ASTM C891-2011 Standard Practice for Installation of Underground Precast Concrete Utility Structures《地下预制混凝土公用设施装配标准》.pdf
《ASTM C891-2011 Standard Practice for Installation of Underground Precast Concrete Utility Structures《地下预制混凝土公用设施装配标准》.pdf》由会员分享,可在线阅读,更多相关《ASTM C891-2011 Standard Practice for Installation of Underground Precast Concrete Utility Structures《地下预制混凝土公用设施装配标准》.pdf(3页珍藏版)》请在麦多课文档分享上搜索。
1、Designation: C891 11Standard Practice forInstallation of Underground Precast Concrete UtilityStructures1This standard is issued under the fixed designation C891; the number immediately following the designation indicates the year oforiginal adoption or, in the case of revision, the year of last revi
2、sion. A number in parentheses indicates the year of last reapproval. Asuperscript epsilon () indicates an editorial change since the last revision or reapproval.1. Scope1.1 This practice covers the procedures to be followed in theplanning, site preparation, and installation of undergroundprecast con
3、crete utility structures. Concrete pipe and boxculverts are not covered under this practice. Also, precastconcrete manholes covered in Specification C478 are excludedfrom this practice.1.2 The values stated in inch-pound units are to be regardedas standard. The values given in parentheses are mathem
4、aticalconversions to SI units that are provided for information onlyand are not considered standard.1.3 This standard does not purport to address all of thesafety concerns, if any, associated with its use. It is theresponsibility of the user of this standard to establish appro-priate safety and heal
5、th practices and determine the applica-bility of regulatory limitations prior to use.2. Referenced Documents2.1 ASTM Standards:2C478 Specification for Precast Reinforced Concrete Man-hole Sections3. Survey3.1 The installation area shall be surveyed using the work-print and a checklist to identify th
6、e work to be done and todetermine that the plans are correct.3.1.1 The location of the utility structure should be where itwill cause minimum interference with traffic and shall beclearly defined on work prints.3.1.2 All underground facilities and structures such as gas,water, sewer, power, telephon
7、e cable, and so forth shall belocated and identified. Location markings shall be placed bythe affected utilities before the construction.3.2 The survey shall identify any obstacles such as overheadwires, building structures, and so forth that will interfere withcrane operations, work progress, or cr
8、eate a safety hazard.Precautionary arrangements shall be made before excavationbegins.3.3 The survey shall give consideration to the soil structureso that proper shoring, sloping, or both, may be planned inadvance of the excavation work.4. Planning4.1 Permits required to do work in accordance with t
9、hedetail plans shall be secured before starting the job. All permitsor a record of the permits shall be retained on the job forimmediate reference.4.2 All utilities and owners of surface and subsurfacefacilities and structures in the area shall be given advancenotification of proposed excavation. Ev
10、ery effort shall be madeto avoid damage to the facilities of others. If any damageoccurs, the owner of the damaged facility shall be notifiedimmediately.4.3 Planning shall include the coordination of all respon-sible parties to ensure that arrangements for removal of brokenpavement, rocks, excess sp
11、oil, and so forth have been made.Responsible parties shall arrange for the delivery, distribution,and storage of required material. If such material cannot bestored on the site, other storage areas must be provided.4.4 Should it appear that a structure location will interferewith traffic, review the
12、 situation with the engineer and notifyappropriate authorities.4.5 Provide for access to call boxes, fire hydrants, etc.5. Safety Requirements5.1 Safety requirements for construction shall be in accor-dance with all federal, state, and local regulations.1This practice is under the jurisdiction of AS
13、TM Committee C27 on PrecastConcrete Products and is the direct responsibility of Subcommittee C27.10 onUtility Structures.Current edition approved Jan. 1, 2011. Published January 2011. Originallyapproved in 1978. Last previous edition approved in 2009 as C891 09. DOI:10.1520/C0891-11.2For referenced
14、 ASTM standards, visit the ASTM website, www.astm.org, orcontact ASTM Customer Service at serviceastm.org. For Annual Book of ASTMStandards volume information, refer to the standards Document Summary page onthe ASTM website.1Copyright ASTM International, 100 Barr Harbor Drive, PO Box C700, West Cons
15、hohocken, PA 19428-2959, United States.5.2 The utility structure or any sections that comprise thestructure assembly shall only be lifted at the lifting points sodesignated by the manufacturer.5.2.1 The weight of each section to be handled shall beclearly indicated by marking of the section or clear
16、ly indicatedon the delivery documents.6. Excavating6.1 Coordinate the various excavation operations from thepoint of opening the pavement to completion of backfill so thatthe work area thus occupied is kept to a minimum consistentwith the conditions governing the work. This is particularlyimportant
17、where an excavation is adjacent to hospitals, policeand fire department buildings, service stations, and so forth.6.2 If unforeseen facilities or obstructions are encountered,stop excavating operations immediately. Expose the obstruc-tions with wood handled digging tools and investigate themwith cau
18、tion. If there is any doubt as to the type of obstructionexposed, request positive identification from those suspected ofowning the facility and then proceed as circumstances dictate.6.3 Buried work frequently requires the use of heavyconstruction equipment and transport of heavy loads. Certainsoil
19、conditions may be encountered that will not support theseloads. To avoid hazards and unnecessary delays caused bycave-ins or equipment becoming mired, carefully observe theprevailing conditions beforehand and take appropriate preven-tive measures.6.4 When excavating across highways, streets, alleys,
20、drives, and walks, perform the work in a manner that willminimize interference with traffic. If necessary, bridge theopening with a structure of adequate strength to support anytraffic likely to pass over it. Handrails are required forstructures bridging sidewalk openings.6.5 Inspect excavations aft
21、er every rainstorm or otherhazard-increasing occurrence, and increase the protectionagainst slides and cave-ins, if necessary.6.6 In dewatering excavations, make certain that the dis-charge is carried to a suitable runoff point.6.7 The excavation size must allow for the overall as-sembled height of
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASTMC8912011STANDARDPRACTICEFORINSTALLATIONOFUNDERGROUNDPRECASTCONCRETEUTILITYSTRUCTURES 地下 预制 混凝土 公用设施

链接地址:http://www.mydoc123.com/p-508682.html