NAVY UFGS-41 22 13 13-2008 BRIDGE CRANES [Superseded ARMY UFGS-41 22 15 00 10]《桥式起重机[代替 ARMY UFGS-41 22 15 00 10]》.pdf
《NAVY UFGS-41 22 13 13-2008 BRIDGE CRANES [Superseded ARMY UFGS-41 22 15 00 10]《桥式起重机[代替 ARMY UFGS-41 22 15 00 10]》.pdf》由会员分享,可在线阅读,更多相关《NAVY UFGS-41 22 13 13-2008 BRIDGE CRANES [Superseded ARMY UFGS-41 22 15 00 10]《桥式起重机[代替 ARMY UFGS-41 22 15 00 10]》.pdf(50页珍藏版)》请在麦多课文档分享上搜索。
1、*USACE / NAVFAC / AFCESA / NASA UFGS-41 22 13.13 (April 2008)-Preparing Activity: NAVFAC SupersedingUFGS-41 22 15.00 10 (April 2006)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated March 2008*SECTION TABLE OF CONTENTSDIVISION 41 - MATERIAL PROCESSING AND HANDLING EQ
2、UIPMENTSECTION 41 22 13.13BRIDGE CRANES04/08PART 1 GENERAL1.1 REFERENCES1.2 DEFINITIONS1.3 SYSTEM DESCRIPTION1.3.1 Load and Sizing Calculations1.3.2 OET Design Criteria1.3.2.1 General1.3.2.2 Classification1.3.2.3 Rated Capacity and Speeds1.4 SUBMITTALS1.5 QUALITY ASSURANCE1.5.1 Manufacturer Qualific
3、ation1.5.2 Pre-Delivery Inspections1.5.3 Certificates1.5.4 Overhead Electric Traveling (OET) Crane(s)1.5.5 Welding Qualifications and Procedures1.5.6 Safety Requirements1.6 DELIVERY, STORAGE, AND HANDLING1.7 EXTRA MATERIALSPART 2 PRODUCTS2.1 MATERIALS2.1.1 General2.1.2 Nameplates2.1.3 Prohibited Use
4、 of Asbestos Products2.1.4 Capacity Plates2.1.5 Safety Warnings2.2 STRUCTURAL MATERIALS2.2.1 Bolts, Nuts and Washers2.2.2 Bridge Girder or Girders2.2.3 Bridge Rails or Bars2.2.4 End Ties and Bridge Girder End Connections2.2.5 Bridge End Trucks2.2.6 Trolley FrameSECTION 41 22 13.13 Page 1Provided by
5、IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-2.2.7 End Stops and Bumpers2.2.8 Footwalks2.2.9 Runway Rails2.2.10 Operators Cab2.2.10.1 Design2.2.10.2 Cab Construction2.2.11 Additional Provisions for Outside Service2.3 MECHANICAL EQUIPMENT2.3.1 Variable Frequen
6、cy Drives2.3.1.1 Bridge Drives2.3.1.2 Trolley Drives2.3.1.3 Micro-Drives2.3.2 Gearing2.3.2.1 Gear Reducers2.3.2.2 Open Gearing2.3.3 Brakes2.3.4 Wheels2.3.5 Bearings2.3.6 Anti-Drip Provisions2.4 ELECTRICAL COMPONENTS2.4.1 Explosion Proof Requirements2.4.2 Control Systems2.4.2.1 Travel Motion Control
7、System2.4.2.2 Drive Control System2.4.3 Power Sources2.4.3.1 System Supply Voltage2.4.3.2 Transformers2.4.4 Motors2.4.4.1 General Requirements for Motors2.4.4.2 Bridge and Trolley Drive Motors2.4.4.3 Motor Enclosures2.4.4.4 Motor Insulation and Time Rating2.4.4.5 Bridge and Trolley Motor Insulation
8、and Time Rating2.4.4.6 Micro-Motors2.4.5 Electric Brakes2.4.5.1 Brakes2.4.5.2 Hoist Brake Time Delay2.4.5.3 Automatic Stop System2.4.6 Control System2.4.6.1 Control Panels2.4.6.2 Bridge and Trolley Control2.4.6.3 Drift Point2.4.7 Cab Control Station2.4.7.1 General2.4.7.2 Cab Indications2.4.7.3 Cab C
9、ontrols2.4.7.4 Cab Heating and Ventilating and Air-Conditioning2.4.8 Pendant Control Station2.4.8.1 General2.4.8.2 Operating Pushbuttons2.4.8.3 Light Indicators2.4.8.4 Pendant Drive Control2.4.8.5 Transfer of Control Stations2.4.9 Radio Remote Control, Infrared Remote Control2.4.9.1 General2.4.9.2 T
10、ransmitter2.4.10 Protection2.4.10.1 Main Line Disconnect2.4.10.2 Isolation TransformerSECTION 41 22 13.13 Page 2Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-2.4.10.3 Surge Protection2.4.10.4 Circuit Breakers2.4.10.5 Overloads2.4.11 Limit-Switches2
11、.4.11.1 Bridge and Trolley Travel Limit-Switches2.4.11.2 Rail Clamp Limit-Switches2.4.12 Wiring2.4.13 Electrification2.4.13.1 Main Power Electrification2.4.13.2 Crane Runway Conductors2.4.13.3 Bridge Span Conductors2.4.13.4 Pendant Festoon System2.4.13.5 Pendant Drive System2.4.13.6 Pendant Retracti
12、on System2.4.14 Special Requirements2.4.14.1 Warning Horn2.4.14.2 Accessory Power2.4.14.3 Receptacles2.4.14.4 Lighting2.4.14.5 Wind Indication and Alarm2.4.14.6 Electrically-Driven Oil Pump Alarm2.4.15 Load-Limit System2.4.15.1 Load-Sensing Electronics2.4.15.2 Alarm and Indicator Light2.4.16 Fungus
13、Resistance2.5 ELECTROMAGNETIC INTERFERENCE SUPPRESSION2.5.1 Shielded Cable2.5.2 EMI/RFI Shielded Boxes2.5.2.1 General2.5.2.2 Construction2.5.2.3 Attenuation2.5.2.4 Finish2.5.3 Drum GroundingPART 3 EXECUTION3.1 EXAMINATION3.2 ERECTION3.2.1 Shop Assembly3.2.2 Mechanical Alignment3.2.3 Electrical Align
14、ment3.2.4 Welding3.2.5 Field Painting3.3 ACCEPTANCE TESTING3.3.1 General3.3.1.1 Test Sequence3.3.1.2 Test Data3.3.1.3 Equipment Monitoring3.3.2 Trolley Travel3.3.3 Bridge Travel3.3.4 Bridge Crane Tests3.3.4.1 Dynamic Load Tests3.3.4.2 Trolley and Bridge Loss of Power Test3.3.5 Overload Tests3.3.6 Ac
15、celeration and Deceleration Tests3.3.7 Grounding Test3.3.8 Adjustments and Repairs3.4 SCHEMATIC DIAGRAMS3.5 MANUFACTURERS FIELD SERVICE REPRESENTATIVESECTION 41 22 13.13 Page 3Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-3.6 OPERATION AND MAINTENA
16、NCE MANUALS3.7 FIELD TRAINING3.8 FINAL ACCEPTANCE- End of Section Table of Contents -SECTION 41 22 13.13 Page 4Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-*USACE / NAVFAC / AFCESA / NASA UFGS-41 22 13.13 (April 2008)-Preparing Activity: NAVFAC Su
17、persedingUFGS-41 22 15.00 10 (April 2006)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated March 2008*SECTION 41 22 13.13BRIDGE CRANES04/08*NOTE: This guide specification covers the requirements for overhead electric traveling (OET) bridge cranes with capacities grea
18、ter than 9 tons 10 tons 9072 kg 20,000 pounds, but less than 27 metric tons 30 tons 27,000 kg 60,000 pounds, suitable for indoor or outdoor use in hazardous or non-hazardous environments.Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracke
19、ted items, choose applicable items(s) or insert appropriate information.Remove information and requirements not required in respective project, whether or not brackets are present.Comments and suggestions on this guide specification are welcome and should be directed to the technical proponent of th
20、e specification. A listing of technical proponents, including their organization designation and telephone number, is on the Internet.Recommended changes to a UFGS should be submitted as a Criteria Change Request (CCR).This guide specification includes tailoring options for NASA, USACE, NAVFAC, kilo
21、gram-pounds (per NAVFAC P-307), and tons. Selection or deselection of a tailoring option (select view-tailoring options) will include or exclude that option in the section. Specific project editing is still required for the resulting section.Forward all procurement of crane systems at Naval Shore ba
22、sed activities with rated capacities of 9072 kg (20,000 pounds) or greater, or for use in specialized applications to: Naval Facilities Engineering Command, Navy Crane Center, Building 491, Norfolk Naval Shipyard, Portsmouth, Va., SECTION 41 22 13.13 Page 5Provided by IHSNot for ResaleNo reproductio
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- NAVYUFGS412213132008BRIDGECRANESSUPERSEDEDARMYUFGS4122150010 桥式起重机 代替 ARMYUFGS4122150010PDF

链接地址:http://www.mydoc123.com/p-984867.html