PFI ES-47-2013 WELDING OF INTERNALLY CLAD PIPING.pdf
《PFI ES-47-2013 WELDING OF INTERNALLY CLAD PIPING.pdf》由会员分享,可在线阅读,更多相关《PFI ES-47-2013 WELDING OF INTERNALLY CLAD PIPING.pdf(10页珍藏版)》请在麦多课文档分享上搜索。
1、PFI Standard ES-47 |Denotes Revision (Revised December 2013) WELDING OF INTERNALLY CLAD PIPING Prepared by Pipe Fabrication Institute Engineering Committee All PFI Standards are advisory only. There is no agreement to adhere to any PFI Standard and their use by anyone is entirely voluntary. Copyrigh
2、t by PIPE FABRICATION INSTITUTE Dedicated to Technical Advancements and Standardization in the Pipe Fabrication Industry Since 1913 USA 511 Avenue of Americas, # 601 New York, NY 10011 CANADA 655, 32ndAvenue, # 201 Lachine, QC H8T 3G6 WEB SITE www.pfi-institute.orgWelding of Internally Clad Piping P
3、FI Standard ES-47 |Denotes Revision (Revised December 2013) 1. Scope 1.1. This standard provides best practices for engineers, fabricators and installers for purchasing and assembly of pipe and fitting (piping components) that are internally clad with a corrosion-resistant or other metallic cladding
4、. 1.1.1. Piping components may consist of carbon or low alloy steel that has been manufactured by concentric forging of an internal liner made of stainless steel, nickel or nickel alloy or other metal in which the manufacturing process metallurgically bonds the cladding to the external piping compon
5、ent. Piping components may also be manufactured by the application of weld metal overlay by arc welding or other welding process such as explosion welding. 2. Cladding Material 2.1. The desired chemical analysis of the cladding must be established by the purchaser and stated in the specifications. W
6、hen cladding is applied by metallurgical bonding, identification of the grade or UNS number of the cladding material satisfies this need. When the cladding will be applied by welding, the fabricator will determine the welding filler metal that must be used to achieve the desired chemical composition
7、 of the cladding since this decision depends on the welding process that the fabricator will use; accordingly, owners and their engineers are generally discouraged from specifying the filler metal that is to be used when cladding is to be applied by welding. 2.2. If in situ verification of the compo
8、sition of weld buildup is required, the extent of such verification shall be specified by the customer. Verification shall be performed in accordance with PFI ES-42, Standard for Positive Material Identification of Piping Components using Portable X-Ray Emission Type Equipment. 3. Materials 3.1. The
9、 cladding thickness should be a minimum of 1/8 inch (3mm) thickness regardless of the thickness of the pipe components themselves. 3.2. When piping system components are supplied by the owner or someone other than the fabricator, those components should be purchased in accordance with this standard.
10、 If components do not meet this standard, the fabricator may have to add weld metal and machine the component ends to make the component suitable for shop and field welding; alternatively, the purchaser may wish to purchase components with square ends and have the fabricator prepare the ends. If cut
11、 lengths and fittings are supplied, the length of the fittings may not conform to standard B16 dimensions, and pipe will have to be trimmed to achieve the required assembly or system dimensions. 3.3. When the butt welds between clad pipe components are going to be radiographed or ultrasonically exam
12、ined by the fabricator or installing contractor, the ends of each component shall be radiographed or ultrasonically examined for a distance of not less than the greater of 3 inches or 1.5 times the thickness of the pipe from the end. Acceptance criteria shall be the same as will be required for the
13、butt weld that will be made between components. The internal surface of the cladding shall be sufficiently smooth that it does not interfere with proper interpretation or radiographs or ultrasonic examination signals. 3.4. For elevated temperature service, it should be recognized that differential t
14、hermal expansion will cause elevated stress at the transition between different types of materials (e.g., at carbon to stainless steel transitions). The customer shall be responsible for selection of filler metals to be used for welds joining clad pipe and fittings to each other and for overall suit
15、ability of such joints for the intended service conditions. 4. Weld End Preparation and Welding 4.1. Since pipe fittings that have been clad may not comply with the standard length dimensions shown in the applicable B16 standard, it may be necessary for the fabricator to measure each fitting prior t
16、o cutting pipe to achieve the correct dimensions in completed subassemblies. 4.2. For field welds and for pipe that is too small to weld from the cladding side, the weld end shall be machined as shown in Figure 1 and fit-up as shown in Figure 2. 4.3. Where ends to be welded together are available fo
17、r dimensional verification, the inside dimensions of both ends shall be measured and compared. Based on the measured dimensions, the fabricator shall determine the bore dimension PFI Standard ES-47 |Denotes Revision (Revised December 2013) so that the internal alignment of the ends to be joined will
18、 not exceed 1/16 in. 4.3.1. Where simply machining the weld end does not result in an extended root face (TIG lip) that consists of only the cladding material, the fabricator shall add weld metal to the end on the inside diameter and on the end of the pipe sufficient to ensure that the extended land
19、 is cladding material or suitable weld metal. The consumables and techniques used shall be such that the surfaces that will be exposed to the working fluid in the pipe in service are of the chemical analysis specified by the customer. On thin pipe, it may be possible to build up the ends sufficientl
20、y that a simple 35 to 40 bevel with a small root face will ensure that the wetted surfaces of the joint are of the required chemical analysis after the weld has been made. 4.3.2. Buildup of the weld end shall be made with filler metal that matches the corrosion-resistance or other critical propertie
21、s of the cladding material. 4.3.3. If the butt weld will be examined by radiography or ultrasonic methods, it is recommended that any weld buildup be similarly examined prior to making the weld or prior to shipping if the weld will be made in the field. When random radiography or ultrasonic examinat
22、ion is specified, it is not known which welds will be selected for examination prior to making the weld, therefore, it is recommended that 100% of any weld buildup should be examined. 4.3.4. If liquid penetrant examination is required for the cladding surface and weld buildup has been performed, the
23、 liquid penetrant examination shall be repeated on the final surfaces prior to fit-up. 4.3.5. Welds shall be made with the filler metal specified by the customer. The root pass will usually be welded using GTAW or GMAW. The balance of the weld can be competed using any suitable process. 4.4. Where e
24、nds to be welded together are not available for dimensional verification or where ends will match equipment or other parts, the engineer shall provide the bore dimension. It is recommended that the bore dimension be in accordance with PFI ES-21 less 0.25 inches. This will ensure that the minimum wal
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- PFIES472013WELDINGOFINTERNALLYCLADPIPINGPDF

链接地址:http://www.mydoc123.com/p-1016590.html