1、Designation: D 6092 97 (Reapproved 2003)Standard Practice forSpecifying Standard Sizes of Stone for Erosion Control1This standard is issued under the fixed designation D 6092; the number immediately following the designation indicates the year oforiginal adoption or, in the case of revision, the yea
2、r of last revision. A number in parentheses indicates the year of last reapproval. Asuperscript epsilon (e) indicates an editorial change since the last revision or reapproval.1. Scope1.1 This practice covers size designations and maximumranges in mass or gradation for standard sizes for riprap, spa
3、lls,or bedding, or both, used for slope protection of dam embank-ments, streambank erosion control, bridge piers and abutments.Sizes used for outer harbor structures such as breakwalls,revetments, confined diked disposal structures (heretoforedescribed as armor stone, cover stone, or dimension stone
4、) forwhich stone sizes range between 5 and 25 tons, or that requirecut dimensions for layed-up structures are beyond the scope ofthis practice.1.2 The values stated in inch-pound units are to be regardedas the standard. The SI units given in parentheses are forinformation only.1.3 This standard does
5、 not purport to address all of thesafety concerns, if any, associated with its use. It is theresponsibility of the user of this standard to establish appro-priate safety and health practices and determine the applica-bility of regulatory limitations prior to use.1.4 This practice offers an organized
6、 collection of informa-tion or a series of options and does not recommend a specificcourse of action. This document cannot replace education orexperience and should be used in conjunction with professionaljudgment. Not all aspects of this practice may be applicable inall circumstances. This ASTM sta
7、ndard is not intended torepresent or replace the standard of care by which theadequacy of a given professional service must be judged, norshould this document be applied without consideration of aprojects many unique aspects. The word “Standard” in thetitle of this document means only that the docum
8、ent has beenapproved through the ASTM consensus process.2. Referenced Documents2.1 ASTM Standards:D 653 Terminology Relating to Soil, Rock, and ContainedFluids2D 4992 Practice for Evaluation of Rock to be Used forErosion Control2D 5519 Test Method for Particle Size Analysis of Naturaland Manmade Rip
9、rap Materials23. Terminology3.1 Definitions: Definitions of other terms in this guide arelisted in Terminology D 653.3.2 Definitions of Terms Specific to This Standard:3.2.1 filter/bedding stonestone, filter stone consisting ofcrushed stone ranging in size from34 in. (19 mm) to number 40sieve size,
10、and bedding stone (often referred to as “spalls”)consisting of crushed stone ranging in size from 6 in. (152 mm)(maximum) to12 in. (12.7 mm) minimum. Filter and beddingmay be placed in two layers beneath the riprap, that is, a filterlayer 8 to 10 in. (203 to 254 mm) thick and a bedding thicknessof 6
11、 to 8 in. (152 to 203 mm).3.2.2 geotextilessuitable geotextile fabrics that meet thedesign requirements may be used instead of the above beddingand spalls. Suitable cover thickness maybe required.3.2.3 gradationthe proportions by mass of stones distrib-uted within specified ranges between maximum an
12、d minimumlimits.3.2.4 riprapstone materials generally less than two tonsin weight, specially selected and graded, and when properlyplaced prevents erosion through minor wave action, or strongcurrents and thereby preserves the shape of a surface, slope, orthe underlying structure.3.2.5 standard size
13、designationone of a group of stoneswith specified gradation limits.4. Summary of Practice4.1 The design team shall establish the size of the mass ofgraded quarry stone using acceptable design criteria. If designcriteria and economic factors permit, standard gradationsshown in the designated tables s
14、hould be selected. Usingstandard sizes, the design team shall select the appropriategradation; this might require the next larger size therebycreating an over-designed structure, but economically, acheaper structure. Added cost may result due to the increasedvolume of stone required, and in transpor
15、ting and placing theadditional stone at the project site. The cost effectiveness of1This practice is under the jurisdiction of ASTM Committee D18 on Soil andRock and is the direct responsibility of Subcommittee D18.17 on Rock for ErosionControl.Current edition approved March 10, 1997. Published May
16、1997.2Annual Book of ASTM Standards, Vol 04.08.1Copyright ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959, United States.using “standard grading” versus “non-standard gradings” al-ways should be evaluated, and standard gradations usedwhenever possible.5. Sign
17、ificance and Use5.1 The standard size designations listed in this practice areprovided so that the design team, consumer, and the producerhave a common reference in sizing stone materials used inerosion control. The design team should perform a materialssurvey, and subsequent testing to determine wh
18、ich quarrysources may have suitable in-place rock and perform suitableblasting and processing procedures to produce the requiredgradations. The design team must recognize the fact that not allsources are capable or willing to produce the required grada-tions. Only those sources listed by the design
19、team should beconsidered for construction of the project.5.2 The standard size designations provided in this guide aresuitable for protective surfacing and structures designed forerosion control. These sizes are for typical structures such asjetties, revetments, groin baffles, bulkheads, lining ford
20、rainage/irrigation ditches and for intake or outlet facilities,bridges and stream channel banks, gabions, and slope protec-tion for earth embankment and rock-fill dams.5.3 The design selection of stone sizes, durability, place-ment, filter/bedding materials, or geotextiles, steepness ofslopes for pl
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
5000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASTMD609219972003STANDARDPRACTICEFORSPECIFYINGSTANDARDSIZESOFSTONEFOREROSIONCONTROL 冲刷 控制 石材 特定 标准 尺寸

链接地址:http://www.mydoc123.com/p-521512.html