1、Section 2 REMOVAL OF EXISTING STRUCTURES 2.1 DESCRIPTION This work shall consist of the removal, wholly or in part, and satisfactory disposal, or salvage, of all bridges, retaining walls and other major structures which are des- ignated on the plans or in the special provisions to be re- moved. The
2、work also includes, unless otherwise speci- fied, any necessary excavation and the backfilling of trenches, holes or pits that result from such removal. 2.2 WORKING DRAWINGS Working drawings showing methods and sequence of removal shall be prepared: (1) when structures or portions of structure are s
3、pecified to be removed and salvaged, (2) when removal operations will be performed over or adja- cent to public traffic or railroad property, or (3) when called for by the plans or special provisions. At least 10 days prior to the proposed start of removal operations, the working drawings shall be s
4、ubmitted to the Engineer for approval. Removal work shall not begin until the draw- ings have been approved. Such approval shall not relieve the Contractor of any responsibility under the contract for the successful completion of the work. When salvage is required, the drawings shall clearly indicat
5、e the markings proposed to designate individual segments of the structure. 2.3 CONSTRUCTION 2.3.1 General Except for utilities and other items that the Engineer may direct the Contractor to leave intact, the Contractor shall raze, remove and dispose of each structure, or por- tion of structure, desi
6、gnated to be removed. All concrete and other foundations shall be removed to a depth of at least 2 feet below ground elevation or 3 feet below sub- grade elevation, whichever is lower. Unless otherwise specified, the Contractor has the option to either pull piles or cut them off at a point not less
7、than 2 feet below ground line. Cavities left from structure removal shall be back- filled to the level of the surrounding ground and, if within the area of roadway construction, shall be compacted to meet the requirements of the contract for embankment. Explosives shall not be used except at locatio
8、ns and under conditions cited by the project specifications. All blasting shall be completed before the placement of new work. 2.3.2 Salvage Materials which are designated to be salvaged under the contract, for reuse in the project or for future use by the Department, shall remain the property of th
9、e Depart- ment and shall be carefully removed in transportable sec- tions and stockpiled near the site at a location designated by the Engineer. The Contractor shall restore or replace damaged or destroyed material without additional com- pensation. Rivets and bolts that must be removed from steel s
10、truc- tures to be salvaged shall be removed by cutting the heads with a chisel, then punched or drilled from the hole, or by a method that will not injure the members for reuse and will meet the approval of the Engineer. All members or sections of steel structures shall be match-marked with paint in
11、 accordance with the diagram or plan approved by the Engineer prior to dismantling. All bolts and nails shall be removed from lumber deemed salvageable by the Engineer as part of the salvage of timber structures. 2.3.3 Partial Removal of Structures When structures are to be widened or modified and o
12、nly portions of the existing structure are to be removed, these portions shall be removed in such a manner as to leave the remaining structure undamaged and in proper condition for the use contemplated. Methods involving the use of blasting or wrecking balls shall not be used within any span or pier
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
2000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- AASHTOHB17DIVISIONIISEC22002DIVISIONIICONSTRUCTIONREMOVALOFEXISTINGSTRUCTURES 现有 结构 PDF

链接地址:http://www.mydoc123.com/p-417586.html