AASHTO HB-17 DIVISION II SEC 13-2002 Division II Construction - Painting《涂漆》.pdf
《AASHTO HB-17 DIVISION II SEC 13-2002 Division II Construction - Painting《涂漆》.pdf》由会员分享,可在线阅读,更多相关《AASHTO HB-17 DIVISION II SEC 13-2002 Division II Construction - Painting《涂漆》.pdf(6页珍藏版)》请在麦多课文档分享上搜索。
1、Section 13 PAINTING 13.1 GENERAL 13.1.1 Description This work shall consist of the painting of surfaces shown on the plans or otherwise specified to be painted. The work includes, but is not limited to, the preparation of surfaces to be painted, application and curing of the paint, protection of the
2、 work, protection of existing facil- ities, vehicles and the public from damage due to this work, and the furnishing of all labor, equipment, and ma- terials needed to perform the work. the adjacent roadbed and shoulders with water or dust pal- liative for a sufficient distance on each side of the l
3、ocation where painting is being done. Upon completion of all painting operations and of any other work that would cause dust, grease, or other foreign materials to be deposited on the painted surfaces, the painted surfaces shall be thoroughly cleaned. At the time of opening structures to public traf
4、fic, the painting shall be completed, and the surfaces shall be undamaged and clean. 13.1.4 Color 13.1.2 Protection of Public and Property If not otherwise shown or specified, the color of the top or finish coat of paint shall be as directed by the Engineer. The Contractor shall comply with all appl
5、icable envi- ronmental protection and occupational safety and health standards, rules, regulations, and orders. Failure to com- ply with these standards, rules, regulations, and orders will be sufficient cause for suspension or disqualification. All reasonable precautions shall be taken to contain w
6、aste materials (used blasting material and old Paint) classified as hazardous. Disposal of hazardous waste ma- teria1 shall be performed in accordance with all applicable federal, state, and local laws. 13.2.2 Weather Conditions The Contractor shall provide protective devices such as tarps, screens
7、or covers as necessary to prevent damage to the Work and to other Property Or Persons from all cleaning and painting operations. Paint Or Paint Stains that result in an unsightly aP- pearance On Surfaces not designated to be painted shall be removed or obliterated by the Contractor at own ex- pense.
8、 13.1.3 Protection of the Work 13.2 PAINTING METAL STRUCTURES 13.2.1 Coating Systems and Paints The coating system and paints to be applied shall con- sist of the system in Table 13.2.1 which is specified for use or modified by fie special provisions. Paint shall be applied only on thoroughly dry su
9、rfaces. Painting will not be permitted when the atmospheric tem- perature, paint, or the surface to be painted is at or below 40F or above 100“F, or when metal surfaces are less than 5F above the dew point, or when the humidity exceeds 85% at the site of the work, or when freshly painted sur- faces
10、may become damaged by rain, fog, or dust, or when it can be anticipated that the atmospheric temperature will drop below 40F during the drying period, except as pro- vided herein for painting in enclosures. Metal surfaces which are hot enough to cause the paint to blister, to pro- duce a porous pain
11、t film, or to cause the vehicle to sepa- rate from the pigment shall not be painted. Subject to approval of the Engineer, the Contractor may provide a suitable enclosure to permit painting dur- ing inclement weather. Provisions shall be made to artifi- All painted surfaces that are marred or damaged
12、 as a result of operations of the Contractor shall be repaired by the Contractor, at own expense, with materials and to a condition equal to that of the coating specified herein. If traffic causes an objectionable amount of dust, the Contractor, when directed by the Engineer, shall sprinkle 59 1 592
13、 HIGHWAY BRIDGES 13.2.2 TABLE 13.2.1 High Pollution and Mild Climate or Maintenance Coastal Mild Climate Repainting Primer Inorganic Zinc-3 mils. Organic Zinc-3 mils. OilAlkyd-2 mils. Intermediate Coat Epoxy 2 mils or Vinyl Epoxy 2 mils. or Vinyl OilAlkyd-2 mils. Top Coat Epoxy, Vinyl, or Epoxy, Vin
14、yl, or OiYAlkyd-2 mils. Total System 5.3-7 mils. 5.3-7 mils. 6 mils. Wash Primer 0.3-0.5 mils. Wash Primer 0.3-0.5 mils. Urethane-2 mils. Urethane-2 mils. Notes: (1) Except for vinyl wash primer, the coating and system thicknesses shown are minimums. (2) Coating systems shown for severe areas are sa
15、tisfactory in less severe areas. (3) Coastal-within 1,O feet of ocean or tidal water. High Pollution-air pollution environment such as industrial areas. Mild-othex than (4) Inorganic zinc paint shall meet the requirements of Military Specification DOD-P-23236A (SH). (5) Organic zinc paint shall meet
16、 the requirements of Military Specification DOD-F21035A. (6) Vinyl Wash Primer shall meet the requirements of Military Specification DOD-P-15328D. (7) Vinyl top coat paint shall meet the requirements of the Steel Structures Painting Council, SSPC-Paint 9. (8) Epoxy paint shall meet the requirements
17、of the Steel Structures Painting Council, SSPC-22. (9) OiVAUcyd primer and intermediate coat paint shall meet the requirements of the Steel Structures Painting Council, SSPC-Paint 25. coastal area not in air pollution environment. (10) OilAlkyd top coat paint shall meet the requirements of the Steel
18、 Structures Painting Council, SSPC-Paint 104. (1 1) Urethane top coat paint shall meet the recommendations of the Steel Structures Painting Council, SSPC-PS Guide 1700. (12) Paints are hazardous because of their flammability and potential toxicity. Safe handling practices are required and should inc
19、lude, but not be limited to, the provisions of SSPC-PA Guide 3, “A Guide to Safety in Paint Application.” cially control atmospheric conditions inside the enclo- sure within limits suitable for painting throughout the painting operation. Surfaces painted under cover in damp or cold weather shall rem
20、ain under cover until the paint dries or weather conditions permit open exposure. Full compensation for providing and maintaining such en- closures shall be considered as included in the prices paid for the various contract items of work involving painting and no additional compensation will be allo
21、wed therefore. All blast cleaning, except that performed within closed buildings, and all painting shall be performed during day- light hours unless otherwise provided by the contract doc- uments. 13.2.3 Surface Preparation All exposed surfaces of structural steel, except galva- nized or metalized s
22、urfaces, shall be cleaned and painted. All surfaces of new structural steel shall be cleaned by the blast-cleaning method unless otherwise specified in the special provisions, or approved in writing by the En- gineer. In repainting existing steel structures the method of cleaning shall be as specifi
23、ed in the special provisions. Any damage to sound paint, on areas not designated for treatment, resulting from the Contractors operations shall be repaired by the Contractor at own expense to the satis- faction of the Engineer. The methods used in the cleaning of metal surfaces shall conform to the
24、following. 13.2.3.1 Blast Cleaning Abrasives used for blast cleaning shall be either clean dry sand, mineral grit, steel shot, or steel grit, at the option of the Contractor, and shall have a suitable grading to pro- duce satisfactory results. The use of other abrasives will not be permitted unless
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
5000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- AASHTOHB17DIVISIONIISEC132002DIVISIONIICONSTRUCTIONPAINTING 涂漆 PDF

链接地址:http://www.mydoc123.com/p-417579.html