1、I I I I I I I I I I I I I I I I I I I GPA TITLExGUIDE 87 3824b79 0002LOb 512 GUIDE FOR PERFORMANCE TESTING OF PLANT EQUIPMENT Initial Publication 1989 GAS PROCESSORS ASSOCIATION 6526 E. 60th STREET TULSA, OK 74145 PHONE: 9181493-3872 TELEX: 91 0-845-21 91 GPA TITLE*GUIDE 89 m 3824699 0002107 459 m D
2、ISCLAIMER The Guide for Performance Testing of Plant Equipment was devel- oped by GPA Technical Section A. These data are to be taken as sug- gestions based on operating experience of Committee members. Each situation requires judgment of the individual concerned. Neither the GPA nor any member of T
3、echnical Section A makes any warranty, guaran- tee or representation, express or implied, with respect to the ac- curacy, completeness, or usefulness of the information contained in this report. i I I I 1 1 I I I I I I 1 I I I! I I I I GPA TITLE*GUIDE 89 m 3824697 0002108 395 m TABLE OF CONTENTS GEN
4、ERAL INFORMATION Disclaimer Table of Contents Acknowledgement PLANT ACCEPTANCE AND PERFORMANCE TESTS Plant Acceptance and Performance Tests TOWERS AND VESSELS Absorbers Fractionators Filters and Separators ENGINES AND TURBINES Natural Gas Fueled Reciprocating Engines Gas Fired Turbines Steam Turbine
5、s Gas Expander Turbines (Turbo Expander) COMPRESSORS, PUMPS AND BLOWERS Reciprocating Compressors Centrifugal Compressors Axial Compressors Worm/Screw Compressors Reciprocating Pumps Centrifugal Pumps Blowers and Fan HEATING AND COOLING Aerial Coolers Cooling Towers Fired Heaters and Boilers Waste H
6、eat Recovery Units Process Exchangers and Reboilers ii 1 ii iii Section Page Tab A 1 A-1 Tab B 1 B-1 2 B-9 3 B-17 Tab C 1 c-1 2 C-14 3 C-25 4 c-35 Tab D 1 D-1 2 D-14 3 D-23 4 D-27 5 D-32 6 D-38 7 D-47 Tab E 1 E-1 2 E-7 3 E-24 4 E-34 5 E-46 GPA TITLEaGUIDE 89 W 3824699 0002LO 221 ACKNOWLEDGEMENT In 1
7、982, Technical Section at the direction of then Chairman J.A. (Joe) Zanetell and endorsement of the Technical Committee undertook, as a section project, the development of a “Guide for Performance Testing of Plant Equipment,“ The Guide would compliment two check- lists that had been previously devel
8、oped by Technical Section A and published by GPA. committee with members of Section A serving as coordinators, writers and editors. The Ad hoc committee was initially chaired by John Hunt, Mobil Oil Corporation with R.A. Robinson, Tejas Gas Corporation, serv- ing as Co-chairman. In March, 1985, John
9、 Hunt retired and Joe Cloessner, Mitchell Energy Corporation, was named to chair the com- mittee. The project was organized to function as an Ad-hoc Since the projects inception in the Fall of 1982, almost every member of Section A and many associates in the GPSA industry contrib- uted of their time
10、 and talent to the development of the Guide. It is beyond the scope of this acknowledgement to name all persons who par- ticipated in the development of the Guide, however, it is appropriate here to recognize their efforts and extend the heartfelt “thanks“ of GPA. Further, it is most appropriate tha
11、t Technical Section A give special due to the people who served long and laboriously to edit the Guide in it published form. A special thanks to the EDIT REVIEW COM- MITTEES. V“rst“ Final Edit Review Committee T. J, Wheeler, Union Pacific Resources Company Chairman Technical Section A, Joe J. Cloess
12、ner, Liquid Energy Corp. Vice-chairman Technical Section A. Howard Grekel, HG Consulting Associates, Inc. J. M. Harryman, Shell Oil Company. “Final“ Final Edit Review Committee Harold L, Schnack, Warren Petroleum Co., a Div. of Chevron USA. Boyd George, Amoco Production Co. Don B. Earnst, ARCO Oil d
13、ead weight gauges and standard 7. Thermocouples and readouts. thermometers. D. Determine Test Schedule 1. Duration. 2. Maximum delay from mechanical acceptance date. 3. Maximum delay of report from end.of test. III. PRE-TEST PREPARATIONS A. Test Notifications 1. Notify gas supply operators and reque
14、st stable supply before and during test. 2. Notify maintenance personnel. a. Additional personnel required for equipment b. Revise plant preventative maintenance schedules installation and calibrations. to avoid test period. 3. Notify plant operations personnel. a. Routine operator assignments. b. E
15、xtra operators required for normally nonattended periodF and for additional monitoring assign- ments. A-3 GPA TITLE*GUIDE 89 = 3824b 0002114 699 B. Test Parameters 1. 2. 3. 4. 5. 6. 7. 8. 9. List and plan analyses of all entering and leaving gas and liquid streams-inlet, residue, product rundown and
16、 product surge vessel liquids. Prove all plant meters. Check orifice plate sizes. Record spring and temperature range, Calibrate all thermometers, gauges and analyzers. Strap all liquid product storage tanks. Read flow totalizers, Note level gauges. Pre-fill displacement fluids in sample containers,
17、 as needed. Stabilize plant operation - make necessary changes in operating conditions - pressure, temperature and flow rates to obtain desired operating conditions. Lower levels of product make tanks to permit zero make-tank deliveries if possible. Check operation of all recording meters and set co
18、r- rect chart time. Check totalizers and integrating flow meters. Confirm computer programming and design computer storage (DCS) recording, storage and retrieval capability. Check operation of all on line stream analyzers and set correct time on strip charts. IV. TEST CHECKLISTS A. Startup-Checklist
19、 1. 2. 3. 4. 5. 6. Take opening gauges and temperatures on all pro- duct storage tanks. Take opening readings for all product delivery meters. Record or mark all opening levels for process liquid surge vessels. If possible, empty all continuous sampler receiv- ing tanks and restart samplers. Change
20、all plant charts and/or mark start time on chart. Record process operating conditions and weather data not being automatically recorded. a. Visual readings by test personnel. b. Printed copy from data storage of process monitoring devices. B. Mid-Test Checklist 1. Take process operating data and wea
21、ther condi- tions at selected test intervals corresponding to the start and end of each interval and at times of each set of spot samples. 2. Take multiple spot and combined samples at selected intervals, if required. 3. Take sets of spot samples at selected times to represent at least three adjacen
22、t time periods A-4 GPA TITLEIGUIDE 89 M 3824b99 0002115 525 during the test. No test should ever be based on only one set of spot or composite analyses. 4. Monitor operation of all recording meters, ana- lyzers, samplers and data-taking devices. 5. Avoid process operating adjustments that tend to de
23、stabilize the process. 6. Delay any routine equipment shut-down until after test completion. C. Closing Checklist 1. 2. 3. 4. 5. 6. 7. Take closing gauges and temperatures on all pro- duct storage tanks at end of each test interval. Take closing readings for all product delivery meters at end of eac
24、h test. Record all test period product delivery ticket volumes. Record or mark closing levels of all process liq- uid surge vessels for each test interval. Shut-in continuous samplers and take/retrieve combined samples. Change all plant charts and/or mark closing time on chart for each test interval
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- GPAGUIDEPERFORMANCE1989GUIDEFORPERFORMANCETESTINGOFPLANTEQUIPMENT 工厂 设备 性能 试验 指南 PDF

链接地址:http://www.mydoc123.com/p-782309.html