1、10-06M 31 63 26 - 1 SECTION 31 63 26 DRILLED CAISSONS SPEC WRITER NOTE: Delete between /-/ if not applicable to project. Also delete any other item or paragraph not applicable in the section and renumber the paragraphs. PART 1 - GENERAL 1.1 DESCRIPTION This section specifies excavation and concrete
2、required for construction of foundation caissons. SPEC WRITER NOTE: Obtain from Structural Engineer bearing material name which shall be same nomenclature as appears in SUB-SURFACE EXPLORATION REPORT. Insert name in following paragraph. 1.2 DEFINITIONS Satisfactory Bearing Material: _ and is assumed
3、 to occur at bottom of caisson elevations shown. 1.3 RELATED WORK A. Materials testing and inspection during construction: Section 01 45 29, TESTING LABORATORY SERVICES. B. Safety requirements and blasting operations: Section 00 72 00, GENERAL CONDITIONS, Article, ACCIDENT PREVENTION. C. Subsurface
4、Investigation: Section 01 00 00, GENERAL REQUIREMENTS, Article, PHYSICAL DATA D. Earth excavation: Section 31 20 00, EARTH MOVING. E. Concrete, including materials and mixes: Section 03 30 00, CAST-IN-PLACE CONCRETE. 1.4 CONTRACT BASIS A. Contract price for caissons will be based upon total length f
5、or each type of caisson shown. Length of caissons will be measured from bottom elevation to top elevation of the caisson. The diameter of the caisson is defined as the minimum diameter of the shaft. 1. Adjustment of contract price shall be based upon total length of each type of caisson placed and n
6、ot on the length of individual caissons. When the total length of each type of completed caisson is greater or less than the length shown due to unsuitable soils or design modifications by the Resident Engineer, contract price adjustment will be made in accordance with Articles, DIFFERING SITE Provi
7、ded by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-10-06M 31 63 26 - 2 CONDITIONS, CHANGES and CHANGES-SUPPLEMENT of the GENERAL CONDITIONS as applicable. 2. Contract price and time will be adjusted in accordance with Articles, DIFFERING SITE CONDITIONS, CHA
8、NGES and CHANGES-SUPPLEMENT of the GENERAL CONDITIONS as applicable, when artificial materials that are not shown are encountered. 1.5 CLASSIFICATION OF EXCAVATION A. Soil/Weathered Rock Excavation: SPEC WRITER NOTE: The requirements for track mounted power excavators may vary. Discuss with soils co
9、nsultant and modify as necessary. Soil or weathered rock that can be reasonably excavated with the rock auger, i.e. rock auger advancement greater than 150 mm (6 inches) per 15 minutes (see rock auger refusal, 1.5.C-2, below) B. Sloping Weathered Rock Excavation: Excavation of soil/weathered rock th
10、at can typically be excavated with the rock auger, except when the steeply sloping orientation of the stratum causes the rock auger to run askew. C. Rock Excavation: 1. Excavation of material that meets the rock auger refusal criteria and requires the rock core barrel or other hard rock excavation t
11、echniques for removal. 2. Rock auger refusal is defined as a penetration rate of less than 150 mm (6 inches) in 15 minutes, while operating a caisson drilling rig, rated with a torque capacity of at least 110 kN-meters (1,000,000 inch-pounds), applying a continuous down pressure of at least 220 kN (
12、50,000 pounds), equipped with a rock auger that contains conical carbide-tipped (“Kennemetal”) teeth. D. Nominal Soil or Weathered Rock Seams: Nominal soil or weathered rock seams below rock auger refusal will be excavated and considered as rock for rock excavation quantities. A nominal soil or weat
13、hered rock seam is one which is less than 600 mm (2 feet) thick. Where soil or weathered rock seams or voids of 600 mm (2 feet) or greater are excavated within a mixed rock/soil or rock/weathered rock profile, excavation is classified as soil/weathered rock excavation until rock auger refusal is aga
14、in established. Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-10-06M 31 63 26 - 3 1.6 MEASUREMENT AND PAYMENT FOR ROCK EXCAVATION A. Measurement: Excavation type in units of length shall be considered to change at the upper contact with a different
15、 excavation type as defined by section 1.5. B. Payment: Contract unit rates per length of each type of caisson shall be provided for each excavation condition type noted above in Section 1.5. Contract price and time will be adjusted for overruns or underruns in accordance with Articles, DIFFERING SI
16、TE CONDITIONS, CHANGES and CHANGES-SUPPLEMENT of the GENERAL CONDITIONS as applicable. C. Payment for Differing Site Conditions: No payment will be made for any rock excavation beyond caisson limits unless additional excavation is directed by the Resident Engineer. When rock excavation, as classifie
17、d, is encountered, contract price and time will be adjusted in accordance with Articles, DIFFERING SITE CONDITIONS, CHANGES and CHANGES-SUPPLEMENT of the GENERAL CONDITIONS as applicable. SPEC WRITER NOTE: Obtain following allowable tolerances from Structural Engineer. 1.7 TOLERANCES Install caisson
18、s with not more than the lesser of 1/24th of caisson shaft diameter or 75 mm (3 inches) from design center location. Caissons shall not be out of plumb more than 25 mm (1 inch) in 3000 mm (10 feet) for the full depth. 1.8 SUBMITTALS A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODU
19、CT DATA, AND SAMPLES. B. Before beginning work, submit a detailed location plan and description of the proposed method of caisson installation, all of which shall be subject to the review and approval of the Resident Engineer. C. Shop Drawings shall comply with ACI 315 “Manual of Standard Practice f
20、or Detailing Reinforced Concrete Structures“. Furnish shop drawings prepared by a Professional Engineer licensed in the State of the project for the detailing, fabricating, bending, and placing of concrete reinforcement. D. /Submit a detailed plan showing load test arrangement, location, and Contrac
21、tors qualifications and results for review and approval by the Resident Engineer./ E. Reports: Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-10-06M 31 63 26 - 4 1. Caisson record: Data as specified. 2. Rock excavation: Data as specified. 3. Soil Te
22、sting Agency Reports shall be issued showing material type and allowable bearing capacity at bottom of shaft within 24 hours after testing/observing each caisson. 4. Certified, “Caisson Field Record“ for each caisson recording actual elevation of bottom, elevation of rock (if applicable), final cent
23、erline location of top, variation of shaft from plumb, bell dimension (if applicable), result of all tests and observations performed, material type and actual allowable bearing capacity of bottom, depth of socket into rock, levelness of bottom, seepage of water, still water level (if allowed to flo
24、od), elevation (top and bottom) of lining left in place, variation of shaft diameter (from those shown), and evidence of seams, voids or channels below bottom. 1.9 APPLICABLE PUBLICATIONS A. Publications listed below form a part of this specification to extent referenced. Publications are referenced
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- VA3163262006DRILLEDCAISSONSPDF