1、PMP 资格认证考试-项目成本管理(四)及答案解析(总分:20.00,做题时间:90 分钟)一、B单项选择题/B(总题数:20,分数:20.00)1.Using the table below, what is the Present Value of an annual expenditure of $4000 per year over the next three years at 10% per year? YearPresent Value of $1 at 10%Present Value of $ 1 at 12%0.9090.8260.7510.6830.8930.7970.7
2、120.636 A. $9608. B. $7206. C. $9944. D. $6551.(分数:1.00)A.B.C.D.2.The initial cost of your project is $25000, which will save the company $6000 per year for the next four years. Using the above table, if your company wants a 12% ROI, what is NPV of the project? A. - $1000. B. - $6772. C. + $1758. D.
3、 + $6772.(分数:1.00)A.B.C.D.3.Which one of the project estimation technique is normally used in conjunction with all of the other estimation method? A. Parametric. B. Bottom-up. C. Extrapolation. D. Historical.(分数:1.00)A.B.C.D.4.Sunk costs are _. A. dollars that have not been invested by are in the ma
4、nagement reserve B. cost that vary in total depending upon the activity of the project as compared to fixed costs C. another name for labor cost since these costs are already budgeted D. dollars already invested in the project will not affect the projects outcome regardless of what is done(分数:1.00)A
5、.B.C.D.5.Reserve funds are set aside for use when _. A. an up-scope of the project requires additional funds to compensate the initial budget B. they are needed for the sporadic fluctuation in potential labor rates when a union contract is under negotiation C. anticipated problems have been identifi
6、ed but not completely expected D. a fund used when the client requests an up-score for the project(分数:1.00)A.B.C.D.6.Which of the depreciation methods offers the least advantage? A. Double declining balance. B. Straight line. C. Sum of the years digit. D. Salvage value.(分数:1.00)A.B.C.D.7.Controling
7、cost is concerned with _. A. influencing the factors which create a change to the cost baseline B. managing the actual changes when and as they occur C. insuring that the customer knows that the project budget is under or over budget D. A and B(分数:1.00)A.B.C.D.8.Which is the most conservative of the
8、 work completion rules? A. 50/50 Rule. B. 0/100 Rule. C. 20/80 Rule. D. 100/100 Rule.(分数:1.00)A.B.C.D.9.Who is responsive for determining the project cost variance acceptable range? A. Functional manager. B. Department heads. C. The customer. D. The project Manager.(分数:1.00)A.B.C.D.10.Which is consi
9、dered the earned value? A. Budgeted Cost of Work Scheduled. B. Budgeted Cost of Work Performed. C. Actual Cost of Work Performed. D. Budgeted at Completion.(分数:1.00)A.B.C.D.11.What does a positive Cost Variance indicate? A. The project is over budget. B. There were not enough dollars allocated in th
10、e budget for the budget item. C. A cost underrun. D. The project is behind.(分数:1.00)A.B.C.D.12.What does a negative Schedule Variance indicate? A. The project is behind in the schedule. B. Up-scope is causing cost overruns. C. The project is ahead of schedule. D. The project is on schedule.(分数:1.00)
11、A.B.C.D.13.If a CV was positive and the SV was positive, what does this indicate? A. The project is over budget, but on schedules. B. The project is under budget, but behind schedules. C. The project is under budget, and ahead of schedules. D. The project is on budget and on schedules.(分数:1.00)A.B.C
12、.D.14.Why is cost management so difficult? A. Most activities are well defined and can be estimated accurately using industrial engineering techniques. B. Many activities have never been done in quite the same manner, under the same circumstances, or with the same people. C. The non-repetitiveness o
13、f the activities creates a high degree of dependency on the motivation of workers to accomplish their work in a timely manner. D. B and C.(分数:1.00)A.B.C.D.15.If the variable cost of producing a unit is $ 100 per unit and all fixed costs equals $2500, what will be the cost of producing ten extra unit
14、s? A. $3500. B. $1000. C. $25000. D. $1500.(分数:1.00)A.B.C.D.16.The project is expected to cost $ 20000. It is necessary to borrow all $ 20000 at the beginning of a five-year project at an interest rate of 10% compounded annually. What is the amount of interest that is paid at the end of the project?
15、 A. $12200. B. $32200. C. $10000. D. $2000.(分数:1.00)A.B.C.D.17.What is the fundamental weakness of the earned value concept? A. The inability to provide accurate estimates of the percentage of work completed. B. Not knowing the clients project scope as it relates to the current WBS. C. There is no w
16、eakness in this concept. D. Once the BCWP is calculated, it is too late to take corrective action on the project costs.(分数:1.00)A.B.C.D.18.Which one of the following estimates should least reflect the actual cost of the project ? A. Order of magnitude. B. Approximate. C. Definitive. D. Detailed desi
17、gn.(分数:1.00)A.B.C.D.19.What is the purpose of the contingency money in a cost estimate? A. Provides money to cover uncertainties in the estimate within the defined scope and schedule. B. Money to cover changes in scope. C. Money to cover unforeseen natural disasters. D. A and C.(分数:1.00)A.B.C.D.20.C
18、harles is working on a project and finds that one of his primary vendors is raising their costs for a key component of the product being produced by his project. In order to cover these costs, he _. A. will ask management for a budget increase to cover the difference B. will assume management reserv
19、e will cover the difference because this increase was out of his control C. will use the cost change control process to obtain approval to use part of the contingency allowance D. will go over budget and ask for forgiveness at the end of the project(分数:1.00)A.B.C.D.PMP 资格认证考试-项目成本管理(四)答案解析(总分:20.00,
20、做题时间:90 分钟)一、B单项选择题/B(总题数:20,分数:20.00)1.Using the table below, what is the Present Value of an annual expenditure of $4000 per year over the next three years at 10% per year? YearPresent Value of $1 at 10%Present Value of $ 1 at 12%0.9090.8260.7510.6830.8930.7970.7120.636 A. $9608. B. $7206. C. $994
21、4. D. $6551.(分数:1.00)A.B.C. D.解析:*根据下表,如果年消费是$4000,利息是 10%,那么三年后总消费的现值是多少? 年 现值年利息为 10%现值年利息为 12%12340.9090.8260.7510.6830.8930.7970.7120.636A) $9608。B) $7206。C) $9944。D) $6551。2.The initial cost of your project is $25000, which will save the company $6000 per year for the next four years. Using the
22、 above table, if your company wants a 12% ROI, what is NPV of the project? A. - $1000. B. - $6772. C. + $1758. D. + $6772.(分数:1.00)A.B. C.D.解析:*25000=-6772。 你项目的初始费用是$25000,这将在以后四年内每年节省公司$6000。使用上题中的表格,如果公司要求 12%的投资回报率,那么项目的净现值是多少? A) -$1000。 B) -$6772。 C) +$1758。 D) +$6772。3.Which one of the projec
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
5000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 计算机 职业资格 PMP 资格 认证 考试 项目 成本 管理 答案 解析 DOC