【计算机类职业资格】PMP资格认证考试-项目范围管理及答案解析.doc
《【计算机类职业资格】PMP资格认证考试-项目范围管理及答案解析.doc》由会员分享,可在线阅读,更多相关《【计算机类职业资格】PMP资格认证考试-项目范围管理及答案解析.doc(18页珍藏版)》请在麦多课文档分享上搜索。
1、PMP 资格认证考试-项目范围管理及答案解析(总分:50.00,做题时间:90 分钟)一、B单项选择题/B(总题数:50,分数:50.00)1.Scope change control MUST be integrated with all of the following control processes EXCEPT _ .(分数:1.00)A.scheduleB.costC.procurementD.quality2.Your company, HealtNut Inc. , is a leading marketer of dietary supplements that can b
2、e produced quickly and without regulatory approval. Management wants to explore new markets and new products to boost revenue and profits. You are leading a team to identify potential products. Because of your background and interest in information technology, you recommended developing wireless com
3、munications products. But when you submitted the idea for review, executive management informed you that this product would not fit with the organizations core competencies. You need to go back to the drawing board and recommend other products using managements guideline as _ .(分数:1.00)A.an assumpti
4、onB.a constraintC.a specificationD.a technical requirement3.You are the project manager of a civil construction company involved with building houses. In your project, you often use work breakdown structures (WBS)from your previous projects as templates. A work breakdown structure can be used for al
5、l the following except _ .(分数:1.00)A.tracking project performance against cost and scheduleB.creating a network diagram, with task dependenciesC.creating a project scheduleD.assigning resources to work on different work elements4.An example of scope verification is _ .(分数:1.00)A.review the performan
6、ce of an installed software moduleB.managing changes to the project scheduleC.decomposing the WBS to a work package levelD.performing a benefit/cost analysis to determine if we should proceed with the project5.All of the following assist in determining the impact of a scope change EXCEPT_.(分数:1.00)A
7、.project charterB.baselineC.performance measurementD.milestones6.Which of the following tool is used for scope verification?(分数:1.00)A.Performance measuremenB.Scope change control systeC.InspectioD.Earned valu7.In your project, you use product analysis to translating project objectives into tangible
8、 deliverables and requirements. All the following tools are used for product analysis EXCEPT _ .(分数:1.00)A.value engineeringB.value analysisC.product breakdownD.benefit/cost analysis8.The causes of variances and the reasoning behind the corrective action chosen are summarized the _ .(分数:1.00)A.work
9、breakdown structureB.accounting codes for the activitiesC.lessons learnedD.performance reports9.Decomposition is the subdivision of project deliverables into smaller, more manageable components until the work and deliverables are defined at the work package level. This is a valuable tool for define
10、scope. However, decomposition may not be possible for a deliverable or subproject if:(分数:1.00)A.The deliverable or subproject is very complicateB.The deliverable or subproject is already being produceC.The deliverable or subproject will be accomplished after a very long time ( far into the futuD.Non
11、e of the above: Decomposition of deliverables is always possibl10.Completion of project scope activities is not measured against the _ .(分数:1.00)A.scope statementB.requirementsC.WBS dictionaryD.WBS11.What is the WBS typically used for?(分数:1.00)A.To organize and define the total scope of the projecB.
12、To identify the logical person to be project sponsoC.To define the level of reporting the seller provides the buyeD.As a record of when work elements are assigned to individual12.A work breakdown structure (WBS) numbering system should allow project staff to _ .(分数:1.00)A.identify the level at which
13、 individual WBS elements are foundB.identify configuration management milestonesC.estimate the costs of WBS elementsD.provide project justification13.The work breakdown structure is an excellent tool for objective control and evaluation. Which of the following is generally not validated through the
14、WBS?(分数:1.00)A.Time, schedule, and cosB.Management coordination and organizational structurinC.Risk and impact of decisionmakinD.Quality of the wor14.What is the document that forms the basis for an agreement among project team numbers and customer by identifying both the project objectives and the
15、major project deliverables?(分数:1.00)A.Project statement of worB.Configuration management requiremenC.Project scope statemenD.Work breakdown structur15.Which of the following is an example of a constraint?(分数:1.00)A.A predefined budgeB.The threat of a strike by a subcontractoC.Relationship with the s
16、elleD.The method used to measure project performanc16.Scope planning for a project is _ .(分数:1.00)A.the project specification that includes design principles and project objectivesB.a three-level project work breakdown structureC.the process of creating a project scope management planD.the record sh
17、owing that all project deliverables are completed satisfactorily17.Generally accepted methods for translating project objectives into tangible deliverables and requirements is also referred to as _ .(分数:1.00)A.product analysisB.risk measurementC.alternatives identificationD.benefit/cost analysis18.Y
18、ou have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. Which document provides this information?(分数:1.00)A.Resource assignment matriB.Change control plaC.Project charteD.Client organization char19.What may the project t
19、eam do to confirm the scope of the project is on track?(分数:1.00)A.Review change requests that have been submitted and approveB.Obtain status from responsible individuals on the teaC.Conduct walkthrough, inspections and reviewD.Complete a scope report and submit it to managemen20.Which of the followi
20、ng statements relating to assumptions is inaccurate?(分数:1.00)A.They are factors which are considered to be true, real or certaiB.They affect all aspects of project planninC.They are progressively elaborateD.They limit the project teams option21.The purpose of the scope statement includes all but whi
21、ch of the following:(分数:1.00)A.Provides a basis for future project decisionB.Establishes a contract between the project team and the customeC.Sets criteria to use to determine if a project or phase have been completed successfullD.Establishes project constraints and assumption22.The PM and the proje
22、ct team have completed decomposition and have verified scope, when the marking department makes a minor change to the product functionality to improve its appeal to the end customer. The PM and the project team _ .(分数:1.00)A.refuses to accept the change since the scope has been verifiedB.modifies th
23、e WBS and the decompositionC.accepts the change and incorporates it into the WBS, modifying the budget and the schedule and assigning accountability to the marking teamD.proceeds per the change process23.A code of accounts _ .(分数:1.00)A.is any numbering system used to uniquely identify each componen
24、t of the work breakdown structureB.includes work packages, used to track phase completionC.is an organizational scheme to keep track of contractsD.charts elements of the WBS against the timeline24.A project manager believes that modifying the project scope may provide added value for the customer. W
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
5000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 计算机 职业资格 PMP 资格 认证 考试 项目 范围 管理 答案 解析 DOC