttle Program Operations-Processing Workforce.pdf》由会员分享,可在线阅读,更多相关《REG NASA-LLIS-1042--1998 Lessons Learned Space Shuttle Program Operations-Processing Workforce.pdf(4页珍藏版)》请在麦多课文档分享上搜索。
1、Lessons Learned Entry: 1042Lesson Info:a71 Lesson Number: 1042a71 Lesson Date: 1998-02-01a71 Submitting Organization: HQa71 Submitted by: David M. LengyelSubject: Space Shuttle Program/Operations-Processing/Workforce Description of Driving Event: Implementation of the Shuttle Processing Contract (SP
2、C)Lesson(s) Learned: Operations and processing in accordance with the Shuttle Processing Contract (SPC) have been satisfactory. Nevertheless, lingering concerns include: the danger of not keeping foremost the overarching goal of safety before schedule before cost; the tendency in a success-oriented
3、environment to overlook the need for continued fostering of frank and open discussion; the press of budget inhibiting the maintenance of a well-trained NASA presence on the work floor; and the difficulty of a continued cooperative search for the most meaningful measures of operations and processing
4、effectiveness.Recommendation(s): 1a. Both NASA and the SPC contractor should reaffirm at frequent intervals the dedication to safety before schedule before cost.1b. NASA should develop and promulgate training and career paths leading to qualification for senior NASA Space Shuttle management position
5、s.1c. NASA should continue to ensure that a trained and qualified Government personnel presence is maintained on the work floor.1d. NASA and SPC should continue to search for, develop, test, and establish the most meaningful measures of operations and processing effectiveness possible.Provided by IH
6、SNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-Evidence of Recurrence Control Effectiveness: 1a. The Space Shuttle Program concurs with the ASAP affirmation that safety is our first priority. The potential for safety impacts as a result of restructuring and downs
7、izing are recognized by NASA at every level. From the Administrator down there is the communication of and the commitment to the policy that safety is the most important factor to be considered in our execution of the program and that restructuring and downsizing efforts are to recognize this policy
8、 and solicit and support a zero tolerance position for safety impacts. The restructuring efforts across the Program in pursuit of efficiencies which might allow downsizing of the workforce consistently stress that such efficiencies must be enabled by identification and implementation of better ways
9、to accomplish the necessary work, or the unanimous agreement that the work is no longer necessary, but that in either case that the safety of the operations are preserved.In the case of the restructuring and downsizing enabled by the SPC transition of some responsibility and tasks to the contractor,
10、 the transition plans for these processes and tasks specifically address the safety implications of the transition. Additionally, the Program has required the NASA Safety and Mission Assurance (S&MA) organizations to review and concur on the transition plans as an added assurance. Other Program down
11、sizing efforts have similar emphasis embedded in the definition and implementation of their restructuring, and the S&MA organizations are similarly committed as a normal function of their institutional and programmatic oversight to assure this focus is not compromised. Additionally, the Program prio
12、rities of 1) fly safely, 2) meet the manifest, 3) improve mission supportability, and 4) reduce cost are incorporated into almost every facet of planning and communication within both the NASA and contractor execution of the Program. Besides the continuous presentation of these priorities in employe
13、e awareness media, the Program highlights their relative order in the formal consideration of design and/or process changes being considered by the various Program control boards. Additionally, these priorities are the focus point for most of the Program management forums such as the Program Managem
14、ent Reviews and SPC Contract Management Reviews (CMRs). They are specified as the basis for the Program Strategic Plan, as well as the SPC goals and objectives used by the contractor and NASA to manage and monitor the success of the SPC. Finally, these priorities are embedded in the SPC award fee pr
15、ocess (which provides for four formal reviews each year). Specifically, the award fee criteria provide for both safety and overall performance gates which, if not met by the contractor, would result in loss of any potential cost reduction share by the contractor.In summary, NASA and all of the contr
16、actors supporting the Space Shuttle Program have always been and remain committed to assuring that safety is of the highest priority in every facet of the Program operation. While downsizing does increase the challenge of management to execute a successful Program, process changes, design modificati
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS10421998LESSONSLEARNEDSPACESHUTTLEPROGRAMOPERATIONSPROCESSINGWORKFORCEPDF

链接地址:http://www.mydoc123.com/p-1018687.html