1、Lessons Learned Entry: 1519Lesson Info:a71 Lesson Number: 1519a71 Lesson Date: 2004-11-29a71 Submitting Organization: JPLa71 Submitted by: Neil Toy / Steve SpohnSubject: Procure an Adequate Mission Operations Server (2004) Abstract: Because the Operations Storage Server was procured and installed ve
2、ry late in Phase D and featured unreliable, non-integrated hardware that could not reliably provide the dataflow performance required for critical MER mission operations, it posed a mission risk and had to be replaced just prior to EDL. Procure an integrated, expandable suite of server hardware that
3、 fully meets mission data throughput and reliability requirements, install the system at least nine months prior to its first planned operational use, and avoid subsequent major MOS/GDS IT infrastructure changes.Description of Driving Event: An Operations Storage Server (OSS) capable of supporting b
4、oth Mars Exploration Rover missions (MER-A and MER-B) was implemented, but only after early server hardware failures that necessitated major re-planning. In 2002, during Phase C (Design & Build) of the MER project, plans were proposed to acquire a high performance, centralized, project server to rap
5、idly process the high volumes of science data expected of the Ground Data System (GDS) during operations on the Martian surface. The Mission Operations System (MOS) funding in Phase D (integration & test), however, was inadequate to support full implementation of the recommended OSS system. The less
6、 expensive OSS that was deployed experienced repeated failures during pre-launch test, post-launch test, and launch/cruise operations. This included major server hardware failures lasting for days that occurred only weeks prior to MER-A launch in June 2003, and several weeks prior to Entry, Descent,
7、 and Landing (EDL) activities in January 2004. Contributing issues included:a71 Late procurement of a server system comprised of low-end, poorly integrated hardware incapable of meeting mission requirements for speed and reliability.a71 OSS design engineering involvement in the OSS was significantly
8、 reduced (from 1.5 FTE to 0.25 FTE) prior to final OSS implementation.Provided by IHSNot for ResaleNo reproduction or networking permitted without license from IHS-,-,-a71 Very limited testing prior to operational use because the original OSS was not installed until late in system integration and te
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- REGNASALLIS15192004LESSONSLEARNEDPROCUREANADEQUATEMISSIONOPERATIONSSERVER2004PDF

链接地址:http://www.mydoc123.com/p-1019157.html