1、Section 11 STEEL STRUCTURES 11.1 GENERAL 11.1.1 Description This work shall consist of furnishing, fabricating, and erecting steel structures and structural steel portions of other structures in accordance with these Specifications, the Special Provisions and the details shown on the plans. The stru
2、ctural steel fabricating plant shall be certified under the AISC Quality Certification Program, Category I. The fabrication of fracture critical members shall be Category III. Details of design which are permitted to be selected by the Contractor shall conform to Division I of these Specifications.
3、Painting shall conform to the provisions of Section 13, “Painting,” of these Specifications. Falsework used in the erection of structural steel shall conform to the provisions of Section 3, “Temporary Works,” of these Specifications. Structural components designated on the plans or in the special pr
4、ovisions as “fracture critical” shall conform to the provisions of Chapter 12 of the ANSI/AASHTO/ AWS D1.5 Bridge Welding Code. Welding and weld qualification tests shall conform to the provisions of the current ANSI/AASHTO/AWS D1.5 Bridge Welding Code. 11.1.2 Notice of Beginning of Work The Contrac
5、tor shall give the Engineer ample notice of the beginning of work at the mill or in the shop, so that in- spection may be provided. The term “mili” means any rolling mill or foundry where material for the work is to be manufactured. No material shall be manufactured, or work done in the shop, before
6、 the Engineer has been so notified. 11.1.3 Inspection Structural steel will be inspected at the fabrication site. The Contractor shall furnish to the Engineer a copy of all mill orders and certified mill test reports. Mill test reports shall show the chemical analysis and physical test results for e
7、ach heat of steel used in the work. With the approval of the Engineer, certificates of com- pliance shall be furnished in lieu of mill test reports for material that normally is not supplied with mill test re- ports, and for items such as fills, minor gusset plates and similar material when quantiti
8、es are small and the mater- ial is taken from stock. Certified mill test reports for steels with specified impact values shall include, in addition to other test re- sults, the results of Charpy V-notch impact tests. When fine grain practice is specified, the test report shall confirm that the mater
9、ial was so produced. Copies of mill orders shall be furnished at the time orders are placed with the manufacturer. Certified mill test reports and Certificates of Compliance shall be furnished prior to the start of fabrication of material covered by these reports. The Certificate of Compliance shall
10、 be signed by the manufacturer and shall certify that the material is in conformance with the specifications to which it has been manufactured. Material to be used shall be made available to the Engineer so that each piece can be examined. The Engi- neer shall have free access at all times to any po
11、rtion of the fabrication site where the material is stored or where work on the material is being performed. 11.1.4 Inspectors Authority The Inspector shall have the authority to reject materi- als or workmanship which do not fulfill the requirements of these Specifications. In cases of dispute, the
12、 Contractor may appeal to the Engineer, whose decision shall be final. Inspection at the mill and shop is intended as a means of facilitating the work and avoiding errors, and it is ex- pressly understood that it will not relieve the Contractor of any responsibility in regard to defective material o
13、r workmanship and the necessity for replacing the same. The acceptance of any material or finished members by the Inspector shall not be a bar to their subsequent rejec- tion, if found defective. Rejected materials and workman- 565 566 HIGHWAY BRIDGES 11.1.4 ship shall be replaced as soon as practic
14、al or corrected by the Contractor. 11.2 WORKING DRAWINGS The Contractor shall expressly understand that the En- gineers approval of the working drawings submitted by the Contractor covers the requirements for “strength and detail,” and that the Engineer assumes no responsibility for errors in dimens
15、ions. Working drawings must be approved by the Engineer prior to performance of the work involved and such ap- proval shall not relieve the Contractor of any responsibil- ity under the contract for the successful completion of the work. 11.2.1 Shop Drawings The Contractor shall submit copies of the
16、detailed shop drawings to the Engineer for approval. Working drawings shall be submitted sufficiently in advance of the start of the affected work to allow time for review by the Engineer and corrections by the Contractor without delaying the work. Working drawings for steel structures shall give fu
17、ll detailed dimensions and sizes of component parts of the structure and details of all miscellaneous parts, such as pins, nuts, bolts, drains, etc. Where specific orientation of plates is required, the di- rection of rolling of plates shall be shown. Working drawings shall specifically identify eac
18、h piece that is to be made of steel which is to be other than AASHTO M 270 (ASTM A 709) Grade 36 steel. 11.2.2 Erection Drawings The Contractor shall submit drawings illustrating fully his or her proposed method of erection. The drawings shall show details of all falsework bents, bracing, guys, dead
19、-men, lifting devices, and attachments to the bridge members: sequence of erection, location of cranes and barges, crane capacities, location of lifting points on the bridge members, and weights of the members. The plan and drawings shall be complete in detail for all anticipated phases and conditio
20、ns during erection. Calculations may be required to demonstrate that allowable stresses are not exceeded and that member capacities and final geometry will be correct. 11.2.3 Camber Diagram A camber diagram shall be furnished to the Engineer by the Fabricator, showing the camber at each panel point
21、in the cases of trusses or arch ribs, and at the location of field splices and fractions of span length (V4 points mini- mum) in the cases of continuous beam and girders or rigid frames. The camber diagram shall show calculated cam- bers to be used in preassembly of the structure in accor- dance wit
22、h Article 11.5.3. 11.3 MATERIALS 11.3.1 Structural Steel 11.3.1.1 General Steel shall be furnished according to the following specifications. The grade or grades of steel to be furnished shall be as shown on the plans or specified. All steel for use in main load-carrying member com- ponents subject
23、to tensile stresses shall conform to the ap- plicable Charpy V-notch Impact Test requirements of AASHTO M 270 (ASTM A 709). Welded girders made of ASTM A 709, Grade HPS70W steels shall be fabricated in accordance with the AASHTO Guide Specijcations for Highway Bridge Fab- rication with HPS70 W Steel
24、, which supplements the ANSI/AASHTO/AWS DIS Bridge Welding Code. 11.3.1.2 Carbon Steel Unless otherwise specified, structural carbon steel for bolted or welded construction shall conform to: Struc- tural Steel for Bridges, AASHTO M 270 (ASTM A 709) Grade 36. 11.3.1.3 High-Strength Low-Alloy Structur
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
5000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- AASHTOHB17DIVISIONIISEC112002DIVISIONIICONSTRUCTIONSTEELSTRUCTURESERRATA012003 钢结构 PDF

链接地址:http://www.mydoc123.com/p-417577.html