1、ASD-STAN STANDARD NORME ASD-STAN ASD-STAN NORM prEN 9239 Edition P 1 August 2014 PUBLISHED BY THE AEROSPACE AND DEFENCE INDUSTRIES ASSOCIATION OF EUROPE - STANDARDIZATION Rue Montoyer 10 - 1000 Brussels - Tel. 32 2 775 8126 - Fax. 32 2 775 8131 - www.asd-stan.org ICS: Descriptors: ENGLISH VERSION Ae
2、rospace series Programme Management Guide for the risk management Srie arospatiale Management de programme Recommandations pour la mise en uvre du management des Risques Luft- und Raumfahrt Programme Management Richtlinien zur Durchfhrung des Risikomanagement This “Aerospace Series“ Prestandard has
3、been drawn up under the responsibility of ASD-STAN (The AeroSpace and Defence Industries Association of Europe - Standardization). It is published for the needs of the European Aerospace Industry. It has been technically approved by the experts of the concerned Domain following member comments. Subs
4、equent to the publication of this Prestandard, the technical content shall not be changed to an extent that interchangeability is affected, physically or functionally, without re-identification of the standard. After examination and review by users and formal agreement of ASD-STAN, it will be submit
5、ted as a draft European Standard (prEN) to CEN (European Committee for Standardization) for formal vote and transformation to full European Standard (EN). The CEN national members have then to implement the EN at national level by giving the EN the status of a national standard and by withdrawing an
6、y national standards conflicting with the EN. Edition approved for publication 1st August 2014 Comments should be sent within six months after the date of publication to ASD-STAN Engineering Procedures Domain Copyright 2014 by ASD-STAN prEN 9239:2014 (E) 2 Contents Page Foreword 2 Introduction . 3 1
7、 Scope 3 2 Normative references 3 3 Terms and definitions . 4 4 Framework of Risk Management in the programme 5 4.1 General 5 4.2 Customers requirements . 5 4.3 Roles and Responsibilities . 5 4.4 Multidisciplinary groups . 6 5 Risk Management process. 6 5.1 Steps of risk management 6 5.2 Process syn
8、optic . 12 5.3 Consolidation of risk . 13 5.4 Maturity of programme Risk Management approach 13 6 Risk Management tools . 13 7 Awareness and Training . 14 8 Documentation . 14 9 Opportunity management concept 15 9.1 Opportunity management process 15 9.2 Identification of opportunities 15 9.3 Assessm
9、ent and prioritization of opportunities . 15 9.4 Opportunity treatment . 15 9.5 Secondary risks . 15 Annex A (informative) List type per category . 16 Annex B (informative) Example of risk sheet . 18 Annex C (informative) Example of qualitative and quantitative assessments 19 Annex D (informative) E
10、xample of 3 colour code criticality and acceptability matrix: general risk mapping 21 Annex E (informative) Example of Risks Portfolio . 22 Annex F (informative) Risk assessment report 23 Annex G (informative) Maturity of programme risk management: assessment criteria 24 Bibliography 28 Foreword Thi
11、s standard was reviewed by the Domain Technical Coordinator of ASD-STANs engineering procedure domain. After inquiries and votes carried out in accordance with the rules of ASD-STAN defined in ASD-STANs General Process Manual, this standard has received approval for Publication. prEN 9239:2014 (E) 3
12、 Introduction Risk Management forms an integral part of programme management. It should be implemented right from the start of the project feasibility phase and continue until material disposal. The ultimate goal is to contribute to an appropriate definition of programme objectives (costs, schedules
13、 and performances ) and to continuously ensure that they are met or enhanced, despite any events likely to affect the programme through its lifecycle. By implementing methods, the programme manager can manage risks in another way than by using intuitive and non-formalised procedures. The aim of this
14、 document is to describe the implementation of Risk Management within the Programme Management framework. It complements programme management guidelines EN 9200. This document is to be used as a basis, for any given programme, for negotiating the requirements and relationships between customers and
15、suppliers; they should comply with to ensure Management of Risk. 1 Scope This document allows to answer specific needs in the field of Aeronautics although it does not present any sectorial characteristic and may therefore apply to the needs of other areas. However, the specificity of some areas can
16、 lead to the use of existing sectorial standards such as EN ISO 17666 Space systems Risk management (ISO 17666:2003). This document: proposes the main steps for setting up Risk Management framework within programme Management. This guideline may serve as a basis for writing a Risk Management specifi
17、cation; describes a process for controlling programme risks within the defined boundaries that are considered as tolerable. This standard process can be used as a methodological guide for writing the programme Risk Management Plan; recognises the need for knowledge management related to Risk Managem
18、ent, in order to capitalize and to share lessons learnt with other programmes, as well as the maturity assessment of the Risk Management; identifies useful documents for Risk Management; proposes an example of a typical checklist of risks related to a programme; in addition: this document addresses
19、opportunities. An opportunity is an uncertain event with positive consequences on the programme. 2 Normative references The following documents, in whole or in part, are normatively referenced in this document and are indispensable for its application. For dated references, only the edition cited ap
20、plies. For undated references, the latest edition of the referenced document (including any amendments) applies. EN 9200, Aerospace series Programme management Guidelines for project management specification prEN 9239:2014 (E) 4 3 Terms and definitions For the purposes of this document, the followin
21、g terms and definitions apply. 3.1 risk uncertain event or circumstance which could have a negative impact on the objectives of the programme 3.2 cause event which is at the origin of a potential risk 3.3 severity assessment of the significance of a risk impact with respect to the potential conseque
22、nces on a programme 3.4 impact effects of a risk on the programme should it occur 3.5 criticality/level of risk characteristic of the risk significance. It enables prioritization of the risks Note 1 to entry: It is generally the combination of the severity and the probability of the risk. 3.6 detect
23、ability ability or capacity to detect the direct trace of a risk or the triggering point of one of its causes 3.7 level of risk tolerance criticality value beyond which specific actions to treat the risk are required 3.8 likelihood / probability/occurrence of the risk assessment of the probability /
24、 likelihood or frequency of a risk to occur 3.9 risk portfolio represented set of identified risks intended to be treated 3.10 lessons learnt - experience feedback collection and exploitation, by all the stakeholders, of information concerning the events which have occurred throughout programme, rel
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASDSTANPREN92392014AEROSPACESERIESPROGRAMMEMANAGEMENTGUIDEFORTHERISKMANAGEMENTEDITIONP1PDF

链接地址:http://www.mydoc123.com/p-453780.html