ASTM F1675-2013 Standard Practice for Life-Cycle Cost Analysis of Plastic Pipe Used for Culverts Storm Sewers and Other Buried Conduits《对涵管 雨水管以及其他埋设管道用塑料管进行生命周期成本分析的标准实施规程》.pdf
《ASTM F1675-2013 Standard Practice for Life-Cycle Cost Analysis of Plastic Pipe Used for Culverts Storm Sewers and Other Buried Conduits《对涵管 雨水管以及其他埋设管道用塑料管进行生命周期成本分析的标准实施规程》.pdf》由会员分享,可在线阅读,更多相关《ASTM F1675-2013 Standard Practice for Life-Cycle Cost Analysis of Plastic Pipe Used for Culverts Storm Sewers and Other Buried Conduits《对涵管 雨水管以及其他埋设管道用塑料管进行生命周期成本分析的标准实施规程》.pdf(4页珍藏版)》请在麦多课文档分享上搜索。
1、Designation: F1675 13 An American National StandardStandard Practice forLife-Cycle Cost Analysis of Plastic Pipe Used for Culverts,Storm Sewers, and Other Buried Conduits1This standard is issued under the fixed designation F1675; the number immediately following the designation indicates the year of
2、original adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. Asuperscript epsilon () indicates an editorial change since the last revision or reapproval.1. Scope*1.1 This practice establishes a procedure for using life cycle
3、cost (LCC) analysis techniques to evaluate alternative drainagesystem designs, using plastic pipe that satisfy the samefunctional requirements.1.2 The LCC technique measures the present value of allrelevant costs to install, operate, and maintain alternativedrainage systems such as engineering, cons
4、truction,maintenance, rehabilitation, or replacement over a specifiedperiod of time. The practice also accommodates any remainingresidual or salvage value.1.3 The decision maker, using the results of the LCCanalysis, can then identify the alternative(s) with the lowestestimated total cost based on t
5、he present value of all costs.1.4 This standard does not purport to address all of thesafety concerns, if any, associated with its use. It is theresponsibility of the user of this standard to establish appro-priate safety and health practices and determine the applica-bility of regulatory limitation
6、s prior to use.2. Referenced Documents2.1 Other Standards:TM-5-802-1 Economic Studies for Military ConstructionDesign Applications (12/86)2Federal Office of Management and Budget Guidelines andDiscount Rates for Benefit-Cost Analysis of FederalPrograms and state documents for guidelines or require-m
7、ents32.2 ASTM Adjuncts:Discount Factor Tables43. Terminology3.1 Definitions:3.1.1 common costs, ncosts that are common to all alter-natives in nature and amount, such as initial planning fees orfuture annual inspection costs.3.1.2 discount rate, nthe investors time value of money,expressed as a perc
8、ent, used to convert costs occurring atdifferent times, to equivalent costs at a common point in time.3.1.3 drainage project, na project having a definable,functional drainage requirement that can be satisfied by two ormore design or construction alternatives, or both.3.1.4 future costs, ncosts requ
9、ired to keep the systemoperating that are incurred after the project is placed in service,such as operation, maintenance, rehabilitation, or replacementcosts.3.1.5 inflation, nthe general trend or rising prices that,over time, result in the reduction of the purchasing power ofthe dollar from year to
10、 year.3.1.6 initial cost, nthe total of all costs; such as designcosts, material purchase costs, and construction/installationcosts, that are specific to each alternative and are incurred tobring each alternative to a point of functional readiness.3.1.7 maintenance cost, nthe annual or periodic cost
11、s,such as inspection and cleaning to keep a drainage structurefunctioning for the project design life, but do not extend thematerial service life.3.1.8 material service life, nthe number of years ofservice a particular material, system, or structure will providebefore rehabilitation or replacement i
12、s necessary.3.1.9 project design life, nthe planning horizon for theproject, expressed as the number of years of useful life requiredof the drainage structure.3.1.10 rehabilitation cost, nthe total of all costs incurredto extend the material service life of a specific alternative.3.1.11 replacement
13、cost, nthe total of all costs incurred toreplace a material before the end of the project design life.3.1.12 terminal value, nthe remaining value of the drain-age structure in place at the end of the project design life.4. Summary of Practice4.1 This practice outlines a procedure for conducting anLC
14、C analysis of two or more drainage pipe alternatives using1This practice is under the jurisdiction of ASTM Committee F17 on PlasticPiping Systems and is the direct responsibility of Subcommittee F17.62 on Sewer.Current edition approved Aug. 1, 2013. Published August 2013. Originallyapproved in 1996.
15、 Last previous edition approved in 2009 as F167509. DOI:10.1520/F1675-13.2Available from Headquarters, Department of the Army, Washington, DC.3Available from Office of Management and Budget, Washington, DC.4Available from ASTM International Headquarters. Order Adjunct No.ADJE091703.*A Summary of Cha
16、nges section appears at the end of this standardCopyright ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959. United States1plastic pipe over a specified project design life. This practiceidentifies the project data and general assumptions needed forthe analysis
17、 and the method of computation.5. Significance and Use5.1 LCC analysis is an economic method to evaluate alter-natives that are characterized by differing cash flows over thedesignated project design life. The method entails calculatingthe LCC of each alternative capable of satisfying the functional
18、requirements of the project and comparing them to determinewhich have the lowest estimated LCC over the project designlife.5.2 The LCC method is particularly suitable for determiningwhether the higher initial cost of an alternative is economicallyjustified by reductions in future costs (for example,
19、 operatingmaintenance, rehabilitation, or replacement) when compared toan alternative with lower initial costs but higher future costs. Ifa design alternative has both a lower initial cost and lowerfuture costs than other alternatives, an LCC analysis is notnecessary to show the former is the econom
20、ically preferablechoice.6. Procedure6.1 The procedure for performing an LCC analysis fordrainage pipe applications is as follows:6.1.1 Identify project objectives, alternatives, and con-straints (6.2).6.1.2 Establish basic assumptions (6.3).6.1.3 Compile data (6.4).6.1.4 Compute life cycle cost for
21、each alternative (7.1).6.1.5 Evaluate results (7.2).6.2 Project Objectives, Alternatives, and Constraints:6.2.1 Specify the design objective that is to beaccomplished, identify alternative systems or designs thataccomplish that objective, and identify any constraints thatmay limit the options to be
22、considered.6.2.2 An example is the design of a storm water drainagesystem for a residential development project. The system mustsatisfy mandated drainage system objectives, such as specifiedrainfall intensities and storm water runoff limits. Availablealternatives, such as different pipe materials an
23、d varyingconfigurations of catch basins, ponds, or underground deten-tion chambers may have different initial costs as well asexpected future costs. The system design may be constrainedby structural and hydraulic limits such as minimum andmaximum slopes and depth of burial, limits on surface flows o
24、nstreets, etc.6.3 Basic Assumptions:6.3.1 Establish the uniform assumptions to be made in theLCC analysis of all alternatives. These assumptions include theselection of the discount rate, the treatment of inflation, generalinflation rate, the project design life, and the desired compre-hensiveness o
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
5000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASTMF16752013STANDARDPRACTICEFORLIFECYCLECOSTANALYSISOFPLASTICPIPEUSEDFORCULVERTSSTORMSEWERSANDOTHERBURIEDCONDUITS

链接地址:http://www.mydoc123.com/p-535388.html