ANSI NEIS 411-2014 Standard for Installing and Maintaining Uninterruptible Power Supplies (UPS).pdf
《ANSI NEIS 411-2014 Standard for Installing and Maintaining Uninterruptible Power Supplies (UPS).pdf》由会员分享,可在线阅读,更多相关《ANSI NEIS 411-2014 Standard for Installing and Maintaining Uninterruptible Power Supplies (UPS).pdf(42页珍藏版)》请在麦多课文档分享上搜索。
1、AN AMERICAN NATIONAL STANDARDNECA 411-2014 Standard for Installing and MaintainingUninterruptible Power Supplies (UPS)Published byNational Electrical Contractors AssociationStandard for Installing and MaintainingUninterruptible Power Supplies (UPS)NECA 411-2014An AmericanNational StandardPublished b
2、yNational Electrical Contractors AssociationNOTICE OF COPYRIGHTThis document is copyrighted by NECAReproduction of these documents either in hard copy or soft (including posting on the web) is prohibited without copyright permission. For copyright permission to reproduce portions of this document, p
3、lease contact NECA Standards it will neutralize acid spilled on clothing or material. Apply the solution until bubbling stops, and then rinse with clear water. Never use bicarbonate of soda on a nickel-cadmium battery. For Ni-Cd, follow 9 Standard for Installing and Maintaining Uninterruptible Power
4、 Supples (UPS) n 10NECA 411 Standard for Installing and Maintaining Uninterruptible Power Supplies (UPS)directions on the manufacturers safety data sheet or, if not available, use weak acids such as boric acid, acetic acid, or dilute citric acid. f) Guidelines for the design of electrolyte spill pro
5、tection and response to electrolyte spills can be found in IEEE 1578, Recommended Practice for Stationary Battery Electrolyte Spill Containment and Management. Guidelines for personal protective equipment around batteries can be found in the manufacturers safety data sheets, in IEEE standards applic
6、able to the battery technology, or in NFPA 70E, Standard for Electrical Safety in the Workplace.3.4.3 Hydrogen Gasa) Guidelines for the design of electrolyte spill protection and response to electrolyte spills can be found in IEEE 1578, Recommended Practice for Stationary Battery Electrolyte Spill C
7、ontainment and Management. Guidelines for personal protective equipment around batteries can be found in the manufacturers safety data sheets, in IEEE standards applicable to the battery technology, or in NFPA 70E, Standard for Electrical Safety in the Workplace.b) Verify that battery rooms and comp
8、artments with lead-acid batteries are adequately ventilated to prevent hydrogen levels from exceeding levels specified in local codes (Fire codes typically stipulate a one percent concentration by volume of the space). Gassing rates can be affected by temperature, air pressure, the battery construct
9、ion, and the amount of charge current passing through cells. Not all gas generated in a battery escapes to the atmosphere. Therefore, calculations for hydrogen ventilation shall be performed by a qualified person based upon data provided by the battery manufacturer for the battery under specified co
10、nditions. Additional ventilation may be required during activation charging cycle or other charging regimens.c) Open flames, sparks, hot plates, smoking, or any other ignition sources are prohibited near batteries, gas ventilation paths, or anywhere that hydrogen can accumulate. Discharge static ele
11、ctricity from the body before touching batteries by first touching a grounded metal surface.11 n1. Scope4. Receiving, Inspecting, Handling, and Storage4.1 Receiving and Inspectinga) Verify that the installation of equipment pads and foundations is complete and ready to receive UPSs upon delivery. Ve
12、rify that elevators, lifting devices, and other moving equipment is rated for the load weights and dimensions (including batteries) prior to the arrival of the UPS. Verify that passageways and doorways are appropriately sized to allow entrance and egress of the UPS equipment. If not, contact the UPS
13、 manufacturer to determine how much tipping, if any, is allowable in order to move the equipment. If weight is a problem, portions of the UPS may have to be disassembled. Do not disassemble UPS equipment without the supervision of the manufacturer; disassembly may void warranty or product listing. b
14、) Upon delivery of equipment and accessories, visually inspect packaging for physical damage. Reject damaged cabinets and file a claim with the carrier. Carefully unpack protective crates and packing to inspect for concealed damage resulting from shipping and handling. If damage has occurred, notify
15、 the delivering carrier and the manufacturer in writing immediately. Request a carrier inspection. Note the condition of the shipment on all copies of the delivery receipt, and file a claim with the carrier.c) Compare equipment and accessories received with the bill of materials to verify that the s
16、hipment is complete. Verify that equipment and accessories received conform with approved submittals and manufacturer quotations. If the shipment is not complete, notify the manufacturer in writing immediately. d) If equipment and accessories are to be stored prior to installation, use the original
17、packing materials to protect from the equipment exposure to environmental conditions. When conditions permit, leave the packing materials intact until equipment and accessories are ready for installation. Properly dispose of pallets and packing materials in accordance with federal, state and local r
18、egulations.e) Large UPS modules or sections are typically shipped fastened to wooden skids or pallets (see Figure 2) and with outer protective packaging materials such that the bottom of the UPS is sealed to prevent water, debris, or rodents from entering during shipping and storage. Leave skids and
19、 pallets intact until just prior to installation on the pad. Smaller UPS might be provided with castors and leveling jacks, allowing them to be rolled into place once they are removed from pallets. f) Large vented batteries (lead-acid and nickel-cadmium) are usually installed on open racks. VRLA bat
20、teries are frequently installed in cabinets, although larger units may be installed on open racks.g) Battery racks are shipped dismantled in separate rail, frame, and brace packages. Battery racks are available in a variety of formats including multi-tier, multi-step, and various seismic ratings. Se
21、ismically rated battery racks and cabinets must be fastened to the floor using seismic bracing selected Figure 2: Large UPS modules or sections are typically shipped fastened to wooden skids or pallets (Photo: )n 12NECA 411 Standard for Installing and Maintaining Uninterruptible Power Supplies (UPS)
22、specifically for the location. Check packages to ensure that the necessary assembly hardware is included. Do not throw away spacers (which are frequently mistaken for packing materials) as these are vital to the seismic installation. Modular battery cabinets are sometimes shipped with the batteries
23、installed, but more frequently the batteries must be installed on-site.h) Battery cells and multi-cell containers are typically shipped fully charged. Take special precautions to prevent shorting of battery terminals or DC terminals of equipment.Batteries are stored energy devices; they cannot be de
24、-energized. Any contact with a battery is considered work on energized electrical equipment requiring handling only by trained and authorized personnel using appropriate personal protective equipment (PPE), tools and instruments. The greatest hazard is contact between the positive and negative poles
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ANSINEIS4112014STANDARDFORINSTALLINGANDMAINTAININGUNINTERRUPTIBLEPOWERSUPPLIESUPSPDF

链接地址:http://www.mydoc123.com/p-437456.html