ASTM D4537-2012 Standard Guide for Establishing Procedures to Qualify and Certify Personnel Performing Coating and Lining Work Inspection in Nuclear Facilities 《制定核设施覆层和衬砌工作检验人员资格考.pdf
《ASTM D4537-2012 Standard Guide for Establishing Procedures to Qualify and Certify Personnel Performing Coating and Lining Work Inspection in Nuclear Facilities 《制定核设施覆层和衬砌工作检验人员资格考.pdf》由会员分享,可在线阅读,更多相关《ASTM D4537-2012 Standard Guide for Establishing Procedures to Qualify and Certify Personnel Performing Coating and Lining Work Inspection in Nuclear Facilities 《制定核设施覆层和衬砌工作检验人员资格考.pdf(7页珍藏版)》请在麦多课文档分享上搜索。
1、Designation: D4537 12Standard Guide forEstablishing Procedures to Qualify and Certify PersonnelPerforming Coating and Lining Work Inspection in NuclearFacilities1This standard is issued under the fixed designation D4537; the number immediately following the designation indicates the year oforiginal
2、adoption or, in the case of revision, the year of last revision. A number in parentheses indicates the year of last reapproval. Asuperscript epsilon () indicates an editorial change since the last revision or reapproval.1. Scope1.1 This guide delineates the requirements for developmentof procedures
3、for the qualification and certification of person-nel who perform inspection of coating and lining work.Establishment of qualification requirements to verify confor-mance to specified requirements for nuclear facility coatingand lining work is necessary to assure satisfactory performanceof the inspe
4、ctions and to avoid compromising safety-relatedcoating systems.1.2 The intent of this guide is to provide a uniform inter-pretation of the requirements in ANSI/ASME N45.2.6 orANSI/ASME NQA-1 as applicable, for the inspection ofcoating and lining work in nuclear facilities.1.3 It is the intent of thi
5、s guide to provide a recommendedbasis for qualification and certification, not to mandate asingular basis for all qualifications. Variations or simplifica-tions of the qualifications described in this guide may beappropriate for special coating and lining work other thansafety-related coating and li
6、ning systems. Similarly, the quali-fication and certification process might be abbreviated for workof minor scope such as touch-up.1.4 This standard does not purport to address all of thesafety concerns, if any, associated with its use. It is theresponsibility of whoever uses this standard to consul
7、t andestablish appropriate safety and health practices and deter-mine the applicability of regulatory limitations prior to use.2. Referenced Documents2.1 ASTM Standards:2D4538 Terminology Relating to Protective Coating andLining Work for Power Generation FacilitiesD5144 Guide for Use of Protective C
8、oating Standards inNuclear Power PlantsD5498 Guide for Developing a Training Program for Per-sonnel Performing Coating Work Inspection for NuclearFacilities2.2 ANSI/ASME Standards:3ANSI/ASME N45.2.6 Qualifications of Inspection, Exami-nation, and Testing Personnel for Nuclear Power PlantsANSI/ASME N
9、QA-1 Quality Assurance Program Require-ments for Nuclear Facilities3. Terminology3.1 DefinitionsDefinitions for use with this standard areshown in Terminology D4538 or other applicable standards.3.2 Definitions of Terms Specific to This Standard:3.2.1 certification, nwritten documentation of qualifi
10、ca-tion.3.2.2 coating and lining work inspection, na phase ofquality control that, by means of examination, observation, ormeasurement, determines the conformance of safety-relatedcoating or lining system applications to predetermined qualityrequirements. The term inspection as used in this standard
11、 shallbe understood to mean coating and lining work inspection.3.2.3 Level I, II, and III inspection, nindicative of thetime in grade classification for personnel who perform coatingand lining work inspection. Each level reflects progressiveexperience and responsibility. This term is separate from a
12、nddiffers distinctly from Coating Service Levels. The latter termreflects differing locations throughout a nuclear plant wheresafety-related and other coatings are found. (See Terminologysection of Guide D5144 for definitions of Coating ServiceLevels I, II, and III.)3.2.4 personnel performing coatin
13、g work inspection,nindividuals whose job functions include but are not neces-sarily limited to coating and lining work inspection.3.2.5 qualifications, nskills, training, and experience re-quired for personnel to perform properly the duties and executethe responsibilities of the appropriate certific
14、ation level.1This guide is under the jurisdiction of ASTM Committee D33 on ProtectiveCoating and Lining Work for Power Generation Facilities and is the directresponsibility of Subcommittee D33.04 on Quality Systems and Inspection.Current edition approved March 1, 2012. Published March 2012. Original
15、lyapproved in 1986. Last previous edition approved in 2004 as D4537 04a. DOI:10.1520/D4537-12.2For referenced ASTM standards, visit the ASTM website, www.astm.org, orcontact ASTM Customer Service at serviceastm.org. For Annual Book of ASTMStandards volume information, refer to the standards Document
16、 Summary page onthe ASTM website.3Available from American National Standards Institute (ANSI), 25 W. 43rd St.,4th Floor, New York, NY 10036, http:/www.ansi.org.1Copyright ASTM International, 100 Barr Harbor Drive, PO Box C700, West Conshohocken, PA 19428-2959, United States.3.2.6 safety-related coat
17、ing or lining system, na coatingor lining system used inside or outside of the reactor contain-ment, the detachment of which could adversely affect thesafety function of safety-related structures, systems, or com-ponents (SSC).3.2.7 training, nthe program developed to ensure thatpersonnel receive th
18、e knowledge and skills necessary forqualification.4. Significance and Use4.1 The requirements of this guide apply to personnel whoperform coating and lining work inspection during (1) fabri-cation, (2) receipt of items at the construction site, (3)construction, (4) pre-operational and startup testin
19、g, and (5)operational phases of nuclear facilities.4.2 It is the responsibility of each organization participatingin the project to ensure that only those personnel within theirrespective organizations who meet the requirements of thisguide are permitted to perform coating and lining workinspection
20、activities covered by this guide.4.3 The organization(s) responsible for establishing theapplicable requirements for activities covered by this guideshall be identified, and the scope of their responsibility shall bedocumented. Delegation of this responsibility to other qualifiedorganizations is per
21、mitted and shall be documented.4.4 It is the responsibility of the organization performingthese activities to specify the detailed methods and proceduresfor meeting the requirements of this guide, unless thosemethods and procedures are otherwise specified in the contractdocuments.4.5 In the event of
22、 conflict, users of this guide mustrecognize that the licensees plant-specific quality assuranceprogram and licensing commitments shall prevail with respectto the process of qualifying personnel performing inspection ofcoating and lining work.5. General Requirements5.1 Provisions shall be made for t
23、he indoctrination ofpersonnel performing coating and lining work inspection as tothe technical objectives of the project, the codes and standardsthat are to be used, and the quality assurance elements that areto be employed.5.2 The need for and content of formal training programsshall be determined,
24、 and such training activities shall beconducted as required to qualify personnel who performcoating and lining work inspection. The extent of on-the-jobparticipation (“time in grade”) also shall be addressed in theprogram, with emphasis on first-hand experience gainedthrough actual performance of in
- 1.请仔细阅读文档,确保文档完整性,对于不预览、不比对内容而直接下载带来的问题本站不予受理。
- 2.下载的文档,不会出现我们的网址水印。
- 3、该文档所得收入(下载+内容+预览)归上传者、原创作者;如果您是本文档原作者,请点此认领!既往收益都归您。
下载文档到电脑,查找使用更方便
10000 积分 0人已下载
下载 | 加入VIP,交流精品资源 |
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- ASTMD45372012STANDARDGUIDEFORESTABLISHINGPROCEDURESTOQUALIFYANDCERTIFYPERSONNELPERFORMINGCOATINGANDLININGWORKINSPECTIONINNUCLEARFACILITIES

链接地址:http://www.mydoc123.com/p-517318.html