1、PMP 资格认证考试-项目范围管理(一)及答案解析(总分:50.00,做题时间:90 分钟)一、单项选择题(总题数:50,分数:50.00)1.Inputs used during scope planning include all of the following EXCEPT _ . A) constraints B) project charter C) budget/cost analysis D) product description(分数:1.00)A.B.C.D.2.Scope change control MUST be integrated with all of the
2、 following control processes EXCEPT _ . A) schedule B) cost C) procurement D) quality(分数:1.00)A.B.C.D.3.Scope definition is _ . A) the process of developing a detailed project scope statement as the basis for future project decisions B) determining the responses needed to perform project activities
3、C) analysis of activity sequence, duration, and resource requirements D) a written statement identifying the quality standards relevant to the project(分数:1.00)A.B.C.D.4.A KEY activity for achieving customer satisfaction is to define _ . A) the business use B) requirements C) product specificity D) c
4、hange control(分数:1.00)A.B.C.D.5.A precision description of a deliverable is called a _ . A) Specification B) Baseline C) Work package D) Work breakdown structure element(分数:1.00)A.B.C.D.6.An output of scope definition is _ . A) work breakdown structure (WBS) B) resource breakdown structure (RBS) C)
5、project scope statement D) schedule delays control plan(分数:1.00)A.B.C.D.7.You are the project manager of a civil construction company involved with building houses. In your project, you often use work breakdown structures (WBS)from your previous projects as templates. A work breakdown structure can
6、be used for all the following except _ . A) tracking project performance against cost and schedule B) creating a network diagram, with task dependencies C) creating a project schedule D) assigning resources to work on different work elements(分数:1.00)A.B.C.D.8.Which of the following statements is tru
7、e about the WBS? A) The WBS is a deliverable oriented hierarchical decomposition of the work to be executed by the project team, to accomplish the project objectives and create the required deliverables. B) The WBS is an unstructured list of activities in chart form. C) The WBS is the same as the or
8、ganizational breakdown structure. D) The WBS refers to the bill of materials.(分数:1.00)A.B.C.D.9.What is the document that forms the basis for an agreement among project team numbers and customer by identifying both the project objectives and the major project deliverables? A) Project statement of wo
9、rk. B) Configuration management requirement. C) Project scope statement. D) Work breakdown structure.(分数:1.00)A.B.C.D.10.Your company, HealtNut Inc. , is a leading marketer of dietary supplements that can be produced quickly and without regulatory approval. Management wants to explore new markets an
10、d new products to boost revenue and profits. You are leading a team to identify potential products. Because of your background and interest in information technology, you recommended developing wireless communications products. But when you submitted the idea for review, executive management informe
11、d you that this product would not fit with the organizations core competencies. You need to go back to the drawing board and recommend other products using managements guideline as _ . A) an assumption B) a constraint C) a specification D) a technical requirement(分数:1.00)A.B.C.D.11.All of the follow
12、ing are characteristics of a work package EXCEPT: A) It is a deliverable or project work component at the lowest level of each branch of the work breakdown structure. B) It is a summary task at the top level of the WBS. C) It includes the schedule activities required for completion of the deliverabl
13、e or project work component. D) It includes the schedule milestones required for completion of the deliverable or project work component.(分数:1.00)A.B.C.D.12.What is the WBS typically used for? A) To organize and define the total scope of the project. B) To identify the logical person to be project s
14、ponsor. C) To define the level of reporting the seller provides the buyer. D) As a record of when work elements are assigned to individuals.(分数:1.00)A.B.C.D.13.You have just taken control of a project in the middle of execution and need to learn who has approval authority for revisions in scope. Whi
15、ch document provides this information? A) Resource assignment matrix. B) Change control plan. C) Project charter. D) Client organization chart.(分数:1.00)A.B.C.D.14.The U.S. Bureau of Indian Affairs awarded your firm a contact to renovate an elementary school on a Navajo reservation. One contractual t
16、erm, Indian preference, requires you to hire native American Laborers and subcontractors from the reservation. This is an example of which type of the following constraints? A) Social. B) Economical. C) Environmental. D) Legal.(分数:1.00)A.B.C.D.15.Due to cuts in funding, your project has been termina
17、ted. The scope verification process _ . A) should be delayed until the project is completed B) should determine the correctness of the work results C) should establish and document the level and extent of completion D) will form the basis of the project audit(分数:1.00)A.B.C.D.16.During the project sc
18、ope planning process, the work breakdown structure should be developed to _ . A) the sub-project level B) the level determined by the project office C) a level allowing for adequate estimates D) the cost center level(分数:1.00)A.B.C.D.17.The decomposition process is a technique used to construct a _ .
19、 A) precedence network B) critical path method diagram C) variance analysis D) work breakdown structure(分数:1.00)A.B.C.D.18.A scope statement is important because it _ . A) provides the basis for making future project decisions B) provides a brief summary of the project C) approves the project for th
20、e stakeholders D) provides criteria for measuring project cost(分数:1.00)A.B.C.D.19.Which of the following is true about the WBS: A) The WBS is another term for the Gantt chart. B) Each descending level of the WBS represents an increasingly detailed definition of the project work. C) Work not in the W
21、BS is usually defined in the scope statement of the project. D) The WBS shows only the critical path activities.(分数:1.00)A.B.C.D.20.What may the project team do to confirm the scope of the project is on track? A) Review change requests that have been submitted and approved. B) Obtain status from res
22、ponsible individuals on the team. C) Conduct walkthrough, inspections and reviews. D) Complete a scope report and submit it to management.(分数:1.00)A.B.C.D.21.A code of accounts _ . A) is any numbering system used to uniquely identify each component of the work breakdown structure B) includes work pa
23、ckages, used to track phase completion C) is an organizational scheme to keep track of contracts D) charts elements of the WBS against the timeline(分数:1.00)A.B.C.D.22.The work breakdown structure is an excellent tool for objective control and evaluation. Which of the following is generally not valid
24、ated through the WBS? A) Time, schedule, and cost. B) Management coordination and organizational structuring. C) Risk and impact of decisionmaking. D) Quality of the work.(分数:1.00)A.B.C.D.23.Completion of project scope activities is not measured against the _ . A) scope statement B) requirements C)
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
5000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 计算机 职业资格 PMP 资格 认证 考试 项目 范围 管理 答案 解析 DOC