How the Power Grid Behaves.ppt
《How the Power Grid Behaves.ppt》由会员分享,可在线阅读,更多相关《How the Power Grid Behaves.ppt(61页珍藏版)》请在麦多课文档分享上搜索。
1、1,How the Power Grid Behaves,Tom Overbye Department of Electrical and Computer Engineering University of Illinois at Urbana-Champaign,2,Presentation Overview,Goal is to demonstrate operation of large scale power grid. Emphasis on the impact of the transmission syste. Introduce basic power flow conce
2、pts through small system examples. Finish with simulation of Eastern U.S. System.,3,PowerWorld Simulator,PowerWorld Simulator is an interactive, Windows based simulation program, originally designed at University of Illinois for teaching basics of power system operations to non-power engineers. Powe
3、rWorld Simulator can now study systems of just about any size.,4,Eastern Interconnect Operating Areas,Ovals represent operating areas,Arrows indicate power flow in MW between areas,5,Zoomed View of Midwest,6,Power System Basics,All power systems have three major components: Generation, Load and Tran
4、smission. Generation: Creates electric power. Load: Consumes electric power. Transmission: Transmits electric power from generation to load.,7,One-line Diagram,Most power systems are balanced three phase systems. A balanced three phase system can be modeled as a single (or one) line. One-lines show
5、the major power system components, such as generators, loads, transmission lines. Components join together at a bus.,8,Eastern North American High Voltage Transmission Grid,Figure shows transmission lines at 345 kV or above in Eastern U.S.,9,Zoomed View of Midwest,Arrows indicate MW flow on the line
6、s; piecharts show percentage loading of lines,10,Example Three Bus System,Generator,Load,Bus,Circuit Breaker,Pie charts show percentage loading of lines,11,Generation,Large plants predominate, with sizes up to about 1500 MW. Coal is most common source, followed by hydro, nuclear and gas. Gas is now
7、most economical. Generated at about 20 kV.,12,Loads,Can range in size from less than a single watt to 10s of MW. Loads are usually aggregated. The aggregate load changes with time, with strong daily, weekly and seasonal cycles.,13,Transmission,Goal is to move electric power from generation to load w
8、ith as low of losses and cost as possible. P = V I or P/V = I Losses are I2 R Less losses at higher voltages, but more costly to construct and insulate.,14,Transmission and Distribution,Typical high voltage transmission voltages are 500, 345, 230, 161, 138 and 69 kV. Transmission tends to be a grid
9、system, so each bus is supplied from two or more directions. Lower voltage lines are used for distribution, with a typical voltage of 12.4 kV. Distribution systems tend to be radial. Transformers are used to change the voltage.,15,Other One-line Objects,Circuit Breakers - Used to open/close devices;
10、 red is closed, green is open. Pie Charts - Show percentage loading of transmission lines. Up/down arrows - Used to control devices. Values - Show current values for different quantities.,16,Power Balance Constraints,Power flow refers to how the power is moving through the system. At all times the t
11、otal power flowing into any bus MUST be zero! This is know as Kirchhoffs law. And it can not be repealed or modified. Power is lost in the transmission system.,17,Basic Power Control,Opening a circuit breaker causes the power flow to instantaneously(nearly) change. No other way to directly control p
12、ower flow in a transmission line. By changing generation we can indirectly change this flow.,18,Flow Redistribution Following Opening Line Circuit Breaker,Power Balance must be satisfied at each bus,No flow on open line,19,Indirect Control of Line Flow,Generator MW output changed,Generator change in
13、directly changes line flow,20,Transmission Line Limits,Power flow in transmission line is limited by a number of considerations. Losses (I2 R) can heat up the line, causing it to sag. This gives line an upper thermal limit. Thermal limits depend upon ambient conditions. Many utilities use winter/sum
14、mer limits.,21,Overloaded Transmission Line,Thermal limit of 150 MVA,22,Interconnected Operation,Power systems are interconnected across large distances. For example most of North American east of the Rockies is one system, with most of Texas and Quebec being major exceptions Individual utilities on
15、ly own and operate a small portion of the system, which is referred to an operating area (or an area).,23,Operating Areas,Areas constitute a structure imposed on grid. Transmission lines that join two areas are known as tie-lines. The net power out of an area is the sum of the flow on its tie-lines.
16、 The flow out of an area is equal to total gen - total load - total losses = tie-flow,24,Three Bus System Split into Two Areas,Net tie flow is NOT zero,Initially area flow is not controlled,25,Area Control Error (ACE),The area control error mostly the difference between the actual flow out of area,
17、and scheduled flow. ACE also includes a frequency component. Ideally the ACE should always be zero. Because the load is constantly changing, each utility must constantly change its generation to “chase” the ACE.,26,Home Area ACE,ACE changes with time,27,Inadvertent Interchange,ACE can never be held
18、exactly at zero. Integrating the ACE gives the inadvertent interchange, expressed in MWh. Utilities keep track of this value. If it gets sufficiently negative they will “pay back” the accumulated energy. In extreme cases inadvertent energy is purchased at a negotiated price.,28,Automatic Generation
19、Control,Most utilities use automatic generation control (AGC) to automatically change their generation to keep their ACE close to zero. Usually the utility control center calculates ACE based upon tie-line flows; then the AGC module sends control signals out to the generators every couple seconds.,2
20、9,Three Bus Case on AGC,With AGC on, net tie flow is zero, but individual line flows are not zero,30,Generator Costs,There are many fixed and variable costs associated with power system operation. Generation is major variable cost. For some types of units (such as hydro and nuclear) it is difficult
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
2000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- HOWTHEPOWERGRIDBEHAVESPPT
